Board: School Building Committee

Date: 2026-06-15


Transcript

Auto-generated; may contain errors.

Speaker 1 (00:19–00:20)

Uh, good evening.

Speaker 2 (00:20–00:37)

I'll, uh, call the, uh, town and Milton school building committee to order. It is now 7 0 2 PM on June 15th, 2026. As we typically do, uh, we'll just do a roll call as they kind of see people online here. Uh, Carrie Hurley.

Speaker 3 (00:38–00:38)

Yes.

Speaker 2 (00:39–00:51)

Uh, Peter Obersheimer. Yes. Uh, Bob Mayhew. Yes.

Present. Yep. Uh, Mark Loring. Present.

Nathan Hutto.

Speaker 4 (00:52–00:52)

Present.

Speaker 2 (00:53–02:34)

And Glenn Hoffman. Yeah. And myself, Sean Wark. So, agenda item number two.

Let's take a quick look at that. Uh, discussion approval, so we have essentially 3 proposals that we need to vote on tonight. 2 of which are for supplemental work with collaborate college. And then 1 is for our contract with PMA for our root.

So. Just kind of focusing on LabArray to start, what we have are two proposals, one from Foley, Buell, Roberts & Associates. They're a structural engineering consultant that will work in collaboration with the architect. They submitted their proposal, and I've got it up if people need to take a look at it, but it's basically the ones that were sent for $4,500 and essentially, Their role is to review the overall structure at LabArray and then basically provide an existing conditions report as essentially they're deliverable that will go in concert with the work that DLR Group and Shinalee are doing with the architecture.

So I'll leave it there to see if any of the members have questions or comments in regards to the structural engineering proposal we received. Yellow background with the yellow hand is always hard to see.

Speaker 5 (02:34–03:22)

Yeah, and I don't know if we have to do the hand thing here, but 2 questions. Appreciate it. Thank you. Thanks.

The 1st is probably straightforward. Just in their purpose number 1. Where they describe basically that they're looking at the classroom building and the newer wing. I just wanted to make sure I followed that, you know, rather than just, I think I know why that's why structurally what they're focusing on, because probably those are the areas with possibility for deeper renovation than the other buildings.

But I just wanted to make sure I was following that. If you caught that and you could explain.

Speaker 2 (03:22–04:04)

Sure. So, yeah, the intention for that one is for, you know, the intention or the intention of the overall project that we've asked them to do is to focus mainly on building C, which is the building with the classrooms in it. I think there were some programmatic stuff that discussed looking at building B, which is the other. Call it addition on the building a, which is the mansion.

So, those are what they're looking at there. I don't believe they're going to in detail look at building a, which is the mansion mainly because our ideal goal is not to do any modifications of that for energy purposes.

Speaker 5 (04:09–05:50)

Okay. My second question, it has to do with the comment and the proposal about sort of reserving the possibility for more exploratory review later, which makes sense to me, given sort of the scope and timing that's available at this stage, and we don't own the property. I'm just trying to and I don't know if you can answer this now or this is just something we keep talking about sure like I'm trying to picture a scenario of sort of a Reservation or you know of whatever we kind of get back From the architect or excuse me from the structural engineer with sort of a Indication that they would like to do an exploratory review to get a more complete you know, whatever, assessment later. I'm trying to think like what that could look like from a timeline perspective.

That may be difficult to answer right now and without kind of being in that situation. You know, one thing I'm trying to do, you know, from the select board perspective, is just kind of think about like what is kind of happening June, July, August, and what is more at a later time, kind of thinking about it from two buckets and, you know, not coming at it with a certain view, needs to be in bucket area. I'm just trying to start to think about what's in what bucket. Yeah, just interested in the group's thoughts on, you know, something like that.

