Board: School Building Committee

Date: 2023-11-13


Transcript

Auto-generated; may contain errors.

Speaker 1 (00:43–00:49)

Once we get set up, we'll call it to order. Okay.

Speaker 2 (00:52–01:16)

So it is now 7.06. On November 13th, they'll call the meeting with school building committee to order. Start it. Mike's going to be remote.

We'll just do a roll call. Oh, who's here? Is that what Mr. Warren?

Here. Dr. Miranda?

Speaker 3 (01:16–01:16)

Here.

Speaker 2 (01:16–01:19)

Scott Tereshack? Here. Gary Early?

Speaker 3 (01:19–01:19)

Here.

Speaker 2 (01:19–01:40)

Sean O'Rourke? Here. First thing on the agenda, or second thing, I always make that mistake, is citizens speak. So, you know, if there are any citizens that are in the audience that do want to speak, we reserve the first 15 minutes of the, oh, there's a mic.

Speaker 4 (01:50–01:56)

Hey, Mike, can you hear us?

Speaker 5 (01:58–02:00)

I can. Can you hear me? Yes, sir.

Speaker 2 (02:01–02:36)

So yeah, we're just starting off with citizen speak right now. So just leading into that portion of the agenda. So for any of the citizens that are in the audience that do want to speak, we just ask that you take your hand. We reserve the first 15 minutes of the meeting for citizens to speak.

And we ask that you limit your commentary to three minutes. And then please state your name and address just for the minutes. And Mr. Jackson, I see your hand is raised.

One second.

Speaker 6 (02:48–02:49)

Thank you.

Speaker 7 (02:51–02:51)

Can you hear me?

Speaker 2 (02:53–02:53)

Yes, sir.

Speaker 7 (02:55–04:09)

Good evening. I'm Peter Jackson from 14 Capon Street. I've been following the discussions of the Select Board that have been having with the State Transportation Department concerning the proposed roundabout at the Randolph Avenue-Chickatobit Road intersection. I'm delighted that MassDOT has agreed to undertake a route 28 quarter study and expand the scope of their analysis for this important project and that important arterial in our town.

It seems to me to be the perfect opportunity to consider the establishment of a school zone with reduced speeds, sidewalks, a signalized pedestrian crossing, and perhaps other measures to enhance safety. This will allow a more comprehensive consideration of the six-acre municipal parcel on Randolph Avenue as the location for the proposed new middle school when the current Guyo Road proposal has proven unsuccessful. I encourage you to endorse that effort to give a more complete analysis and consideration of the Randolph Avenue parcel. Thank you.

Speaker 2 (04:11–05:11)

Any others? I'm just looking to see if there's any other hands raised. All right, I'm not seeing any others. All right, next.

Thank you. Item three on the agenda is approval of meeting minutes. I apologize the, the meeting minutes for the 12th I think were sent out previously but we never voted on them. And then I sent out the ones today on the regarding the September 29.

The October 16th minutes, we still have to do those. I have to work with Tim on those. So I'm fine deferring these mainly because I just sent them out today. So if we want to defer them to our next meeting, totally fine.

Unless other people want to approve them, I'm just leaving it out there for anyone. So.

Speaker 6 (05:15–05:20)

I didn't get a chance to review, so I would welcome the opportunity.

Speaker 2 (05:21–05:47)

That's perfect. I think one of the ones sent today was from August. No, the title on the email was August, but the minutes when you look at the attachment are the 12th of September, I believe. I think it was the opposite.

Was it? Yeah. Okay. Yeah, the email said the 12th, but the minutes were from August.

Speaker 8 (05:48–05:49)

I'll check that.

Speaker 2 (05:53–06:16)

All right. Item four on the agenda, or four A, is a discussion update of our project timeline. So I'll just share my screen for a minute.

Speaker 4 (06:31–07:01)

Yes, we are.

Speaker 2 (07:05–09:13)

So what we've got here, the red line here is the date today, the 13th. So first thing, you know, we'll touch on these otherwise, but, you know, the docs to the Executive Office of Energy and Environmental Affairs, we're working on a dual path on both of those. We've submitted the docs to EEA. We've had meetings with them.

They're up to date on everything we're doing. Similarly, and we'll touch on this later, we've sent it through Walter Timmelty, Senator Timmelty's office. We may have reviewed it, sent it up to Senate Council's office that provided red lines that we got back. So we'll dive into that later.

