Board: Fire Station Building Committee

Date: 2026-01-20


Transcript

Auto-generated; may contain errors.

Speaker 1 (00:22–01:31)

I see we have a quorum, so I'm going to call the meeting to order. Where are your socks? You're making me cold. This is the full Biosection Building Committee meeting.

On the full committee, you knew that the Atherton subcommittee was meeting earlier. We started late. We ran late. We spent a lot of time reviewing Brian Who is walking through a 6 options?

We did not reach a point. So we're going to turn around and tell you what we think. The 6 of the 6 options, which ones we should move forward with. But there have been of the 6 options, there are members sitting here from the street subcommittee.

That would have recommended 3 of them. Okay, so my suggestion is, and I'd like to, one at a time, have those people recommend their option, take a vote, have a full committee kind of review them, let's walk through all three, and then look to vote what the best options. Does that sound reasonable?

Speaker 2 (01:31–01:38)

But Brad, I think we should make note that we had a good crowd here. Yes. Supportive of what we're doing, I think.

Speaker 1 (01:39–04:37)

Yeah, they supported it. So just for the full committee, which was great, we had the chair of the Warren Committee. I spent some time with him in between meetings. Although interesting, he made it clear as a bell to me that regardless of what option we go with, if we need to really sell that, he said, he thinks the Warren Committee wants the answers to two questions.

Do we really need to do anything with Athens Street? If we do, do it now, or can we wait 10 years? So it kind of frames for me the importance of when we make an option, properly packaging and selling it. Because the Wall Street is the first group we've got to get through.

And by the way, I appreciate his honesty and integrity. He's got a lot of members of that committee were not there during any of the discussions when we first got the approval to go ahead with these fire stations. So it's really probably not surprising that they would ask that. And by the way, why are they asking that?

No surprise to Nick. He said because they are looking at all the funding coming up, especially a brand new school. And if they had the druthers, they wouldn't want another $15, $16 million project on the planet. All right, so fair enough.

But we had other members here. We had members of the Milton's Historic Commission, the chair. We had members of the Community Preservation Committee. They made a strong commitment to us, and I worked with the members that were here at the table, that, come on, get to us soon, because we'd like to provide you funding for this.

We recognize that when that act passed, a lot of the sales pitch to the community was to work at the fire stations. He's saying Atherton Street, but that's We went too quickly on the central. But anyway, and he mentioned that what they've done during the fifth year, what they did for four years was they said, look, we've got about a million bucks, and we're going to recommend three expenditures. One on our storage stuff, and I don't know the guidelines, but of the million dollars.

However, this last year, for the first time, and they're coming into town meeting, coming up, they're recommending spending more than their million, they're going to finance it. And so what they would be doing is, I don't know the numbers, they say it's a $4 million project, we're gonna finance that over 10 years, I'm making these numbers up. And so we're gonna commit community preservation funds for the next 10 years of X dollars a year. So they're doing that and hint, hint, they would expect us to keep that in mind and come in.

I mean, honestly, it sounded like if we went in and asked for 2 million, that they would be very receptive.

Speaker 2 (04:37–04:43)

Yeah, because we had mentioned that a million is a goal, and he encouraged us to increase that.

Speaker 1 (04:43–04:57)

Right. Exactly right. So that's all good news. All right, so Ellen has Oh, and I have, by the way, there was no other, yeah, go ahead.

Speaker 3 (04:58–05:00)

Brian, do you have copies of the handouts?

Speaker 4 (05:00–05:07)

Oh, I did. They might've been burned off, but it's okay.

Speaker 1 (05:08–05:32)

I have them to share though, too, up on the screen, Mark, if that's… I'll let you take mine if you like. So of the six options, Ellen was comfortable with option two or three, or two, then three.

Speaker 2 (05:32–05:44)

Two or three. And I say three because of the spare engine that the Jeep is keeps mentioning, and it seems like it's the right thing, and it needs to go into a garage.

Speaker 1 (05:45–06:08)

And LeRoy is supportive of option 5B on this call, on this sheet. I think it's always money's important in all these. Option 2 is a $15.1 million option. 3 is a $16.1 million option.

And 5B is an $18.6 million option.

Speaker 5 (06:09–06:16)

Now- Excuse me, this is Philippe. Are you guys sharing something on the screen or- Oh, one moment.

Speaker 1 (06:18–06:36)

Yeah, we will be in a second, Philippe. Thank you for the heads up. That's what we talked about, these options here. Thank you.

Alan, would you prefer Brian to go through option 2 and 3? Or would you like to?

Speaker 4 (06:36–09:39)

I think just for the members that weren't part of the subcommittee, I know that we kind of broached the subject and we gave some draft of this at our previous meeting. We've broken it into 6 options as we see it. Options 1, 2, and 3 are continuing with the design as we see it right here with the renovation of the existing structure. and adding with option one being the original design with the single bay on the side of the existing structure, option two has two bays, option three has three bays.

all of which would come with different variables. But I think what's most important to say is that as we were charged with the objectives of how Chief sees the apparatus being stored there, that options one and two, definitely number one and possibly number two, do not fit the current needs of the apparatus and storage needs that he will need at this facility. Option 4 is the full structural renovation and bringing the facility up to seismic code in discussions with the structural engineer and with context that will more than likely result in complete demolition of the 2nd floor, trying to raise that floor. but also not really addressing the width of the existing bays that we have here.

So there are some additional costs that we see for design. We see some definite added costs for construction, as well as potentially a longer construction period in order to get that seismic upgrade completed. Option 5 and Option 5B deal with the construction of a separate facility in the rear of the property. Option 5 leaves the existing facility alone.

Option 5B would include the renovation of the existing facility with that. Both of those do have their own, all their own variables as well, inclusive of added design costs. a longer construction period for the renovation portion. And then ultimately option six is the demolition of the existing structure as we see it, fully abated and demoed with a new facility built in the same location to afford chief and the staff in order to dispatch out onto Blue Hill Ave.

That obviously would come with added construction costs, added abatement, but also a longer construction timeframe for that last option there. So this has kind of been boiled down from the past two to three months. to establish the programming, establish the needs of not only now, but how Chief sees the operations in the future, take into consideration what has been designed already, and then also kind of spread out what we have for all of these different options here at this location.

Speaker 1 (09:41–10:23)

One important thing I think to add, of the active residents that came, participated in our meeting, all of them, and I went down purposely because the meeting was breaking, and told them to make sure that I read them correctly, all of them would prefer any solution that involves saving at least some of that to the current Athens Institute station. Or translated, none of them wanted us to demolish that station. I just wanted you to know that. So that was important.

And by the way, we have a member of the planning board, We had a member of the Historic Commission, we had two members of the Community Preservation. In the Select Board, thank you.

Speaker 4 (10:23–11:02)

So, 1 comment on here, if you look at the estimated total project budget of each of these options, this does not reflect any money that would be helped out from the CPC on here. And so you've seen numbers that were talked about a 1Million dollars, potentially upwards to 2Million dollars. Those are not reflected in that number. And you can scroll down to the bottom where you can see, would there be potential CPC funding with those options?

There would be a no, if we demolish the building. Obviously, we also have it as a no for option 5, if we were to construct a new facility out back and not touch the existing facility.

Speaker 1 (11:02–11:11)

But as importantly, the three options that we're gonna consider here as part of the full committee, all would, they're all yes for community preservation.

Speaker 2 (11:11–11:20)

But I don't understand how 5B is, because if we don't, if it's not, if the program isn't needed, why would we touch that building?

Speaker 1 (11:20–11:31)

Because 5B says three bays plus renovation of the existing building to use, we're gonna use bays at the existing building.

Speaker 2 (11:31–11:33)

I don't think that is the plan. That's not the plan.

Speaker 1 (11:33–11:34)

That's not the plan.

Speaker 6 (11:34–12:14)

Am I breaking that law? subcommittee as not being in favor of 5B. Actually, he was not in favor of 5. He was not in favor of 5, which is leaving the existing structure alone.

He did not say he was not in favor of 5B, which actually has to for the existing structure. Chief, do you want to talk about how we might use the programming?

Speaker 7 (12:14–17:04)

It's the same programming that we discussed earlier and we've discussed a couple of times. When you look at the operations of the fire department. We're quickly running out of room. We talked about adding the second bay down in East Milton.

That is for a spare engine. We're soon to receive a new ladder truck. We're going to keep maintaining the current ladder truck that we have as a spare. And I say spares, they're actually backups, right?

So they're backups. So when a piece of apparatus goes out, and I just want to make sure everybody else that wasn't in the subcommittee understands. So when a piece of apparatus goes out of service, we have to have another piece ready to go in service at a moment's notice. And then for any kind of maintenance or scheduled maintenance or anything, the big trucks, they require a lot of maintenance.

When they go out of service, they go out of service for a considerable amount of time. The talking with the mechanic, the mechanic has requested that we eat. 2 spare 2 backup and a backup line. So that's where we kind of run into the issue.

The backup ladder will go here. 1 of the spare engines will go down and engine 2. that's where that 2nd bay is. So then we have that option that that 3rd.

Spare for the backup engine 2nd, 1 and. we need a place for that. And then the other thing is that, you know, when you look at the programming and, you know, some of the things that we look at, and I probably explained it better the first time, when you look at the fire department and look at where our issues are and moving forward, you know, from where we were to where we are, you know, a lot of things that we did and how we operated were dictated because of the spaces that we had when we didn't have a lot of space. So now where we do have some space with the operational needs, they're kind of changed.

So, you know, having the brush truck and the Kubota here in the boat here makes the centrally located piece of equipment that can get out and get, you know, quick water on a brush fire or the boat in the water or the Kubota into the Blue Hills up by Chickasawbit or down by the DuPont River or up by, you know, the ski slope. So having that stuff located, that equipment centrally located is important for operational needs. So I know that the previous Programming had all that equipment up Engine 4, but it makes a lot more sense. And, you know, the way that we operate now, we're able to get that equipment where it's needed a lot quicker and a lot more efficiently.

The other thing that we have, and we looked at, you know, where are we? in the fire department, you know, from where we were to where we are to where we're going. Some of the immediate needs, we found that with the brush fire season, we were woefully equipped to put fast water on a fire. Well, actually we had fast water fire on the fire with our small brush truck that carries 200 gallons.

But once you go in there, You work your way in, and then all of a sudden you use 200 gallons. And if it's an acre of fire, that 200 gallons doesn't do anything to it. So a quick moving fire, it just travels. And the one that we had last November, it ballooned from a quarter of an acre to 15 acres within a half hour and an hour.

And it literally chased myself and the DCFRs, Ranger, up the hill. So if we had more water at the time, so that's what we're looking at. you know, how do we get more water in there? And they have the deep tankers, there's some tankers around Norfolk County.