Speaker 2 (05:53–07:12)

Yeah, I might, I'll lead off, but anybody else, feel free to jump in. Yeah, my end is, you know, for the $4,500, you know, we're spending on this and the tight timeline associated with it, There's not much more than a visual review and essentially reviewing the existing documents that they have there to do what they can for analysis. This kind of task that we're asking the architect and the structural engineer to do, like I've made an analogy almost to like a home inspection, you know what I mean, before we purchase something to really look at it for Call it visible signs of structural deficiencies. I don't think they're going to run calculations or, you know, open any walls up to look behind them, mainly because we don't, again, we don't own it, so we can't do that.

But I think as the program comes out later, if we buy it, then, yeah, there would probably be, if there's things that they see that are concerning, they would expand upon it on the future task. OK. I don't know if anybody else, Glenn or Mark, from your experience on any of these kind of projects for other schools, if you have a similar experience.

Speaker 6 (07:17–08:16)

Yeah, no, I very much agree with your assessment, Ashok. We're going to be competitive as it relates to the time frame. We just got a lot of information we can't or not going to be able to do. the in-depth and structural assessment.

We just don't have the time, similar to the architect. And we also don't want to sink too much money into something that we don't need, because it's not within our control to buy it or not buy it. I think that's something that we should make sure we're being open about with folks. There will still be questions, but we're trying to answer as many as we reasonably can within the time frame.

Obviously, when we buy it, before we put any people in it, we will do much more in-depth assessments. But we just can't right now. So I totally agree with all your points.

Speaker 2 (08:16–08:20)

Any other comments on the structural engineering proposal that we received?

Speaker 7 (08:22–08:31)

Oh, yeah, Nate. I'm all in, Sean. I think that seems pretty reasonable. Work he's going to be doing pretty a power.

Yeah, and market rates.

Speaker 2 (08:32–08:36)

Okay, and Nathan, I apologize. I didn't see your hand up.

Speaker 4 (08:36–09:50)

No, all good. I, I wanted to, I have a question. That's all I think along the lines of what he was asking in the same family. I don't the proposal to me sounds reasonable.

Just I just want to check my thinking here coming out of the. the architects work and the structural engineers work, we will have a sense of whether the education program proposed by Milton Public Schools can fit into these buildings. What we won't have a sense of is, for example, the level of deferred maintenance that sits on top of these buildings or Capital investment needed. I'm, I'm asking this just from a place of, like, I, I've seen now, maybe 1 or 2 years in a row.

Now, the level of capital investment that we defer. Every year, and probably sits on some backlog somewhere. And I, I'm curious if we're going to purchase these buildings, just what what amount of capital debt we're purchasing at the same time.

Speaker 1 (09:52–09:53)

Yeah, well.

Speaker 4 (09:54–10:00)

As it relates, I assume that I'm leading all that up to say, I assume that's not we will not have that question answered as part of this.

Speaker 2 (10:02–11:36)

So, no, we will not. So, with with kind of encompassing your question specifically as it relates to the structural proposal. I wouldn't I think any renovations we're doing there as part of the overall project if we buy it. Along with any additions that we put on there from a structural perspective will be all, you know, not a lot of capital future capital investment needed there for structural improvements, but not knowing the systems.

you know, when they were installed, what we're going to use them for. But again, my anticipation is most of that stuff will get gutted. And, you know, I mean, we would just renovate all of building C, basically, you know, soup to nuts of all systems. So the future capital expenditures for that would start as essentially a brand new system.

I don't think the intention would be to keep some of the stuff that's there. Yeah. And I only say that because a lot of the rooms are probably going to have to get reconfigured from what's there, you know, for just from walking it. A lot of it's like lab space.

It's subdivided. And then once you start moving walls around, then you have to move HVAC registers. And by the time you start doing some of that stuff and balancing everything out, it's easier just to, you know, have it gutted and start over from scratch. My personal opinion.

Speaker 4 (11:37–11:52)

So I guess my, the question or the, the non, the inability to answer really applies to buildings a and B where we're specifically not doing any assessment and not intending to touch it very much.