The portion of it is the stuff that the EEA submission, we're on track. So for the schedule of everything that we're looking at. I know on here it has us meeting with EA for the third time. We haven't been able to meet with EA.

We've asked multiple times. But with the track that we're going on with Senate Attorney Timothy's office and EA, we're on track. I'll touch on that later on the agenda. The stuff that we've had through here is mainly onboarding the OPM.

Tonight is our first meeting with our OPM, so Sean Burke is on the call with us tonight. We have an agenda item to review and approve, or recommend to the select board approval, the contract with PMA Consulting. So the good thing is for this part of the timeline, again, the work that we've had to do to get to this point to onboard an OPM, we're right on track. I think that was it.

Everything else after this is kind of some of the stuff I want to talk about tonight, like dive into the architectural RFS, start laying out that schedule, getting into that stuff. So in regards to this initial schedule that we put together for the project, any questions or comments on there?

Speaker 6 (09:15–09:17)

There is a line there that is dragging.

Speaker 2 (09:18–10:33)

that's a special legislation. So what happened with that one is that's the, we drafted the special legislation with the town attorney. That's what's got sent to EEA and that is also what got sent to Senator Timothy's office that they commented on. So it's the actual language of the special legislation.

So that was due back in August. It has 8-6, I'm not sure how yet. We drafted that a while ago. So that checkmark's all done.

So we hit that mark, you know, back in August. That's the stuff that's been going on that they've been reviewing. looking, showing what was right to me, but I thought it was the right flagship. Yeah, I put it in red just to highlight to me that was one of the initial things.

The problem was when I first talked about this, the color coding on the graph, the blues, the greens and stuff tied into this thing here. But whether it was medium risk, high risk or not, that was irrelevant as far as true risk. It was just there for the color. It was a template that came off Excel and that's why I used that for that.

Speaker 9 (10:34–10:51)

Some of the talkers point to the timeline, the ultimate timeline for this now is pushed to, we think, like mid-July. We're not going to get a vote on this before the end of the calendar year.

Speaker 2 (10:51–11:03)

We're going to touch on that when I get to that agenda. That's the tough thing with the schedule. Schedules is to kind of highlight everything and then we're going to dive into each one of them a little bit later. Sorry about that.

So, sorry.

Speaker 9 (11:06–11:21)

Well, I just think when we get to that piece, if we could go back to the EEC, we'll go back to this and just within the EEC section, like have that identified as like when when we are anticipating being able to close that portion of this work out. Yeah.

Speaker 6 (11:24–11:26)

Any other questions for everyone?

Speaker 2 (11:26–12:10)

Just making sure. All right. Item 4B is Discussion, Update, Recommendation and Contract with PMA Consultants. So I sent along…

Stop sharing the screen. We had sent along essentially what the town has is their standard contract with PMA Consulting that basically lists out the scope of services that we're asking them to do, which is similar to everything that we interviewed them for. The contract value on that I think was $160,000. We've got Sean Burke here.

So Sean, I don't know if you want to weigh in a little bit just on kind of that contract that you guys had sent over or that we sent to you guys that you guys filled out.

Speaker 8 (12:11–12:41)

Yeah, it's pretty standard kind of what we do with any school project scope of services and find in there, but it's really open to whatever is required to get the project through to the next phase. So we're not limited to the scope that's in there. It's more of a minimum. All that that contract is set up typically as cost plus.

So you assign tasks and we do it. So it's a little bit fluid in that we find what to do and what's most appropriate to do. to help move the project forward and we just we do those tasks.

Speaker 10 (12:45–12:50)

Any questions? Does it address any change orders?

Speaker 11 (12:50–12:56)

Does it address any change order language?

Speaker 8 (12:56–13:36)

For us, chain changers would just be cost plus. So, anything within that budget, you can literally have us do anything you want within the budget. We just like to have a framework of what the expectations are so you understand what our role is, but it's certainly open to expansion for whatever it is to do. Yeah, you were talking contractual changeover is based on what their scope to do, not construction changeover.

Yeah, there was the only reason we ever have an amendment or change orders if we we ended up going over the budget. Otherwise, I don't think unless if the town wanted a formal change order to add a scope of work, that's fine. We wouldn't be opposed to it, but I'm not sure that it's necessary.