And one of the pieces of equipment that I would love to look for, you know, possibly through a grant would be a thousand gallon or 2000 gallon tanker. We had to go to Canton, Sharon, Foxborough, Dover, Norfolk for that equipment to get that water into the fire. And so you're requiring on our mutual aid partners to get enough water into the fire. And I don't, everything says that that these forest fires aren't going away.

They're here to stay. So that's a challenge that we have now. And we have that urban wildland interface. It's difficult.

We have a lot of buildings. Fortunately, we were able to save the $1.4 million into that horse farm up by the state police barracks. And we were able to, if you look to where that fire stops, it's right on that trail just on the outside of it. So we're able to stop that.

But if we weren't able to stop that, you know, you look at buildings or, you know, you look at stuff that happens, you know, out west where we haven't lost the structure yet. I think, you know, we're pretty good. I think the firefighters that we have here and our mutual aid system is pretty good. But quick water and substantial water on the fire is an important need for the fire service now for us.

Speaker 2 (17:04–17:06)

And that's part of the program.

Speaker 3 (17:06–17:14)

That's part of 5B? It's backfill space for the future, correct?

Speaker 2 (17:15–17:20)

Of 3, 4, 5, 5B and 6. It's part of from 3 up.

Speaker 1 (17:21–17:30)

All right. Yes, all of that encompasses. Yeah. But the proposals that we're going to consider here now are 2, 3, and 5B.

Right.

Speaker 3 (17:30–17:41)

So 5B has money in it. in that budget to rent, to support the new program.

Speaker 2 (17:41–17:53)

Correct. Option three and four and five do as well, John. Oh, they do. Yes, yes.

And I'm sorry, you should have one of these breakouts because it's really difficult to read it on here.

Speaker 6 (17:54–18:25)

You know, the two things five does is it avoids the cost of raising the construction cost of raising the floor in the existing structure. avoids the cost of temporary operations, which is about 1.5. Because with a phased construction schedule, you can use the existing structure to house firefighting as well. And you end up with a new East Milton design.

Speaker 2 (18:27–18:43)

One question I have, the square footage for most of these around the same, between 14, 16, 12, And 5B is 22. So that sounds like we're just adding the Appleton station.

Speaker 4 (18:43–19:03)

At this point, I did, because not knowing what we have for that programming, whether we were going to steal from some administrative space and repurpose it in the existing structure, I made it a simply what we have currently as the asset and what the square footage is added on to option three, ultimately.

Speaker 2 (19:04–19:45)

Because I was the one who was proposing two or three. I will take two off the table, because it's not hitting the program. It's not getting that spare vehicle that the department needs. But what it does do, it hits the requirement for the program.

It can get at least $1 million, if not more, in CPC funding. And it's $16.1 million. So you're saying rather than two and threes, because it reuses the reincorporates the existing building into a new fire station.

Speaker 4 (19:45–20:05)

Can I just ask Jeff from context or Sean to speak up just regarding the constraints of the property itself and some of the discussions you've had about. three bays and how that would be configured on a site plan such as this, whether it's using existing facility or a new facility with three bays outside of where it currently stands.

Speaker 8 (20:06–22:47)

Sure. I can talk about this, Sean, if you don't mind. Originally, the design for this property had essentially option one, which had one additional bay added to the two existing. That is fairly close to the property line abutting Bradley road.

Now, there's a bit of a setback from the actual road to the property line. And, of course, the town owns both the road and the property line. So, there may be some considerations there from a planning perspective. Placing a second bay next to the current design's one bay, so you're talking about option two with two new bays, that second bay would have to be stepped back from the face of the current single bay that's there.

So you'd have this stepping effect on the facade. But most importantly, because the grade drops off, we'd be dealing with additional construction costs to support that. elevation of that first floor level above the existing grade there. In particular, the engines or whatever vehicles are coming out adjacent to Bradley Road would have a much more acute angle that they're entering the road from.

It may be possible to do that. I've looked at it and I think it's possible to construct it there. It may not be the best design and it may not be the best operationally, but I think it's feasible. Now, adding a third bay, new bay, so option three, to add three new bays, it just does not seem possible to add that in a series next to two bays that would be there because we'd be encroaching so far over the property line, which would be problematic on the face of it.

And we'd have additional issues with the grade and even more problems with vehicles entering onto Bradley road. I think. it probably is sort of a non-starter. So I think a third bay, if it was new, would have to go in the rear of the station.

We'd have to redesign it so that there would be a third bay or maybe two bays in the back that would exit onto Bradley Road, but more from the back of the building, kind of around to Bradley Road, and they would hit Bradley Road in a perpendicular manner. But they would be detached from The current design, there would be 2, basically 2 rear bays, which would allow you to house apparatus there.

Speaker 5 (22:48–23:19)

So, as of the, yeah, what kind of apparatus would be there in the, in the, like, the 3rd bay? Is it just the, like, the boat and, like, a pickup or something? Or it's a full fire truck? Like, are we talking 3 fire trucks?

Or 2 fire trucks and something else? Like. Yeah, a boat or a boat and the sea do and something much smaller that does not require the same kind of.

Speaker 8 (23:19–25:12)

Yes, so the way the chief has laid it out in the operations assessment that he has done, um, and the subcommittee has been working with in terms of what meets the program or not, essentially, it's going to remain a single engine company station house. So there will be 1 engine responding from here, which will be in that most immediate adjacent Bay to the existing building. Anything else that's located in the additional base would be reserve and spare apparatus or auxiliary special pieces like, um. Like a brush truck and other aspects like that.

Uh, at least in terms of the current operational plan, I can't speak to what a future chief might do now. Um, but the expectation would be, you know, it'd be designed for, um, similar to how station, uh, the East station is designed for one engine company to be housed there and respond with one engine. So, uh, the, the vehicles in these other two bays would be, um, additional to that engine. I just, I also want to point out that in a new scenario, if we're doing options.

5 or 5 B, or option 6, a new building would be cited in the rear of the lot and it would face onto Bradley road and there we have done some initial. study just to determine would it fit and it would fit down there without having to remove the existing building there's there's room for them to both coexist although it's not ideal there it's a little tight um it can all fit there and uh the apparatus which is exit out onto bradley road directly and perpendicularly rather than um coming out onto The intersection, which it doesn't have if I go, this is this is Brian.

Speaker 1 (25:13–25:32)

So you're mentioning those, those, uh, the 3 days facing out onto Bradley role from behind with the states plan. And they, whatever future number of years. Closing Bradley road, would it make more sense for us to think about the design and have a face out to Athens and street?

Speaker 8 (25:33–26:56)

Well, you're getting into a whole other aspect of this, which is the interaction with the mass DOT potential changes to the intersection. And I think there's, as Brian's noted in his chart here under options five and six, I think there's, oh sorry, five and five B. I think there's major implications to the MassDOT plans if we were to site a fire station in the rear of the lot, whether it exited onto Atherton or Bradley, it would majorly complicate what MassDOT wants to do. And as we've discussed in this committee, MassDOT is awaiting the decisions that the town is going to make and has stated to us in other conversations in meetings that we've had with them.

That they would abide by whatever decision the town makes, and that would potentially change the mass do t plans for the intersection and they would just go to work on how this new fire station sighting would. adjust their plans. I think that if we were to face the station toward Atherton Street or Bradley, either way, there's no way for them to do a connector that cuts through the lot any further. So it doesn't really matter at that point which way we face it.

It would just be up to our own preferences. And I think Bradley Road being a larger road and a little bit more robust, I think, would probably be the preference. But that's up to the chief.

Speaker 5 (26:58–27:03)

I'm hearing you correctly. They're waiting for our design to finalize their design.

Speaker 8 (27:04–27:19)

Yes, they've told us that they would be waiting to understand which direction the town would move forward. And I'm not certain that they literally be waiting for us to finalize the design, but they want to know which way we're going. Yeah. Keeping the existing.

Speaker 9 (27:20–27:30)

Yeah. So an option 3, he added days in the existing waste design. Well, that fit with the realties plan.

Speaker 4 (27:32–27:50)

Maybe. I think it's going to depend on the constraints that Jeff had just talked about, the stepping. If a bay needed to go out further back on where that was, the initial mass dot schematic that you saw was cutting right through the rear of that property. I don't think we know yet exactly where those lines are going to be.

Speaker 9 (27:50–27:59)

Just on the schematic, they got rid of basically that bottom line. Yeah. And that's a great difference too.

Speaker 1 (27:59–28:09)

So they're going to have to deal with it. and backed up, so. And Paul, on this chart of his, he addresses that. It has its own line, the fifth line up.

So maybe. Right.

Speaker 10 (28:10–28:47)

I would certainly let this committee dictate what's best for Milton, and then let MassDOT react to that. I think that was their message. It's worth a discussion point, but I wouldn't stress over that aspect of the site plan. Can I ask a question?

I just have two questions. So on 5B, the renovation of the existing building, what does renovation of the existing building mean? Does it mean the plan to renovate it as it would be in their options 1, 2, and 3?

Speaker 4 (28:48–28:49)

That's how I took it, yes.

Speaker 10 (28:50–29:04)

So then if we're doing a new build out back, so the East Milton design rebates, I mean, not duplicating living quarters, or duplicating a kitchen, or duplicating- That's the exact variable that had not been fleshed out yet.

Speaker 4 (29:04–29:15)

Whether or not there would be additional programming, or whether would we continue to keep the, we'll call it the housing quarters at the existing facility, and not need them, a structure out back.

Speaker 10 (29:16–29:20)

I think that's kind of important.

Speaker 2 (29:20–29:20)

Yes.

Speaker 11 (29:23–29:57)

I think the intent of 5B is that you have a standalone brand new fire station as if the existing building was no longer there and self-supported like a bigger East Milton, correct? However, you still have this with no physical connection to the front building. However, you still have the capacity in the front building in the existing two days for additional storage needs. So then you have your apparatus and the three new, but you then have however many square foot of the old living quarters that in theory are new in the building out back that you can decide if that makes sense to become a different program space.

Speaker 10 (29:57–30:00)

That program space wouldn't be the fire department.

Speaker 11 (30:00–30:02)

Well, that becomes a question.

Speaker 1 (30:02–30:34)

Well, I think Nick's basic challenge is a good one, which says, again, we're not probably as far along in our deep diving and all this as we'd like to be. But if we built any kind of a building that has three beautiful bays in the back for modern equipment, and we're going to use two bays of the existing station for some equipment, Why wouldn't we renovate and use those living quarters up there?

Speaker 3 (30:34–30:47)

No, you don't want to because you're going to provide an elevator, handicap access, little sprinklers for the building. It's a rabbit hole. You're not going to want to go down.

Speaker 1 (30:47–30:48)

I don't know about the elevator, by the way.

Speaker 3 (30:48–30:50)

Oh, I see.