Speaker 2 (11:54–12:04)

Uh, correct. Yeah. So from the structural perspective, yeah, their, their focus is mainly going to be on building C and as Pete mentioned in his first comment, uh, some into building a B.

Speaker 7 (12:08–12:38)

Don, I would agree with you that this building will probably be in near total gut. And the way the building code is configured, if you configure more than 50% of the space within a building, you have to bring the entire building up to building code, which almost definitely you would have to do with this building to change it to an educational use. That's my opinion. Without even seeing the inside of the building, I'm guessing that would be how that would go down.

Speaker 2 (12:39–13:09)

Yeah, and along those lines, Glenn, the intention is to only do those renovations or that level of renovation to building C, which is the back one with the classrooms. The front, call it mansion, which is building A, and the amended portion of that that's attached to it, building B, the intention is not to do anything there to trigger that exact scenario that you were talking about. That answer all your questions.

Speaker 4 (13:09–13:18)

That was great. Thank you. No problem.

Speaker 2 (13:18–13:19)

You don't get a question.

Speaker 4 (13:21–13:25)

Yeah, her question is, why won't you throw this ball for me?

Speaker 2 (13:25–13:40)

Gotcha. Any, any other comments or discussion as it relates again, just to the structural proposal that we received. If there are none, I'd happily entertain a motion.

Speaker 6 (13:42–13:46)

I'll take a motion to accept the structural proposal as presented.

Speaker 2 (13:47–14:00)

Second. Yeah, Bob, I don't believe you can second because- I'll second. Yeah, sorry, you're a non-voter. Give him some.

That's a procedural thing I'll have to check.

Speaker 3 (14:00–14:01)

I'll second.

Speaker 2 (14:02–16:11)

All right, sorry about that, Bob. That's all right. I thought when I swore in, I. That's okay.

All right. Any other discussion? Hearing none, so we'll go to a roll call vote because we're all remote. Peter over.

Yes. Glenn Hoffman. Yes. Nathan.

Yes. Mark. Yes. Carrie Hurley?

Yes. And Sean O'Rourke? Yes. Okay.

The next proposal that we saw was for $6,500, and that's from PMC Consulting. So they're essentially the cost estimator, I think, from The reviews of a lot of the proposals we had, and you can see they basically do all the schools around Massachusetts, so they have a good history of pricing, different options and different types, renovations, new construction, and stuff like that. They were actually the same consultant that we used on the project two years ago when we were working with Arrow Street. So again, they'll be taking The architectural layouts that the Chenally is developing for the pre-K, K enrollment and system program that we're looking at, along with whatever structural inputs are provided.

And then, you know, with that, developing that overall cost estimate for the program at Lab Array for preschool, kindergarten. So just with that kind of opening statement, again, I'll open it up to see if any And hearing none, so if there are no questions or comments similar to before, entertain a motion.

Speaker 6 (16:12–16:18)

I'll make a motion to accept the proposal from PMNC as presented.

Speaker 2 (16:18–16:31)

Second. Okay, second by Glenn. Any discussion? Hearing none, so we'll do a roll call vote.

Moved around again, so it'll be a different order. Apologize. Carrie Hurley?

Speaker 3 (16:31–16:32)

Yes.

Speaker 2 (16:33–16:33)

Peter Obersheimer?

Speaker 3 (16:34–16:35)

Yes.

Speaker 2 (16:35–18:03)

Glenn Hoffman? Yes. Nathan Hutto? Yes.

Mark Loring? Yes. And myself, Sean O'Rourke, yes. All right, so then that essentially wraps up, you know, for a lab array.

This will get, I know Shanali is trying to do a site visit out there, I believe, this Thursday. So, you know, she's going to try to get these consultants out there with them too. Well, just the structural engineer, not the cost estimator. So, I appreciate everybody, you know, jumping on this.

The other one that we have, that we have to vote on tonight is, Our owners project manager that we selected last week of PMA consultants has provided their cost estimate or their proposal for the schematic design services that we're doing as part of MSBA. So, it's similar to the effort that we did two years ago. But this time, obviously, it's going to be a little more intensive or structured because we're under the MSBA program. So, you know, I think as you guys are starting to see, there's a lot of checks and balances and paperwork associated with that.