Speaker 1 (30:50–30:53)

No, I don't think it's a requirement for like a sidewalk.

Speaker 3 (30:53–31:02)

If it's not open to the public, then you don't need it. No questions asked. It's all yours. Every last unit for the bill.

That's how I would interpret it.

Speaker 2 (31:03–31:18)

But I think, John, that my question to the square footage is that it's increasing the program. Right. So is that in that in what is the use, because we did it here. Now, hopefully at some point we get an elevator next door that we can use that space.

Speaker 1 (31:19–31:22)

Although that's not required for the public.

Speaker 2 (31:22–31:52)

No, no, for the public. If we said, OK, we've got a white box that we're going to pay to put sprinklers in and white box it and hold it for the future. But is there a program? We don't need a program to go in there, because if you do a new building, it's the same as the same square footage is bought.

It's 16,400. So it's just like, it seems to be we're tacking on S4 footage without the need, the program need.

Speaker 3 (31:53–31:55)

Oh, I think we heard that.

Speaker 10 (31:56–32:57)

And they program in stores speak, programming in building offices, living quarters, kitchen speak. So we have programming upstairs at Appleton. If we build a new building behind in a program, like living quarters, Now we have two sets of brand new, freshly renovated living quarters that we built. So do we just mothball the second floor of Appleton and not renovate it?

Which leads us to the same issue we have back here. Do we renovate it for some other use? Okay, what is the use? And what cost is that?

Is that actually captured in here accurately enough? Do we forego building new living quarters out back, which is again, just an iteration of option three, and then we're cutting back into option three. If we're renovating Atherton entirely, what is the second floor being used for? And that's scary.

If we're, especially when we're building an entirely new building in the back, I guess that's kind of the whole question I'm trying to get at. And I know we're completing programming and storage, but I'm talking more about the active like office, with more such spaces.

Speaker 2 (32:58–33:17)

You know, Brent, I know we are kind of out of time in terms of having a decision for Nick, but, and I fully support three. But if folks are thinking 5B is the way, should we do a quick study for both? I don't know.

Speaker 1 (33:19–33:21)

But when you say do a quick study for both.

Speaker 2 (33:21–33:23)

To see what works.

Speaker 1 (33:24–33:26)

And address what we do with the living space.

Speaker 2 (33:27–34:13)

Well, how do you do it? How do you actually, how do you do it? I mean, do you use part of the existing on 5B? the existing station and reduce the square footage of the proposed new.

So you're getting close back to the 16,000. I think the great difference is too great to make that, but that's just me being out there and I couldn't be wrong. But I just, I personally, as someone who lives in the town and I see old folks having to leave because they can't afford it. I would go with the, Option three, which is $2.5 million less.

But if folks want to explore both, I would support that.

Speaker 1 (34:14–34:36)

I guess I'd ask vertex and context. Is there any way if we put three-bay building in behind, and I know John has already made his position clear, that we could reuse that living quarters space in the old station? I know it's not part of this plan, but just the practical.

Speaker 11 (34:36–34:52)

Okay, programmatically, you're not going to want to have the building, the living quarters in a separate building from the apparatus floor. I mean, just. Yourself, you want to be self contained and even connecting them the distance that you would get great change wise. To the bay floors to the living quarters that I didn't know that's.

Practical.

Speaker 7 (34:52–35:38)

And Sharon Fire currently does that with a new firehouse. They have a firehouse and they have probably a 200 foot walkway to the administration office. And then you go into the police station, I think, maybe the DPW, and then probably about 300 yards down. there's another outhouse and they keep all their spare, they keep their brush truck, they keep their spare ambulance, they keep their spare boat down there, they keep their ski-doo or whatever it is.

That's a lot of equipment. Yeah, so when you look at it, it's just the operational, you know, the chief has a lot of problems with maintaining that equipment where you're supposed to watch it and take a look at it each and every day. make sure it's ready to go. It's a huge challenge where it's just not happening because the guys are a quarter mile away at a totally different building and it's just getting neglected.

Speaker 2 (35:38–35:42)

Are there living quarters where the trucks are though? Are they expected directly?

Speaker 10 (35:42–36:11)

Yes. Couldn't that be a solution if it's option one with a trimmed down storage facility in the rear that is, I don't know how conditioned that space needs to be, but if the purpose is storage, it's not a quarter of a mile away, for example, but it's 30 feet. So what kind of garage space does it need to be? And it's option one plus, you know, like I say, a trimmed down metal fabricated building.

Speaker 7 (36:17–36:26)

I believe that was talked about years ago, and I do kind of remember that, but I don't know where that went or why that went away or anything like that.

Speaker 10 (36:26–36:27)

I don't recall that.

Speaker 7 (36:27–36:45)

And this is when Sharon was getting built, and I know Chief Grant talked about a spare building out back, but if you do kind of connect it with that parking garage, it's that maybe if you do something like that, you know, I don't know why it went away. I have no idea.

Speaker 2 (36:45–36:52)

So you can put your spare and then your brush truck in a separate building?

Speaker 3 (36:52–37:14)

Conceivably, yes. A low-cost, pre-engineered metal building that was conditioned so the water doesn't freeze if you got the needed. And then you just abandon these. You remove entirely from the existing Atherton Street station and say community preservation preserve it.

Speaker 2 (37:15–37:26)

No, you'd still use the, it would be, I think you're saying use option one and then build this extra space out there. Terrific, and then what do you do with the old station? It gets reused, that's option one.

Speaker 3 (37:26–37:30)

Reused by whom? The fire department. I beg your pardon.

Speaker 2 (37:30–37:33)

But that was the original option.

Speaker 6 (37:33–37:41)

Option one, I thought we all agreed that three full-size bays was a prerequisite.

Speaker 10 (37:43–37:58)

standalone building is what I'm suggesting is a full-size standalone building with two full-size bays in the rear. The option one has design with one Full size Bay, that will be the dedicated active for that.

Speaker 2 (37:58–38:05)

That's because you can do those full size phase, build those 1st, then those can be the temporary orders.

Speaker 1 (38:06–38:14)

That's an interesting option building chief. What do you think of that? The 2 full size bays. A building right directly behind it.

Speaker 11 (38:14–38:35)

I mean, it's almost option three. Option three is keeping the one new bay to the right of the existing bays with two other bays somehow situated on that work. But if you just put a standalone building out back for your spare truck and the anchor or something that you need only in the summer or whatever it might be.

Speaker 2 (38:35–38:42)

To John's point, it's like off-the-shelf construction, pre-manufactured.

Speaker 1 (38:43–38:48)

Yeah, well, it could be. Yeah. Yeah, that's what we all desire.

Speaker 2 (38:48–38:56)

Yeah, no, but you could, it could be some cost savings there and still meeting the chief's requirement for the extra two days.

Speaker 7 (38:58–39:42)

It's something that I've thought about. And when I was in Sharon a few months ago, we saw as long as it's there and it's ready to go and it's close, it's not a quarter mile or 300 yards away or whatever, and that it's a building that will maintain. And I think the other part of it too, it's not just a metal Quonset hut. You know what I mean?

I don't think that the record is temporary. Right. Nobody would look, nobody would appreciate something like that. But if we did have direct connection or whether we connected or close enough where it was something that where the firefighters could get down there and easily and maintain the trucks and get in those trucks and have them available.

And that's something that

Speaker 2 (39:42–39:52)

And that can be built first, right? They can build that, then your operations move into that temporarily. So you're not paying for temporary accommodation.

Speaker 7 (39:52–39:54)

At least for the trucks.

Speaker 2 (39:54–40:04)

At least the personnel. And then we can get a nice trailer or something for the staff. Or something. We could accommodate it.

It would be less expensive.

Speaker 1 (40:05–40:15)

I mean, we clearly, all of these options, Almost all these options require temporary quantities, and what we're talking about now requires that.

Speaker 2 (40:15–40:37)

Yes, but Brian, what I'm saying is this two bays we're building out back, we're going to connect it to the existing Atherton station. That can be built first, and that can be the temporary location That can be the location for the trucks. You wouldn't have to house them anywhere else during construction.

Speaker 7 (40:38–40:56)

Can we ask Jeff? I know Jeff has probably the most history on this committee, and I'm not sure if it was Contax that designed it originally, or if it was the Space Needs Committee. I forget that company that did it. So I'm not sure if he has any history on that.

Speaker 9 (40:56–41:07)

It was a separate space building. It was basically a glorified space building out in the back of the property, which would be exiting to Bradley Road side.

Speaker 2 (41:13–41:21)

She granted proposed back in the day, and that was before our organized committee. I think that was the committee.

Speaker 6 (41:21–41:29)

So, I'm not sure if Jeff is really with it and Brian and Brian Richard Wells has had his memories. Oh.

Speaker 1 (41:30–41:39)

Richard, would you like to I give up? I give up. Well, you know, Richard in person, you have a big hand, but on the screen, it's really kind of small.

Speaker 12 (41:39–42:31)

So I'll be brief, three things. So the point you're talking about right now, I think I might actually still have a picture of that, going back to when Chief Grant, that was the beginning of your committee, Brian, when the, that separate building that sat behind. So I'll look and see if I have, I do recall that. So just two points.

One is from my, Senator Driscoll and I both are of the opinion with MassDOT, and I'm very strong on this, I don't want to see them do anything until this station is at least either under construction or finished. and then let them go from there and figure out, because the last thing you want them to do is interrupt the public safety operations of this facility. And that, to me, is first and foremost.

Speaker 1 (42:32–42:34)

And Richard, they've made that commitment to us.

Speaker 12 (42:34–42:59)

They have to us as well. They've been very good to at least my staff. They've been they've been very good to our office. So I'm OK with that.

Second thing. And you know this, Brian, like, look, we saw and I know you were talking about this when I was first. How are you coming to the opinion of how much CPC money you're entitled to? Where are you getting this figure?

Speaker 1 (42:59–43:25)

So we had two members of the CPC join us in our meeting earlier today. And they spoke up and said, look, they told us that they now are in a position where they can finance grants over a few years. That depends on how much. And, you know, they told us you should be thinking of two million, not one, when we mentioned a million.

Speaker 12 (43:27–43:47)

Well, that's what I was going to say. Because politically, we sold CPC pretty much on the backs, as you know, the chief knows, and I think some of the more senior members know, of that we were going to redo these fire stations. And to this day, we have not spent a nickel of CPC money on any of the buildings.

Speaker 1 (43:49–43:58)

We haven't gotten there, but when we make a decision of which way we want to go, as long as we're reusing the existing building, because… I heard all that.

Speaker 12 (43:59–43:59)

I agree.

Speaker 1 (43:59–44:05)

But we probably should push them for our first attempt going in there for more, like $5 million.

Speaker 12 (44:05–44:37)

I think you're owed. You got zero for headquarters. I mean, if you recall, in the ads for the CPC, vote, we used the picture of the old headquarters. It's like, look what we can do.

And you got zero, not a nickel. And no matter what role I'm in, I will never go away from this. To me, the euro double, if not triple. And if they've got to put their money where their mouth is on this CPC project, now is the time, and this is the project.

Speaker 1 (44:38–44:39)

This is the only time.

Speaker 12 (44:39–45:39)

I know it is. And this is it. And you already know. I've heard you talk about it tonight.

We've heard it in prior meetings. You know what the Historical Commission is. You know the historical aesthetic look of this building. So whatever they can do to help contribute to that and get this product to where it is, is a good thing.

And then this is my last question. And you may have already addressed this. This is why I know Nick's there. Where do you think Total, How much more money do you think you're going to go to?

So of the $50 million that was appropriated in the initial early amendment, because I'm in my mind thinking legislatively, if we need to, to go and try and amend this to a higher level to let it go out even farther than it goes. Because we all agree, we never thought it would even come near 50 million. How close do you think?

Speaker 1 (45:39–46:28)

Yeah, go ahead. We probably discussed this when you were on. Here's the bottom line, the number of 50 million originally developed as part of the special purpose stabilization was a combination of the amount of declining debt that they froze in the interest rates expected on new construction. Judy, as it turns out, We thought we were in great shape.

Oh, we'll only need 36 million or whatever it is, and face those old interest rates. COVID hit, and the interest rates today are so much higher than what they did. They could no longer substantiate a $50 million project. You know, Nick told us earlier, they probably could afford a, how much was it a year?

Speaker 10 (46:29–47:48)

Yeah, so I think, Richard, you have a point. So the projects approved today will be about $35 million under the $50 million cap. So that's like the overall cap on capital projects is $50 million. So we'll be right close to that $50 million depending on the options that are in front of us.

The real kind of important cap for how we can utilize what we have available to offset the debt service costs is a different annual cap. That's $2,329,000 of which we'll only have about $200,000 Phil Kleisler, CoB, ESF-14): Remaining at all the other projects and then so it setting aside the $50 million capital, I think, is not an issue in this case it's it's the other. Phil Kleisler, CoB, ESF-14): factor, which is the amount of money and debt service that brings up from the library and school projects which are up against so. the ask of the taxpayers will be, you know, an increase on their tax bill of approximately a million dollars, I would say, depending on the final forecasting.

So per year, per year, um, and then declining from there. So that's, and that's about a 1% increase on like the average tax bill. Cause we have about a hundred million, that's a little bit more than a hundred million dollar levy. So to answer your question about a million dollars of additional tax per year.

Speaker 12 (47:49–49:04)

That's all I had. Thanks so much for seeing me. I've been listening for a while, but I am following this. Particularly, I know we are trying to go with this, and particularly the math thought, the quasi-roundabout was a curveball that none of us, including all of you, did not foresee, but as I've said to the undersecretary of MassDOT, like, look, this fire station has been a priority now and it's been in the works for, and that has to be, as you all in this room know, that side of town and that the population and geographic makeup of that town, including vehicular traffic on 138 in that town, is much different than it was when I came on the police department in 1984.

And so I think This has to be a functional, efficient, 21st century facility before they do anything else as far as roadway changes. And we're going to continue to model it. And don't be afraid to reach out to us at any time on this, because Bill and I are lockstep on this, on that the fire station has to be the priority here for us. That's all I have.

And I'm good. Thank you very much. Thanks for allowing me to comment tonight. Thanks, Bill.

Speaker 2 (49:04–49:33)

Brian, where would we go with this? Because I think Nick's idea is an interesting one. In my mind, I'm trying to, in my mind, my mission here is to deliver the best fire station for the least amount of money. And I think the, to Nick's point, I wasn't on the committee when that was discussed.

That's not a bad idea. But do we have time to take a quick look at that?

Speaker 4 (49:35–50:25)

My opinion of this is that we need a strategy and a plan of what is going to be asked of in May, because as we sit currently right now with our appropriation, we don't really even have the funds to get started on anything until we get appropriated more funds. And so to have that strategy, what I think we could do is take a look at, if we go to the last page of the packet, where it's a rough idea, excuse me, of what, the ask would be at this town meeting, which is made up of several different components, including OPM fees, designer fees, cost estimate, building fees. All of these have variables if the strategy is to go back to fall town meeting with an estimate in hand that those numbers can reduce.

Speaker 1 (50:26–50:38)

And this is what Nick wants us to be ready to do for the next annual town meeting to ask for this Full design specs, right? Are you looking at that?

Speaker 10 (50:39–50:47)

Yes, I think that helps us and keeps us on track.

Speaker 1 (50:50–51:05)

So it seems reasonable, but this requires the vertex and context agreeing. It seems reasonable that we might have time to flesh out another option, as Ella's asking.

Speaker 7 (51:06–51:17)

Is Jeff's on? Can we ask Jeff what his thoughts are? Because he's been on here from the beginning of this, and does he know why they went away from this plan?

Speaker 2 (51:17–51:31)

He designed the original plan. I think it was on the study committee, the early, early committee that none of us were on, and not even Jeff. You were on that committee.

Speaker 9 (51:31–51:34)

I was on the building committee and that was brought, and I didn't come on.

Speaker 2 (51:34–51:35)

The study?

Speaker 9 (51:36–51:51)

No, the building committee. And that was on, that was one of the points that was brought up early on from Chief Grant. And the exact reason why we went away from that, we talked about a drive-thru ban, we talked about a back-end, one-way, and then a separate building.

Speaker 1 (51:52–52:02)

Chief Grant was very much against driving from the Lowell part of that lawn up Bradley Road. That was why he was against this discussion.

Speaker 3 (52:02–52:06)

There was also a station on saving the station and using what was there.

Speaker 1 (52:07–52:29)

And frankly, in the community and kind of what we heard tonight is this is a strong opinion to try to save and reuse some of that building. Then then if if we all accept that as that, that's one of our requirements, it starts becoming all right, well, How much of it should we do? And that's where we are, all these options.

Speaker 9 (52:30–53:32)

So just looking at this throughout this, I mean, it seems like we're going to save the building and structurally able to do it and renovate the second floor without trying to go over 50%. And I know they had some questions about how the framing was on the front half of the building without it being opened up. So I'm not too sure about that. But looking at the price, looking at the square footage and everything, it looks like option three is, if we're keeping the buildings, is probably the best bet for the town's dollar of getting storage space, rehabbing the existing building.

And, because I mean, whether you put the two, the three additional I believe it's probably cheaper to build on the building than build several buildings. But if you're doing the state building, it is cheaper. And that is a good idea, keeping the building, if we can use it as a temporary. But more than likely, it's going to be exiting right there on the new direction, isn't it?

Who knows? But I mean, state-wise, it needs.

Speaker 1 (53:32–53:45)

Is it? There's a big problem, Paul, you saying option three works, which I don't think is obvious. When we're discussing using a couple That wasn't the active fire engine, right?

Speaker 9 (53:45–54:15)

No, no. So this this one right here is adding three bays to this. Plus the two additional bays. And just rehabbing the second floor as well.

Just raising the roof. We're just keeping the bays. Okay, I see. So technically you have five bays, three new ones, whether they're attached or two detached.

to attach to the voting in one detention. That's just my opinion.

Speaker 10 (54:15–54:27)

I think to your point, whatever, whether in kind of my perspective now, what Alan was trying to advocate for, at the end of the day, it sounds like this committee, based on all these conversations,

Speaker 5 (54:37–54:46)

I'm sorry, was there a way to adjust the sound? It kind of cut a lot. Okay. Yeah.

Speaker 4 (54:46–54:55)

Sorry about that, but it's, can you hear me fully?

Speaker 5 (54:56–54:57)

It's better now.

Speaker 4 (54:59–55:01)

Yeah.

Speaker 5 (55:01–55:04)

It's came back to normal. Sorry about that.

Speaker 10 (55:06–55:21)

I think if Or what we need for town meeting if we're not. I think sorry, I've kind of lost what I was trying to I was trying to help you kind of move to the next stage. I agree with Bob and leave it there. I think that just leaves.

Speaker 1 (55:35–55:42)

that two, whatever, point billion might not satisfy that vote for option five.

Speaker 10 (55:42–56:00)

For what I had asked about and for what Paul is saying, it's basically the same thing as option three. And I think that gives you enough to study that and enough kind of to pull Warner together at this point. However, Leroy's perspective is slightly different from that in terms of what the case gets down to.

Speaker 1 (56:00–56:08)

Leroy, could you be influenced to make option three work? This is a question for 3A.

Speaker 2 (56:08–56:10)

3A. Version of 3A.

Speaker 9 (56:11–56:12)

That's just my opinion.

Speaker 5 (56:14–56:28)

I don't think it's a good idea to put a fire station at the bottom of a hill. I would not support any options that builds a new station in the back of where it is.

Speaker 2 (56:30–56:47)

But I think we should be clear, if she'd correct me if I'm wrong, if we did this other building connected, but out the back, just for the, it would be the water truck, and then the spare engine. The main engine would be off Blue Hill. Yes.

Speaker 9 (56:49–56:52)

Well, that's the way I'm envisioning it. That design right there.

Speaker 8 (56:52–58:14)

Yeah. Let me add a comment at this point. If we are considering putting 2 buildings on the site, just be prepared. There will be 2 separate mechanical systems.

There'll be 2 separate building envelopes. There'll be 2 separate of everything. While it may be a good sort of long-term approach, you know, to be able to house and store things there, it may be wise to consider whether option three on the face of it, without going to a separate storage building, is a slightly better long-term scenario, even if those two additional bays still exit onto Bradley Road kind of similarly. But if they're attached now, it allows us to, you know, Manage all of the systems within 1 building.

I know obviously you'd have the temporary conditions to deal with. Um, but I guess the point that Nick's trying to make is that. While there might be different flavors of how do you address this, the ask is roughly similar. And so those could be addressed and studied and compared and contrasted, and a final decision might not have to be made before we pull things together for a Warren article at town meeting.

We could delay that a bit more, knowing that it's all within that overall ask to some degree.

Speaker 2 (58:16–58:21)

But I put forward a motion to move forward with option three.

Speaker 1 (58:21–58:44)

Well, the only issue I have with that motion, discussing it here, is it automatically, basically, so everyone should know, that's not considering how the other motions. So technically, just so you know. But I'm still confused about option three, the three new bays. But are they one next to the building facing?

Should be the terrace.

Speaker 10 (58:47–59:00)

The goal that the committee agrees that the goal is five days. A mutation to be determined as the size that I have here. We're the one building, two buildings.

Speaker 11 (59:00–59:21)

Option three is five days, but reusing the building itself for programming. Whereas option five B might leave you with square footage. We don't necessarily have a program identified yet. You still get five days out of it.