So, that's kind of representative of their fee that they've provided. Um, with that, I'll see if anybody has any questions on the overall proposal. I'll do my best to answer what I can.

Speaker 5 (18:09–18:53)

Yep. You know, I'm going to have some questions along the way. Part of it is just my catching up. So I appreciate it guys, but, you know, um.

And I couple questions. Um. On the contract itself, I don't have the paragraph from the contract that this refers to, but I caught at the beginning and I don't I don't have any edits or anything like that. These are just clarifying for my own understanding, but it looks like it's.

There's a second contract potentially later in the relationship. I can kind of further explain, but if that's enough, I just was trying to wrap my head around that.

Speaker 2 (18:54–19:58)

Yeah, that's a good point. So, as I mentioned, this is only for schematic design that we're doing. So, under MSBA, we have certain modules that go up, and the schematic design will take us, I believe, to module 5 where we we do the vote for the funding and at that point after the module 5 for the funding we do you know the full detailed design because now it's an approved project so the the contract that we have for them right now would basically take us up to that point for a vote and then if the vote passed there would be a second contract that would come in with PMA to basically run the remainder of the project from Module 6 all the way up to Module 9, I think it is. So this is, if you think about it in a simple way, this contract would be for PMA to work with the architects and engineers to get us to a vote, and then if it passes a vote, then we would have a supplemental contract after that.

Speaker 5 (20:00–20:06)

Okay, I may have one or two more, but I'll take turns. I see Mark is raising his hand.

Speaker 2 (20:07–20:07)

Yeah, sure.

Speaker 5 (20:08–20:08)

Go ahead, Mark.

Speaker 6 (20:09–20:36)

Yeah, it was really just a comment on that point, which is the architect contract that we'll do eventually will be structured the same way. So they'll both end right at that end of that module to see if the town votes to approve the project. That way we're not locked into a contract for services we don't need. The town votes it down for some reason.

Speaker 4 (20:36–20:50)

All right, Nathan. I just have a couple of probably very basic questions that maybe I should already know the answer to. Sean, who signs this contract? Who is the owner?

Speaker 2 (20:52–21:09)

I believe the town would be the owner, so I think Nick signs it or the select board. I think The last time we did this was with, I don't know if Ben signed it, so Winston may have decided, but he's he's on the contract as the signatory.

Speaker 4 (21:09–21:10)

Oh, yes.

Speaker 3 (21:10–21:11)

Yeah.

Speaker 4 (21:11–21:24)

Okay. Miss that. And do we have in a contract like this? Do we have general counsel do a review of the terms and conditions?

Speaker 2 (21:24–21:49)

I believe so, so I believe Nick has talked with the council about it, but I can text him and ask right now if it helps. Okay. Because we had a discussion earlier regarding this and there was another item that we were discussing that he had talked to council about, so I'm just assuming they have reviewed it.

Speaker 4 (21:50–22:36)

Okay. That would make me feel better just because Yeah, I would, you know, we can't review all of us probably. And then. Is is so the proposed fee is $380,000.

I don't have a. I don't have a reference point for that, like. What do you for those of you who have been on this rodeo once before and work in this business? Does that.

First of all, I guess, is that how much of that is just set by MSBA versus differentiated based on the based on the OPM? And how do we feel about that fee?

Speaker 2 (22:38–24:43)

I can speak to kind of what we had previously, so I believe when we were doing this again, kind of outside the MSBA guidelines that we're working under now, I believe our contract with PMA was like for $275,000 for a similar effort that they were doing. Again, not as paperwork heavy as MSVA, and that was, like I said, for $275,000, and they didn't spend all of it. you know, for the money that we allocated. And I believe this contract said not to exceed.