But you have a second floor of the existing building that currently right now doesn't have a program assigned to it.

Speaker 1 (59:21–59:33)

And so this option would include. or the in-service fire engine, or the construction.

Speaker 2 (59:33–59:48)

The idea is what Nick's saying, it's a flavor of option three. So with option three, we can look at connecting it to the building and also having it slightly reconnected, but not built in a different way.

Speaker 4 (59:50–01:00:30)

And I think in the near future, we're looking for what, what is it that we're putting on this warrant right here? And I think we, if we, if that is the ask of that five Bay, and that's the charge. We might have enough info to kind of extrapolate what those costs are going to be right now. And we can strategize about when the next ask is going to be as that we can forecast.

Well, how much design funds do we need? Or how much PM funds do we need? If the if the thought is to go back in the fall. With, say, a.

redone DD estimate at that point, that significantly lessens the amount that we would ask for in May to jumpstart the project to get going.

Speaker 2 (01:00:30–01:00:35)

So in May, the ask is option 3 is 875 live.

Speaker 4 (01:00:35–01:00:39)

So what that includes, it would be getting us through a bid in hand.

Speaker 2 (01:00:39–01:00:39)

Yeah.

Speaker 4 (01:00:40–01:01:00)

So that would include the finalization of design, as we see here, with a design of two new bays on the side of that. Bidding phase prequalification phase that would go through that all of which would may not be needed before the next funding ask, which we would be able to, we could push it into the next 1 event.

Speaker 2 (01:01:00–01:01:01)

So that would be at the top.

Speaker 11 (01:01:01–01:01:25)

But my only question is, if we look at flavors of 3, we're now we're saying, we're just not adding to. Rinse and repeat bays onto the existing building, which we don't think it fit in the Bradley Road. We have to reshuffle if they're attached. And then also study adding 1 bay and then a brand new building out back that hasn't been designed yet, even though it's a pre-engineered middle building.

We already have a one-bay option.

Speaker 2 (01:01:26–01:01:33)

And that's what is designed through, I don't know, 75%? Correct. That would stand, and we add to that.

Speaker 11 (01:01:34–01:01:51)

So yeah, and we don't know if we can add it to the right, we have to add it to the back, where it might be discharging perpendicular to Blue Hill Ave, or if we're going to say we're going to put a two-bay building out back, or a one-bay, those haven't been even put on paper yet from Jeff's team, so from getting a bid at hand, But that's a little longer.

Speaker 8 (01:01:51–01:02:24)

So yeah, I think your point is well taken. And that is that the 875 5 may not be the actual ask. It's might have to be a little bit more than that 950 or something in order to cover the cost of additional study. And the schedule may have to be adjusted to accommodate looking at these other options, which would delay potentially.

Being able to have bids in hand for the fall, but that would have to be looked at in more detail, considering we're just following it right now, not go to a town meeting or.

Speaker 2 (01:02:26–01:02:42)

For vote with a bit in hand, it's typically a solid cost estimate. So, we don't have to go through all those so that that number wouldn't have to include all of those activities, but we would have to have a rock solid presentation.

Speaker 1 (01:02:42–01:02:43)

This is what we're doing.

Speaker 8 (01:02:43–01:03:38)

And then we would have what we did not do in the prior phase was a construction drawings estimate that was put on hold by the committee. We had already factored in to these costs here that we would be doing a cost estimate for the CDs of the, well, basically it would be 100 percent CDs of the current design. Of course, we could go to town meeting with that cost estimate at 100 percent CDs, which would then include whatever option was chosen for the additional two bays. To Ellen's point, we could go to town meeting with a solid CD level, 100% designed cost estimate to get funding, which is what traditionally has been done for the other.

Well, I guess I can't say for the fire station projects, but what I've heard is for other projects in town seems to be the way things have been done traditionally.

Speaker 9 (01:03:41–01:03:54)

Jeff, would you be able to design it to place the two new bays, one to the side and one under? With the grade difference?

Speaker 8 (01:03:54–01:04:28)

Well, that's a, I don't know. Um, I guess, yeah, I think that I would prefer to have the two new bays face Bradley road, because I think the challenge getting any additional second new Bay alongside the original new Bay is it's just going to be such a tight intersection with Bradley. And I, and I just don't, I don't like the idea of folks having to pull vehicles out to be that proximate to Bradley.

Speaker 1 (01:04:28–01:04:35)

He doesn't want two bays beside, even with one under.

Speaker 7 (01:04:35–01:04:51)

Yeah, I'm sorry. That way, I just attached it to the building. So it's, you know, so you come downstairs, you don't have to actually. So it's same, same mechanical system, same everything else.

Yeah. So it's just the eyes already there. Take the green light to work on for you. Yeah.

Speaker 2 (01:04:52–01:04:59)

That's an idea. So about the motion. Five thirty.

Speaker 1 (01:04:59–01:05:04)

So. Well, no, I haven't. But this is sort of.

Speaker 9 (01:05:07–01:05:15)

That would, just off the cuff, by doing this, does this increase the 50% of the remodel? No. No.

Speaker 8 (01:05:15–01:05:47)

No, we would have the original design remain intact. We would stick with the expectation that the building would meet the code, but it would not be upgraded to meet the code for new construction, which would seismically retrofit the building. So it would not be seismically retrofitted. It would stay within its current design.

And we would stick with the less than 50% area alterations. We just add a new addition to it, a bigger new addition, but it would be a new addition, which is perfectly allowable.

Speaker 1 (01:05:48–01:06:18)

At the end of the day, we would have three new bays. as the site and we'd be able to reuse the two existing bays or whatever. And frankly, I got to tell you this option, my sense is, I already know we have a member of the select board, the planning board, the CPC committee and the historic commission would be fully behind this. And that would be important in town meeting.

Speaker 2 (01:06:18–01:06:26)

I make a motion to go with option three. Which is 875-500 is the S. Do we have a second to the motion?

Speaker 1 (01:06:27–01:06:31)

Well, approximately. Approximately.

Speaker 3 (01:06:32–01:06:43)

I'll second that, but we should have discussion on it. You were concerned about, or Jeff was concerned about some additional funding needed. above and beyond the 875.5?

Speaker 4 (01:06:43–01:07:11)

My question, I think, and it's to Nick, is 875.5 is obviously a number that we've taken with a lot of assumptions going through and carrying what we think we need right here. At what point, for warrant purposes, is a drop-dead date for when something needs to get on set warrant? Because I think context and vertex need to sharpen this up a little bit, make sure everything's covered, and make sure that we're presenting to you exactly what that ask would be.

Speaker 10 (01:07:11–01:07:45)

So we obviously need file number. I think it certainly sounds like there's probably more baked into this than would be necessary just to get through town meeting. But if everything's moving according to plan and moving well, I think having it not there to just keep momentum going, keep the project moving, assuming a positive vote in October. So I think I would defer on the high end.

I would build it out to get to a bid in. even if that number is more than you really need to get the fall. Everything just kind of goes right through.

Speaker 1 (01:07:45–01:07:50)

So it's a 2.1 million for his coming up town meeting.

Speaker 2 (01:07:50–01:07:54)

No, it's not. It's around 900,000.

Speaker 3 (01:07:54–01:08:22)

So it's a 900,000 ask in May. In May. Which will get us to a point where we can then ask for $12 million to build the thing. Is that correct?

Yes. Okay. So it's a down payment. So you know what's going to be asked at town meeting.

Why am I spending $900,000? I don't even know what I'm going to be buying later on. So tell me what it is. Give me the whole.

Speaker 1 (01:08:22–01:08:31)

I think we can. I think we can articulate it. Do it. Right.

I agree. Do it. Do it. Acceptable degree at that town meeting.

Speaker 2 (01:08:31–01:08:39)

I would say what we're saying is we'll have a bid in hand when we go to the town meeting. So we'll know how much it is.

Speaker 4 (01:08:39–01:09:21)

But now meeting in May of the fall to your point, John, when we come for design funds. You need to have an understanding of what the down payment is for and what the overall construction project is what we'd be able to do while we're not going to be able to do much work on this project until we get this funding is we can provide. What we have for our old estimate escalated up to where we are now. with ultimately what we're asking for, which is going to be this five bay solution in which we could put placeholders in for what we think that construction costs.

The first question is going to be, if we're appropriating a million dollars, how much is this project going to cost me to come back again? And we would have that covered in some sort of presentation.

Speaker 11 (01:09:21–01:09:24)

Some visual test. You have schematics.

Speaker 3 (01:09:24–01:09:30)

I would absolutely try to have graphics of what it is. We would. You know, etc.

Speaker 4 (01:09:30–01:09:41)

My last question that I have pertains to CPC funding and Once when the application is coming, I think they said in March or something like that.

Speaker 10 (01:09:41–01:09:42)

Yeah.

Speaker 4 (01:09:42–01:10:00)

And once, once you find out if you are awarded anything, does that become realized quickly or is there a set reimbursement or what I'm wondering is it's not available from presentation from presentation purposes. Are you showing that right off the top or are you still have to borrow that?

Speaker 10 (01:10:01–01:11:27)

But with a reimbursement after in this case, because it's a large project, that would be supported by Michigan Cadet. They would need a slightly different project timeline than they typically do. They typically open applications in May, a final application was due in September, and then they make their recommendations of the following May time. So that window has been entirely missed for this cycle.

So we would need to work with them to, fire station building will be submitted in May, and then they have a town meeting on our occult for fall. So the article 1 funds the fire station projects at $13 million. Article 2 will be to fund the fire station project for $2 million from CPC. So it'll be standalone, side-by-side articles.

That committee will have to just handle its approach a little bit differently than typically. They typically wait for the annual. They'd have to bring that forward to the fall. And I can share with them and I can email Tom or Brian on copyright, just to give them an update as to what this calendar looks like and ask them to take that up alongside when it would go to town meeting in general.

Because I think the project ran into an issue before was they said the project was already funded. So it comes to the same town meeting, sequential votes, or even maybe even a single vote, but they happen at the same town meeting. So that funding is secure.

Speaker 6 (01:11:33–01:11:45)

to this question. Chief, does this design meet your programming needs now and for the foreseeable future?

Speaker 7 (01:11:45–01:12:34)

I think it does. I think it's one of those things. And so we talk about, again, Mr. Walker, I appreciate everything that you've done, and I appreciate everybody here.

This is not an easy, but for me, it was where do I see the fire department? How do I see it? And I don't take it lightly, and I do ask a lot of the firefighters here. Paul has great input.

I trust Paul. There's a lot of deputies that have been around for a long time. I trust those deputies, and I trust Charlie Collingham, the mechanic. How do we move forward?

And so I think this does answer some of our, most of our questions, most of my concerns. I think that's the way, you know, and I think it is a good compromise.

Speaker 1 (01:12:34–01:12:37)

And Nick, you have always supported with this.

Speaker 10 (01:12:45–01:13:17)

And I think that that question has been kind of resolved here. So, the chief and I have talked about kind of our true apparatus needs I think this is, but what we have to remember is these buildings stood for 7500 years so you got to be thinking. And thinking about where we will be long-term is crucial and not missing an opportunity to get the apartment where it needs to be long-term and at least have one department ready to go for 75 to 100 years.

Speaker 1 (01:13:17–01:13:24)

Even the new building, the East Milton station, it's been more than 75 years. Isn't that crazy?

Speaker 3 (01:13:24–01:13:36)

So the Allen's motion, which in consecutive we're still under discussion, are we settling on the 875 or are we adding that with both more? Or to close a void, to close the motion.

Speaker 10 (01:13:38–01:14:19)

If everybody's comfortable with just a nice round number of a million dollars not to exceed, and essentially the Townie Mark was going to put a max on it. This committee will then have the approval of the design contracts, the OPM contracts that fall under that. So you'd be asking if we want to build in a little bit of a room to accommodate maybe some of the options to look for, if you were to say that is that the Springtown meeting for design of a renovated Atherton street station. I think that will cover kind of the goals that you're accomplishing and giving you the room, and maybe the architect of the OPM will come in much below it.

Speaker 6 (01:14:20–01:14:27)

Yeah, there you go. propose that as a friendly amendment or you can withdraw your motion.

Speaker 3 (01:14:27–01:14:37)

Well, I was seconding your motion and I'll propose it with the caveat of a friendly amendment of changing the 875 to one, not to the C190.

Speaker 1 (01:14:37–01:14:39)

Do you accept that friendly amendment?

Speaker 3 (01:14:39–01:14:39)

I would accept that.

Speaker 1 (01:14:40–01:14:44)

Okay, good. So that's the motion that's been made and seconded in front of the board. Is there any more discussion?

Speaker 5 (01:14:45–01:14:54)

Could you please repeat the motion? Sure. Vote for option three. Yes, correct.

Okay. Okay. Thank you.

Speaker 3 (01:14:54–01:14:57)

$1M and 75,000.

Speaker 5 (01:14:57–01:14:57)

Yes.

Speaker 1 (01:14:59–01:15:20)

Thank you. Okay. Anyone else for discussion? Oh, darn.

Where's my silent sheet? So, because we're a hybrid meeting, we have to do a roll call vote. Brian Walsh, yes. Chris Madden?

Yes. I don't know who that is. Ellen.

Speaker 2 (01:15:21–01:15:21)

Yes.

Speaker 1 (01:15:24–01:15:33)

Brian. Brian. Oh, don't feel bad. Brian.

Speaker 13 (01:15:33–01:15:34)

Thank you.

Speaker 1 (01:15:36–01:15:41)

I have. Gene. Gene Sullivan.

Speaker 2 (01:15:43–01:15:49)

Seven. He was. In Philip's, um, yes.

Speaker 1 (01:15:50–01:16:02)

Okay, let me just make sure we have 6 votes here. 1, Paul. Oh, Paul, thank you. Mr.

Walker and missed. Yeah, we're going to walk.

Speaker 3 (01:16:02–01:16:05)

Hello. Mr. Boylan. Yes.

Yes.

Speaker 1 (01:16:05–01:16:11)

Yes. It's unanimous. The motion's been adopted.

Speaker 6 (01:16:11–01:16:21)

Oh, I'm sorry. Would you like to vote? I would like to vote. What would you like to say?

I'm going to declare victory. We got three new bays, so I'm a yes. All right.

Speaker 1 (01:16:21–01:16:51)

It's officially unanimous. Good job. And again, I got to tell you. I think I'm thrilled that the town manager has been working with us here and with his support, and I'm confident now we'll get the select board, the historic commission, and all the committees of town.

And that's going to be important.

Speaker 2 (01:16:52–01:16:57)

The historic and the planning board, very concerned. I think that's why you get the showing today.

Speaker 1 (01:16:57–01:16:58)

Yeah.

Speaker 7 (01:16:59–01:17:01)

All right.

Speaker 14 (01:17:01–01:17:15)

We've got two aiming for… We just need to pay our invoices. Oh, okay. Yeah, thank you.

And Sean, if you want to show hardware pulls, we can go through that very quickly.

Speaker 1 (01:17:15–01:17:19)

No, we don't need… Yes.

Speaker 4 (01:17:22–01:17:47)

I may need your help. Yes. So, Chair, with Gene being out of country, he usually makes a recommendation to Nancy Bulger after our meetings. I think maybe his Wi-Fi has been a little spotty.

I checked in with her with the previous invoice pack and she said I didn't get anything. So I may need you as the chair to say that we voted on this and that she's good to pay.

Speaker 1 (01:17:47–01:17:49)

Oh, you're here too.

Speaker 15 (01:17:49–01:17:51)

I didn't realize that. Yeah.

Speaker 1 (01:17:52–01:17:57)

most of the book first. He can pass that message on phone. I'll take care of it.

Speaker 4 (01:17:59–01:18:57)

All right, sure. We can go through this quickly and we can be a little informal with our monthly report. If anybody has any questions, feel free to call me for the sake of time. For our invoices this month, the Vertex companies for 42,000, Context for 48,000, another Context invoice for $3,800.

An initial invoice from ICO energy and engineering. This is our commissioning agent that we have signed on a few months ago. They've now developed the commissioning plan and we'll be implementing that and having our kickoff meeting. So that's what represents that 1st 1000 dollars.

And the requisition from tower construction for $53,594.83. I will say we're going to be asking for an updated cash flow from them as well as this is, as you know, December was pretty slow out there. We will start seeing these invoices ramp up and I want to make sure that information gets to the town.

Speaker 6 (01:18:57–01:19:02)

We're recommending this as an omnibus motion.

Speaker 4 (01:19:02–01:19:09)

Yes, for a total of $148,394.83. I'll second if I can move a question. Please. May I second?

Speaker 3 (01:19:12–01:19:15)

Go ahead.

Speaker 1 (01:19:16–01:19:17)

Yeah.

Speaker 3 (01:19:17–01:19:27)

On the context numbers, it was a $3,800 AV charge for the bidding, responding.

Speaker 4 (01:19:27–01:19:59)

And then you've got the basic East Milton services, construction services for 48,000. of the other project.

Speaker 3 (01:19:59–01:20:16)

So it's the A-B-D-E Smilton, which really would be parentheses. Correct. Yeah, we knew that that was the process we were going to look at. So now that Brian described it, I think that's fine.

Speaker 1 (01:20:19–01:20:34)

OK, any other questions? Hearing none, unfortunately, we got to do a roll call vote. Just the unfortunate is that I don't have my list. Pardon me, I didn't know.

I don't have my list. I don't have my list. I don't have my list. I don't have my list.

I don't have my list.

Speaker 12 (01:20:34–01:20:34)

I don't have my list.

Speaker 7 (01:20:34–01:20:36)

I don't have my list. I don't have my list. I don't have my list. I don't have my list.

Speaker 1 (01:20:36–01:20:43)

I don't have my list. I don't have my list. I don't have my list. I don't have my list.

I don't have my list. I don't have my list. I don't have my list. I don't have my list.

I don't have my list. I don't have my list.

Speaker 3 (01:20:43–01:20:44)

I don't have my list. I don't have my list.

Speaker 1 (01:20:44–01:20:50)

I don't have my list. I don't have my list. I don't have my list. I don't have my list.

I don't have my 148, 394, 83.

Speaker 3 (01:20:50–01:20:55)

Roy, is he yes? Mark Boyle, yes.

Speaker 1 (01:20:56–01:21:10)

Thank you, Mark. Paul, is he yes? Yes. Brian, is he yes?

Philippe? It was nice knowing you. Here's the good news. We have six votes.

We have enough. Great.

Speaker 5 (01:21:10–01:21:11)

All right. Sorry, yes.

Speaker 1 (01:21:12–01:21:27)

Oh, there you go. Thank you. Okay. So, the motion to approve is unanimous.

Brian, did you send Nick a draft of what he wants to present to? The amount of money.

Speaker 4 (01:21:27–01:21:27)

Oh, yes, absolutely.

Speaker 16 (01:21:28–01:21:29)

I am from Mars.

Speaker 4 (01:21:29–01:22:30)

Yes, you did. Thank you. And lastly, we can hurry through. These are small-dollar change orders we wanted to bring forth.

I know that Sean had actually gotten some of the physical material here, and I don't want to waste his time here. We had three potential change orders that we're bringing forward to you for recommendation. Grand total is $5,827.80. We currently have $408,000 remaining in our contingency.

Uh, let's go through the other 2 1st, and because you have the physicals here, um, change order 005 are 1. this has been modified with some of the reduction in hours that we requested. This is relocated intake louver on the exterior. Um, John correct me if I'm wrong.

This is just relocating a louver to align up with some of the exterior windows that we have. It's resulting in some added duct work that needed to run down the length of the building in order to exit the. exit the structure.

Speaker 16 (01:22:30–01:22:56)

Yeah, the previous location ended up being in a brace frame, and so this is to extend it further down the elevation, and it results in added dark boards. We got an original proposal for this to be larger. We had them to charter the pencils. It came back.

I was pretty happy with the updated amount. It was less than $2,000, so that's that. And then it took a while to get because it's

Speaker 4 (01:22:57–01:23:41)

I can also send the backup to all of these. For the sake of printing, I didn't print out, because they can be pretty large. But if anybody has any questions, I can send those out. The second is a general circuit question from our electrician.

There was a request for information, which had several questions in there. It resulted in our engineer of record issuing a request for proposal. I believe the piece of equipment was the blower fan. Current circuitry on it, we needed to assign it 1 of the circuits that we had in our electrical schedules that resulted in a 1614 dollars and 64 cents for that.

But both of those have been reviewed and recommended from our, our team and context team.

Speaker 1 (01:23:42–01:23:47)

Okay, so it's a motion to approve the. $5,827.80.

Speaker 4 (01:23:49–01:24:12)

We got one presentation quickly with the Millwork hardware pulls for $971.35. This is a recommendation from the designer as to what was owned and what they are suggesting to have as part of the hardware pulls.

Speaker 16 (01:24:15–01:24:38)

In my opinion, they look a little cheap. So I asked the mill worker to propose what would it cost to have something that's, in my opinion, a new minester, it's brushed nickel, kind of matches some of the other options and aesthetics of the building. It's not too significant, but I wanted to provide that. I assume you guys would ask why and what it is.

Speaker 5 (01:24:39–01:24:41)

Sorry, but I cannot hear Jeff right now.