So I think what they're trying to do is make sure they have, I know for myself, you know, when I, when I try to enter into contracts that are not to exceed, I try to aim for a high enough ceiling that you don't have to go back for amendments. In context, this is, The funding for this will come out of the 1.5 million that we had allocated by town meeting. And I, you know, so there is capacity in there that if we needed to increase it, we probably could, depending on, I'm not anticipating the architects being over a million. Um, so I, you know, that's.

You know, kind of what I see for right now, the other 1 that plays into it and just knowing, talking, um, with people before the number of options also plays into it for, um. you know if there are 10 options that we're studying it's probably a higher fee than what we're doing here we've got well essentially we've got three options that we're looking at in two potential sites so if you think about it it's really about six uh five options got it good thank you no problem and scott tereshak's with us too so i apologize he was in the waiting room and i've uh Got them online. Sorry about that, Scott. No problem.

And Pete, can you get your hand up again?

Speaker 5 (24:44–24:56)

Section 3.2 requires us to designate a day-to-day communicator with the OPM. Just curious if that's you? Is that this whole committee? Do you have any thoughts on that?

Speaker 2 (24:57–25:25)

It will probably be me. Yeah. Similar to what we were doing before, there were times where Uh, I would be on calls with the OPM and, you know, just kind of, uh, assisting with certain things that were there, but obviously when certain items come up that, you know, are called beyond my, my, my, my scope, you know, those are the ones that we, you know, we, we put it on the agenda and, you know, we'll have, uh, standing meetings to address all that stuff.

Speaker 5 (25:26–26:47)

Yeah, that, and that makes, I wasn't signing myself up for that, but I like. I'll just, I like, I was looking for it and I like it. 4-5 basically gives us kind of some control over, you know, their team, you know, and them replacing members on their team. You know, I think that the team that showed up at the presentation made an impression on us and that basically says, you know, that's That plus them plus additional people will be the team if they're going to replace people, you know, subject to our approval.

So that thought that was good. My only last comment was trying to see where I saw this, whether it's in the agreement or their cover email, but they said something about um sort of outreach period and they they they referenced like a two-month time span um in 2027 28 28 I couldn't remember and if that and I can find it if it makes more sense but I was just if that was referring to like a community engagement period it seemed a little um short but um I could just be um you know connecting just something I think we should keep an eye on outside of the the Contract language itself.

Speaker 2 (26:48–27:00)

Okay. Yeah, and I didn't see that. So, if you can highlight it to me, I'll take a look for it. All right, I'll look what we're talking.

Okay. All right. Mark, you had the end up. Sorry.

Speaker 6 (27:01–27:48)

I was just going to say, I'm happy to volunteer Sean to be the point person usually to the point. I like the. It's obviously in the full construction thing cost typically. A way you can roughly estimate design and OPM costs is architectural costs are about 10% of the construction cost of the project.

And then OPM fees vary a little bit more, 3% to 6%. Usually, if it's a larger project, it's a little bit lower. Again, that's all on the full construction. We're not even close to that, because 5% on $150 million is, I think, $7.5 million, something like that.

So, again, we're not even close to that because we're not near the construction phase, but just wanted to provide that kind of context.

Speaker 2 (27:49–28:21)

Yeah, it's popping in my head, too. So, one of the things, too, Pete, that you can look at is MSBA publishes all their cost data. So, they do have an overall spreadsheet of previous projects, and they list out the OPM. overall percentages, and I don't know if they're as high as what Mark was talking about, but essentially all that information is there, and then I can pull that up if you want me to.

I can find it for you.

Speaker 5 (28:21–28:26)

I think that would be for Nathan's question. I didn't have any questions about the fees. Okay, sorry about that.

Speaker 2 (28:29–28:33)

Too many questions. I'm trying to keep track of them, writing them down. You're doing well.

Speaker 8 (28:38–29:06)

Thank you.

Speaker 9 (29:09–30:04)

All right. What I can do is I can put this in the chat. So let me share my screen just so I can give you guys just what I'm seeing. Sorry, too many screens.

Speaker 2 (30:04–31:22)

So at the MSBA site, they have Cost for elementary, for middle, middle high schools, basically everything all the way through. Feasibility studies for designer-based services when they're there. Let's move this over. Reimbursables, they basically break everything down.

So for the OPM, when they're looking at this stuff, these are kind of a stretch. Mark was right, about 4% of the overall project cost. When they're showing 3.4 million, I don't know if that's all the OPMs of all the projects, if it was summarized. I don't think it's per project, so I forget what this was for.

But I was just showing this for people, not to confuse people, but to show the data for what you're looking for is on MSBA's site. So, for your question for engagement, Pete, were you able to find the portion of the contract that you were looking for?

Speaker 5 (31:26–31:43)

When you were talking community engagement. I know you're asking for, I was just stumbling. Sorry, I don't want to hold you guys up.

Speaker 2 (31:43–31:55)

Good. So there are no other questions or discussion points. Let's see if anybody's open to making a motion for the OPM contract.

Speaker 6 (31:59–32:04)

I'll make a motion to accept the OPM contract from PMC as presented.

Speaker 2 (32:06–32:09)

One minor, and it's PMA, not PMC.

Speaker 6 (32:09–32:13)

PMC is the company. Sorry. Thank you. I'll take that friendly amendment.

Speaker 2 (32:13–32:28)

Yep. Second. All right, second by Nathan. Any further discussion or questions?

Hearing none, we'll do roll call vote. Kerry Hurley?

Speaker 3 (32:28–32:28)

Yes.

Speaker 2 (32:30–33:40)

Peter Oshimer? Yes. Nathan Hutto? Yes.

Mark Loring? Yes. Thank you. Glenn Hoffman?

All right, thanks. Scott Tereshack? Yes. And Sean O'Rourke?

Yes. So I think that takes care of our portions of the agenda for discussion approvals. The other one that we need to approve is the OPM selection narrative. So this was an additional thing that, you know, we had to basically give an overall write-up for how the selection was made of the OPMs.

So Nick Milano, I know, had sent that out by email earlier today for everyone. So with that, I'll see. I've reviewed it briefly, but I'll see if there's any other questions or comments as far as it.

Speaker 1 (33:40–33:42)

I have a copy of it if people need me to share.

Speaker 3 (34:02–34:20)

I did notice and this is just. Request spell check. Very top of it.

Speaker 8 (34:21–34:23)

Yeah. Yeah.

Speaker 2 (34:34–34:59)

So essentially, what Nick was asking is if outside of this meeting, if there are comments that people have to it, minor edits and stuff like that, not total rewrites, to provide them to him. But I believe we'd be OK approving it tonight. I'm not anticipating much follow-up comments.

Speaker 3 (35:02–35:08)

I mean, we should all be pretty familiar with it. because we used part of the format, right?

Speaker 2 (35:09–35:22)

Yeah, correct. So this is an MSBA requirement that we need to provide the process by which we went through to select the OPM so that they have it on record.

Speaker 3 (35:23–35:27)

No, I'm just saying it so that we can push to get this approved tonight.

Speaker 2 (35:27–35:28)

Understood.

Speaker 5 (35:29–35:43)

Sorry. I mean, yeah, I think it looks fine. in at the end, Sean, as the point of contact that's highlighted in yellow. But I trust Nick to handle all that stuff.

Speaker 2 (35:44–36:01)

Oh, Mark made that motion earlier. Nobody seconded it. So I don't think I'm on there. I'm just kidding.

So similar, I will entertain any motion in regards to this.

Speaker 4 (36:05–36:14)

I'll make a motion to approve the OPM selection narrative report. Second.

Speaker 2 (36:16–37:39)

Second by Peter. Any further discussion? Hearing none. So we'll go to a roll call vote.

Kerry Hurley? Yes. Nick Donato? Yes.

Peter Robesheimer? Yes. Scott Tereshek? Yes.