Speaker 16 (01:24:42–01:25:03)

The other item is that we have various pole sizes. So depending upon the billboard items that are being pulled on, rather than just having a simple four-inch pole, you have For a cabinet that's full height, six feet, you have a larger pole, so it's more centered, equal weight. And for the smaller drawers, you have a six-inch pole.

Speaker 3 (01:25:04–01:25:06)

So this is in the kitchen, your job?

Speaker 14 (01:25:06–01:25:07)

Yes.

Speaker 3 (01:25:07–01:25:13)

Any other spots, like in the dressing quarters or the living quarters? Yes. The dressing quarters.

Speaker 16 (01:25:13–01:25:19)

Puppies and things like that? Lockers that are there, too. There's a pair of poles there as well. About 70 poles in total.

Speaker 1 (01:25:19–01:25:22)

And to me, they look stronger than that other one. Is that true?

Speaker 16 (01:25:23–01:25:27)

They're both metal. This one's stainless steel, this one's brushed nickel.

Speaker 3 (01:25:28–01:25:32)

Sean, did Contax spec the first one?

Speaker 16 (01:25:32–01:25:48)

Yeah, so this was part of the base spec that was going to hold over from the 2021 project. So I came in and I did the chief to kind of put a different spin on some of the interior finishes. Do you like them? Where's my wife?

Speaker 17 (01:25:48–01:25:52)

She'll tell you if I like them or not.

Speaker 16 (01:25:52–01:25:56)

It makes the interior feel a bit more considered.

Speaker 3 (01:25:57–01:26:04)

It's less institutional. It's just a more sophisticated look. Yes. Got it.

So, Brian, you were saying you didn't see the code.

Speaker 4 (01:26:04–01:26:07)

Now you could typically put a change in our code.

Speaker 15 (01:26:07–01:26:13)

Yes, so that's in our PCO log, which is going out to you as well as part of a packet. You'll be able to see what that code would be.

Speaker 3 (01:26:14–01:26:15)

We're going to vote on these tonight?

Speaker 15 (01:26:15–01:26:15)

Yes.

Speaker 3 (01:26:16–01:26:17)

when we see your code then.

Speaker 4 (01:26:18–01:26:28)

You know what it is often? I apologize, what do you mean code like- Signing of a reason for that? Yes. So this would be an owner request.

Yep.

Speaker 3 (01:26:29–01:26:37)

No, I'm mistaken. It's my mistake or- This one. Yeah, I quit. We can save $971.

I'm going to the state.

Speaker 18 (01:26:37–01:26:41)

$971 tax is mine, so let's do it.

Speaker 16 (01:26:41–01:26:57)

Okay, so. Okay. go forward. The other two are more or less required.

There are coordination issues.

Speaker 4 (01:26:58–01:27:12)

I would consider the intake louver a coordination issue between sub consultants and the general circuit question would be your omission on the electrical engineer who did not assign that general circuit to that blower fan that we had.

Speaker 3 (01:27:12–01:27:22)

So the electrical engineer, our consultant That's correct. Why are we paying for them? Why are we paying for them? Is that an oil company?

Is that an oil company?

Speaker 18 (01:27:22–01:27:27)

Is that an oil company? Is that an oil company? Is that an oil company? Is that an oil company?

Speaker 12 (01:27:27–01:27:28)

Is that an oil company? Is that an oil company?

Speaker 18 (01:27:28–01:27:34)

Is that an oil company? Is that an oil company? Is that an oil company? Is that an oil company?

Is that an oil company? Is that an oil company? Is that an oil company? Is that an oil company?

Is that an oil company? Is that an oil company? Is that an oil company? Is that an oil company?

Speaker 12 (01:27:34–01:27:35)

Is that an oil company? Is that an oil company?

Speaker 18 (01:27:35–01:27:36)

Is that an oil company?

Speaker 4 (01:27:36–01:28:22)

Is that an oil company? Is that an oil company? Is that an oil company? Is that an oil company?

Is that an oil company? Is that an oil company? Is that an oil company? Is that an oil company?

Is that an oil company? Is that an oil company? Is that an oil company? Is that So we started, I have to do a little bit of math here.

Right now we have approved about $14,000 because if you remember at our previous meeting, we took a $15,000 credit for some of the asks that we gave back to there. So right now we have approved about $14,000 through change order number 5. The addition of this would put us up about $20,000 approved at this point with about $400,000 remaining. So we started with about $420,000 and that's where we are right now.

Speaker 7 (01:28:22–01:28:39)

I guess my big question would be, I mean, I know that's unforeseen, but is there anything that would. Create a large contingency below the budget. Yeah, exactly. At this point where we're now we're talking about finishes.

You know, little things like that.

Speaker 4 (01:28:39–01:28:51)

Is there anything. No, it's it's my hope that we've uncovered any type of unforeseen at this point. I think submittals are at a very. Farther along stage where things have been flushed out.

Speaker 15 (01:28:51–01:28:52)

Ordination has been done.

Speaker 7 (01:28:52–01:29:01)

Biggest 1 that sits in the back of my mind. I hate to revisit it, but the water. Like, is that going to be a substantial change order?

Speaker 4 (01:29:01–01:30:01)

Yes, so we do have some original some. Liminary numbers with that. Yes. We're probably looking and I forget if there was.

What we need to pay for is the additional excavation, the tie-in, but we're also looking to get some credits back from the other water lines that we're not going to go per the plan. So when I send out that PCO log, you'll also see the numbers that we're either carrying as a rough order of magnitude or something that has been submitted that we're still reviewing that we're not in agreement with. So if you look at the bottom, not only with the assigned Blame, we'll put the blame pie on there. But it also will track, if we take everything right now as face value and we approve everything blanketly, how does that relate to where we are with our existing contingency?

So if we feel as though that we're uncomfortable where that stands, you'll see that on our monthly report. We'll put that in a red, and it'll be one of the first things that we talk about.

Speaker 1 (01:30:03–01:30:07)

OK. What you're really worried about will be a rule for those via taps later.

Speaker 16 (01:30:07–01:30:27)

Yeah. All right, any other discussion? Yes, there is. Bridges.

Bridges? Bridges. Right now, the spec owns a 42-inch sub-zero bridge. A 42-inch sub-zero bridge?

Speaker 17 (01:30:27–01:30:27)

Yes.

Speaker 16 (01:30:27–01:31:17)

Yes. during design. Now what I did was I went through last week because I'm doing the millwork. So I had the millwork approved.

Typically what you want to do is make sure it coordinates with all the lines. So we've got a sub-zero fridge and we've got a wolf induction range. The wolf induction range is 36 inches wide. That's around 10 K.

estimate and the sub-zero fridge at 42 inches around 15K estimate. That's on the hook for the owner to purchase.

Speaker 3 (01:31:19–01:31:24)

And that comes out of the owner's contingency somewhere?

Speaker 4 (01:31:24–01:31:30)

It will come out of our very tight, thin FF&E budget that we're working with.

Speaker 3 (01:31:30–01:31:32)

Which is 48,000 of this, apparently.

Speaker 4 (01:31:32–01:31:33)

Currently, yes.

Speaker 3 (01:31:33–01:31:36)

Like 36 of it is two at once.

Speaker 4 (01:31:36–01:31:45)

What we have also in the FF&E, we have a line item. We have communications and line items that we can maybe use.

Speaker 16 (01:31:45–01:31:54)

I just wanted to let you know what I have found. So a 42-inch fridge is running you around nine grand.

Speaker 3 (01:31:54–01:32:01)

Can we cut to the chase and say, can we ask you to come up with a conventional

Speaker 16 (01:32:02–01:32:43)

What I'm getting at is that 42-inch fridge, $9,000. The millwork to accommodate that has to have a size for a 42-inch fridge. To go to a 36-inch fridge, which are more common and less costly, let's say it's $2,000. Roughly, you can find one.

There's way more options when you get to the 36-inch fridge and especially when you get into a fridge and a 30-inch fridge. I also don't want to approve a millwork opening or a 30-inch or a 36-inch fridge, because that limits your ability to have a 40-inch fridge. Now I pivot now to the discussion with the fire department. Hold on before we go down there.

I know you want to say it's money. No.

Speaker 3 (01:32:43–01:32:52)

The fire department doesn't need a 42-inch refrigerator for a cluster of guys who are probably eight, right?

Speaker 16 (01:32:53–01:34:01)

If they were to have a say in this matter, And I want to walk me down to Paul, he would say they do. So that's why it was priced that way. So before we go down the road of me approving the work, which is going to cost the committee to revise later on and having been. Actually, certainly, I'll make sure that we are now making a decision doesn't have to be tonight by the next.

Next week, I would like to have a decision about going 42-inch fridge or 36-inch fridge because it impacts the size of that opening. I also don't want you guys showing up with an $8 million fire station. You guys go to check out the fancy new kitchen that I designed and all of a sudden you're like, why the heck is the fridge in there that looks so silly? And nope, that was a combination for a 42-inch fridge.

I'm imploring the team to figure out what size fridge. Now, you seem to make it a very simple discussion. Clearly, we want a 36-inch fridge, which I'm happy to buy the millwork for, but I want to make sure that the entire team has the ability to review the decision. I heard Ron just talk about it.

Speaker 9 (01:34:01–01:34:05)

You have two.

Speaker 16 (01:34:22–01:35:08)

So when I took the project over, which was 75% of the cities complete, there was a space for a bridge. Now I was managing a ton of other things that definitely fought in the matter. Went ahead with the 42-inch bridge. We didn't know what the bids were going to be.

We didn't know what the contingency So same number of people There as here there's there's five firefighters five to Seven firefighters here.

Speaker 7 (01:35:08–01:35:11)

There's three firefighters down there.

Speaker 1 (01:35:11–01:35:19)

So for a day Two thirty six inches versus 142 The ratio is almost the same

Speaker 9 (01:35:21–01:35:38)

So it's four groups, three, at each station, each outside house. That's why, like, right now, you don't have to spell that code. You just have two. So in one room.

Like you said, it was called Northside.

Speaker 1 (01:35:39–01:35:44)

I vaguely recall a conversation Gene had about the appliances, saying something to me.

Speaker 16 (01:35:45–01:36:18)

He's very adamant about having the best appliances, and that's why I put it into that. He was he was making that point I think we're all the same page here we wanted it to be sized adequately to service people it's gonna be clearly it's too expensive even at $9,000 so millwork and approvals process. Right.

Speaker 1 (01:36:18–01:36:22)

And that's what you need. That's the decision you need now. What do I millwork?

Speaker 16 (01:36:22–01:36:27)

The other thing I can do is I can size it for 42 and clearly a 36 inch will fit in there. That's my point.

Speaker 3 (01:36:28–01:36:32)

Do they make 42 inch general electric? That's my point.

Speaker 9 (01:36:32–01:36:36)

Or not. I've looked into it. Yeah.

Speaker 16 (01:36:36–01:36:38)

I have all the cut sheets.