Mark Lurie? Yes. Glenn Hoffman? Glenn, drop off.

Sorry. I'll unmute, yes. There we go. Sorry about that, Glenn.

Not my fault. Yep. And then Sean O'Rourke, yes. So the next thing on the agenda is just approval of minutes.

So what happened was, Along with this attachment that we're sending to MSBA, we also have to approve the minutes that were associated with the creation of the request for services for the OPM. So, I know Nick sent out two sets of meeting minutes. I believe it was March 2nd and March 9th. So, I'm just going to.

Open open it up for discussion for those 2 sets of meeting minutes. I know there are other meeting minutes that were listed. We're just going to table those to our next meetings.

Speaker 5 (37:43–37:57)

You guys have a quorum on those to vote without me if I. Abstain, this is where before I was on, I think I. Well, that doesn't count against the quorum, so that's fine.

Speaker 2 (37:58–38:02)

Yeah, I think we'd be fine with it, Pete.

Speaker 3 (38:09–38:14)

I have to abstain from the March 2nd.

Speaker 2 (38:21–38:32)

Okay, so what I would ask, and it's probably easier if we just do a motion for one at a time, and then we just do a roll call vote for each one, and then, you know, Carrie, I'll make it easier if you need to abstain.

Speaker 3 (38:33–38:33)

Okay.

Speaker 4 (38:33–38:42)

All right, I'll make a motion to approve the March 2nd meeting minutes. Okay.

Speaker 6 (38:42–38:43)

Second.

Speaker 2 (38:44–38:50)

Second by Mark Loring. Any discussion? We'll do a roll call vote. So, Carrie Hurley?

Speaker 3 (38:51–38:53)

I'm going to abstain.

Speaker 2 (38:54–39:15)

Peter Obersheimer? Abstain. Glenn Hoffman? Yes.

Nathan Hutto? Yes. Scott Tereshek? Yes.

Sean Warwick? Yes. Who is that mark mark?

Speaker 6 (39:15–39:15)

Yeah.

Speaker 2 (39:16–39:20)

Yeah. Sorry about that. I mean, it's, uh, there's 1 less on my, on my thing.

Speaker 6 (39:20–39:22)

So that's no problem. Just want to make sure I'm a yes.

Speaker 2 (39:23–39:32)

Yep. Sorry about that. All right. So that's the, uh, March 2nd meetings.

Uh, and then the next 1, we have is March 9th.

Speaker 4 (39:33–39:42)

Okay, I'll make a motion to approve the March 9th. School building committee meeting minutes I'll 2nd.

Speaker 2 (39:42–39:46)

Any discussion? Hearing none, so Kerry Hurley?

Speaker 3 (39:46–39:46)

Yes.

Speaker 2 (39:48–40:01)

Glenn Hoffman? Yes. Nathan Hutto? Yes.

Scott Tereshak? Yes. Mark Loring? Yes.

Peter Obersheimer?

Speaker 5 (40:02–40:03)

I'm staying.

Speaker 2 (40:03–40:08)

Okay. And did I miss anyone? Sorry.

Speaker 5 (40:09–40:19)

All right. So, I forgot if I said this, but it's because I wasn't on the committee yet, obviously. But I can't remember if I said that, so thanks.

Speaker 2 (40:20–41:01)

Yeah, we're glad to have you now. All right, so item five, now that we've got those minutes approved and everything else, is adjournment. So entertain a motion to adjourn. So moved.

All right. Yeah, thank you, Pete. Any discussion? Hearing none, so roll call vote.

Peter Obersheimer? Yes. Glenn Hoffman? Yes.

Nathan Hutto? Yes. Scott Tereshak? Yes.

Mark Loring? Yes. And Kerry Hurley?

Speaker 3 (41:01–41:02)

Yes.

Speaker 2 (41:03–41:06)

And myself, yes. All right. Thank you guys very much.

Speaker 1 (41:06–41:09)

Have a great night. Thanks, Sean.