Speaker 1 (01:36:38–01:36:40)

You're not going to get cheaper going away from that model.

Speaker 16 (01:36:40–01:36:59)

There's two Gene Keys. The first is there. And what's the 36 inches? 36 inches is around, so when you get to 36 inches, you're talking about a standard home appliance, not 42 is more, they call it like a luxury home appliance.

So you're around $2,000.

Speaker 1 (01:36:59–01:37:08)

Cheapening for some reason really had it against standard home appliances. And they'll replace it in two years.

Speaker 16 (01:37:24–01:37:48)

and that made sense. Half of it in a 36-inch range. I think an induction range is clearly cost prohibitive. I do think that the users would prefer a 36-inch range.

I believe induction was requested due to the electrically powered items that they have, as opposed to just an electric range.

Speaker 3 (01:37:49–01:37:52)

For those people who have pacemakers, believe it or not,

Speaker 7 (01:37:56–01:38:02)

Right now, we have no fire fighters that have that thing.

Speaker 3 (01:38:02–01:38:08)

So I mean, there are all sorts of things. I mean, since we're going down rabbit hole, I'm not going to go down to the fence.

Speaker 16 (01:38:09–01:38:22)

I don't consider a rabbit hole important. So it sounds like this group here is really dependent from 43 to 76. And I will size. Tonight, we'll send an email there.

Speaker 4 (01:38:31–01:38:31)

on this job.

Speaker 15 (01:38:31–01:38:48)

And so what we want to do is meet with the chief probably within the next week, go through all of these, and we might need to prioritize them as well as we know our FFE budget is tight, we know our contingency is what it is, but we need to get what we need to get in right now in order to open up this firehouse.

Speaker 4 (01:38:48–01:38:59)

And if something needs to be deferred until we have our contingency shaken out and we have an understanding of what we have left in our kitty, that's what we'll do. But that has been generated and we're ready to meet so that we can put

Speaker 16 (01:39:00–01:39:25)

What I'm going to do is I'm going to come back to the group now knowing it's 36 inches because the 42 inch bridge all had basically the same size opening it could go into, so that was pretty easy. I'm hoping to find three or four manufacturers that have a 36 inch wide bridge and do the same process. That way I can both expedite the submittal review of the work.

Speaker 1 (01:39:31–01:39:42)

Okay, so that was. We had that discussion because it was related to 1 of these costs, right?

Speaker 3 (01:39:42–01:39:59)

Right? It was well, no, yes, it was supplemental to it. So we're going to get back to the 971. Or separate item.

Oh, right. Approved now. Okay, this is.

Speaker 1 (01:40:00–01:40:22)

Yeah, the motion that was made second. Was for paying for the 5,827 dollars 80 cents, which included. 97135 for the bill. And the bill work was that and it just thought it made you think of, oh, we got this other issue with there's a whole set of things.

Speaker 16 (01:40:22–01:40:38)

I have to. Review and coordinate across the whole not today. Separately just as the designer. When I approve the millwork, it's going to be marked up.

There's going to be an effort. I'm hoping there's no added cost to it. There might be an added cost to have a nice box around your bridge.

Speaker 3 (01:40:39–01:40:42)

But the refrigerator may be less than $15,000.

Speaker 16 (01:40:43–01:40:53)

Yeah, so theoretically I saved you guys already. In concept, if I were better sales, but I'm.

Speaker 17 (01:40:53–01:40:55)

Are you in real estate sales?

Speaker 16 (01:40:55–01:41:02)

Actually, uh. Run for my clients, this is all right.

Speaker 1 (01:41:02–01:41:15)

So we added a motion. It's in May and 2nd. We have to do a roll call vote and that's for again, the. 5827 and 80 cents.

Uh, Brian yes, chief. Yes.

Speaker 9 (01:41:16–01:41:17)

Yes, John Sheldon.

Speaker 1 (01:41:17–01:41:20)

John Sheldon, yes. LeRoy.

Speaker 9 (01:41:20–01:41:23)

Yes.

Speaker 6 (01:41:23–01:41:23)

Mark Boyd. Mark.

Speaker 1 (01:41:23–01:41:31)

Yes. Yes. Paul, yes. Paul, yes.

Yes. And Brian, yes. And Brian Beaupre, are you still with us?

Speaker 17 (01:41:31–01:41:34)

Yes, I'm with you. I'm with you.

Speaker 1 (01:41:34–01:41:59)

Elie, are you still with us? I'm having a tough day, I got to tell you. You have no idea. I guess he's not, but we have six votes, so it's unanimous, it's approved.

Thank you. Do we have anything else to talk about about East Milton? Not really. It looked like it was stalled for a while, but I'm riding by it regularly.

In fact, I'm waiting for one of the teachers, one of the kids to report to you.

Speaker 4 (01:42:03–01:42:19)

No, like I said, I agree. It has been slow moving, the dam proofing. Once the seal went up, the dam proofing, the fine grading, the quibbling over the waterline stuff that didn't need to go on as long as it was. We will be seeing a significant delivery next week.

Speaker 3 (01:42:21–01:42:24)

Concrete or when it couldn't be cold.

Speaker 4 (01:42:24–01:42:24)

I know.

Speaker 3 (01:42:25–01:42:25)

Congratulations.

Speaker 4 (01:42:25–01:42:26)

I know.

Speaker 9 (01:42:27–01:42:29)

Right. There's a lot of weight in the spring.

Speaker 4 (01:42:30–01:42:52)

Yes, so we know that there's a moratorium that opens in April. I was completely on board with them not allowing us right now. It's my intention is once we get into February and late February, you just kind of open the discussion back up again and to see if there'd be any relief on the back end of that. If we start seeing warmer weather in March.

Speaker 1 (01:42:53–01:42:59)

Yeah, and they'll be able to close it enough to do that. They work in the winter. Right?

Speaker 4 (01:42:59–01:43:40)

Yes. Yeah. Yeah. And, you know, in full transparency.

I was hoping for a little bit more help from our general contractor about. The moratorium and working with that and finding a solution. It wasn't there and so I think when that February timeframe comes out, I'll kind of lead the discussion with their to to see if there's anything that can be done. Because any help we can get on that back end is going to help us in the future with our schedule.

Because of the size of our site, we're going to have a lot of deliveries going on, and we want to mitigate as much excavation we have to do, because that means we're going to be shifting materials around while we're trying to dig our waterline.

Speaker 3 (01:43:41–01:43:44)

And is that the town DPW or the MWRA?

Speaker 4 (01:43:44–01:43:50)

So the MWRA permit hurdle has been taken care of now at this point.

Speaker 10 (01:43:50–01:44:11)

So this would be the opening of the street tying into the main that's out on the street.

Speaker 1 (01:44:13–01:44:22)

And that work and street work will be done after the school is closing. No. What'd you say it's going to be for? It's before March, April.

Speaker 17 (01:44:22–01:44:23)

Yeah. Oh yeah.

Speaker 3 (01:44:23–01:44:28)

When is spring break? Or whatever. Do they have a vacation break or something?

Speaker 1 (01:44:28–01:44:31)

They do in April, I thought.

Speaker 3 (01:44:31–01:45:03)

April's holding a vacation break. Yeah, they did when I went. So, so Brian, speaking of vacation, so the next meeting is Tuesday of February, which is the 17th. okay so the 16th is president's day and that week of the 16th is it vacation yeah me i'm fine no but everyone else i just want to highlight so it's are we going to have a meeting on the tuesday the 17th or tuesday of february what would would people prefer we delay it a week and avoid the vacation week

Speaker 1 (01:45:03–01:45:14)

be good. Better for me. Okay. What date is the following 24?

24. Take your kids while we propose meeting on the 24th.

Speaker 3 (01:45:14–01:45:19)

That doesn't put you guys too far off with those rules. You can handle the 24th.

Speaker 4 (01:45:19–01:45:48)

Yeah, the payments are quickly once we get them approved here. So my only question with the vote of the upset limit of, we'll say a million dollars for this. Ask here. You are initiating this work process.

Does that go through chair and to you about meeting with the Warren committee? I think also, while it will still be February, I believe this committee is going to need to start talking about community outreach and educating people of the project and what the ask is going to be.

Speaker 1 (01:45:49–01:46:15)

So that might be something. Well, in my mind, we would start that educating the community at town meeting. That's kind of the, you know, you got 279 members from all over the town. I don't know what other, you know, then we can start thinking about tying into neighborhood associations, but I was thinking town meeting would be the first big pitch, which is what, April?

Speaker 10 (01:46:15–01:46:23)

I think it would have been a different conversation if it was a new construction and the existing buildings be on the left and right.

Speaker 12 (01:46:23–01:46:23)

Yes.

Speaker 10 (01:46:31–01:46:52)

your client may need something. that you're thinking about would be more big projects. In line with what people expected and already voted for. It was a deviation from that.

Speaker 1 (01:46:52–01:47:24)

I think that's where the advantage is. The Warren Committee is already, you saw Jay here, it'll be tightening at us again. I got to start articulating and thinking of answering his two questions, right? Which is, do we have to do anything with the Athens Institute?

So I got to go and dig up some of our old materials. But we actually, why? But I'll do it with him, we're going to meet with the community preservation people. Yeah, I think we'll be in good shape.

Speaker 6 (01:47:24–01:47:27)

So what's the date you're thinking about, Brian?

Speaker 1 (01:47:27–01:47:30)

28th? 24th.

Speaker 6 (01:47:30–01:47:32)

24th, I am not in town.

Speaker 17 (01:47:32–01:47:42)

You're not in town. Is it, are you like a few days later or what's the? I'm going the 24th, 25th, 26th. I'll be back the 26th after.

Speaker 7 (01:47:45–01:47:52)

I loved it. Um, you're not a general quorum. That's fine. I'm here for every vacation anyway.

Speaker 18 (01:47:53–01:47:58)

So you see, well, 70, you want to hear loud? Yeah.

Speaker 11 (01:48:00–01:48:01)

You're on vacation.

Speaker 1 (01:48:04–01:48:06)

Does that date work for you folks? Yes.

Speaker 11 (01:48:06–01:48:08)

I'm away. So I can do the 24th.

Speaker 1 (01:48:09–01:48:10)

It's too many brides at the table.

Speaker 11 (01:48:10–01:48:14)

I'm sorry. I'll send Brian's to 24.

Speaker 7 (01:48:14–01:48:18)

It's fine. I can just, I can relay my concerns to you. What to you. Yeah.

Speaker 1 (01:48:20–01:48:36)

You know, that's what we'll do. All right. It's a tentative motion to adjourn. Second, second.

It's non-debatable. All those in favor, just say aye. Aye. Aye.

Okay, Brian. I mean, Philippe, he's gone. Good. He's gone.

Speaker 19 (01:48:37–01:48:38)

But I didn't even have to ask.