Speaker 2 (13:40–14:46)

Any other questions? Was that you with the contract? We don't have the ability to execute contracts that we just make recommendations to the select board. Select board is actually the one that executes contracts similar to it.

our recommendation to start negotiations with PMA consultants. So I think at this point, you know, our step, if we want to take the next step forward, was basically move this to a vote on it and then go up to the select board, select board, and then execute the contract. Once they execute the contract, then PMA would be on board basically running these meetings. I assume the contract is similar to what's being used in the fire, but it's different.

a template is different. I believe it's different. There was a previous, the previous town administrator was on. I'm not sure if it's the exact same contract that was used for the fire station building.

The overall essence of having an owner's project manager here to take over the management of this project is what it is. I just say that because I haven't looked through the fire station building committee contracts. I can't really say they're identical.

Speaker 9 (14:57–15:08)

I'll make a motion to approve the… Recommend the OPM draft contract for approval by the State Board.

Speaker 2 (15:11–15:25)

I'll second that. Any further discussion? Hearing none, because the mic's on MO, we'll go to a roll call vote. Mark?

Yes. Selina?

Speaker 6 (15:25–15:28)

Yes. Yes.

Speaker 2 (15:29–15:33)

Yes. Yes. Yes. Yes.

Speaker 12 (15:34–15:34)

Yes.

Speaker 2 (15:37–17:54)

Yes. Yes. So, I didn't foresee on here is our funding article. So, as many of you guys are aware.

We've got an appropriation and tell me it is a little over 100,001 or 6,001 was a presentation. I think since last we met, we went to the Warren Committee. It's been passed by the Warren Committee. They were recommending it.

The Select Board recommends it. So, basically what it comes down to right now is just presentation, a meeting. She'll probably need me repeating the presentation unless she feels like she wants to jump in front of that meeting. Yeah, I mean, the good thing with that now, it gives us additional funding and kind of ties into our upcoming tasks of like onboarding our tech and stuff like that.

So, you know, open that up for any discussion and questions or anything like that kind of leading up to town meeting. How much would we be asking for? I think it's four hundred and six thousand. It's four hundred and five thousand change.

I think so. Total is sixty one, I believe. Six. Yeah.

How long would that money last? Do we expect the money to last? So until the end of this feasibility study. It will last longer than that.

So the intent of this is to onboard the OPM and the architect to run until most likely next fall. we'll talk about this as we get into architectural services, is to onboard an architect early in the year, let them start running with design, and ideally have something end of the summer, September, that we can put a view into what it looks like, whatever concept it was before the DRA had it, maybe something totally different, a much more refined one that will allow showing the price of better. So at the end of this exercise, we'd have a really good cost assessment and a good schematic design that would kind of tie everything together.

Speaker 6 (17:55–18:09)

Any other questions, discussion, anything like that on the funding article?

Speaker 2 (18:09–21:07)

All right, hearing none. Item 4D is the land swap. So, as we're talking about, I'll pull the timeline back up just for purposes, because we were talking about it earlier. So yeah, the special legislation, so we'll start with that.

So the special legislation that we have right now is in, was that Senate Counsel's Office, they provided red lines back to us. We're basically, we're incorporating those red lines and basically going to present it back to Senate Council. The process by which it would get voted on, ideally, we're hoping for was December. There's a number of subcommittees that has to go through, and because we're in November right now, there's no way we can get it through the subcommittees ready for December.

So the goal or what we're aiming for is next July. So our understanding is that they vote on these things in December and in July. So what we're doing right now is working with them. Part of it falls into, along with the special legislation, we have to get the appraisals done.

So there's a contract already executed for that. Appraisals are underway. And then the alternative analysis. I didn't have it ready for tonight, so I couldn't put it on the agenda for a vote, but essentially at our next meeting, that it's going to do.

I'll have that done. Basically, I've sent out the initial draft and I received comments from them. So it's mainly just incorporating those comments. So the intent of that is have all those deliverables done essentially by our next meeting.

I believe the appraisals will be done because it was a 45-day window that Nick put on that. And I believe it was supposed to be soon like mid-November or something like that and then with my alternative analysis along with special legislation that's everything we have to get to EEA. There's potentially they might request a survey of the parcels that Norm Randolph have and if we have to do that BSC has given us a We scope for that, and we would have funding with what we have under our ledger right now. Don't we already have a stock?

Survey? Lovegow Road. Oh, yeah, the additional the additional parcels that are up off Randolph Ave, which are basically the stuff between Granite Links and Randolph Ave off the access road, those ones that we added at the end, those we don't have surveyed for. Typically, they accept record plans from the town.

And that's, we haven't heard differently, but we're just waiting to get back to them. That third meeting we're supposed to have with the EA, that's one of the things we want to confirm with them, because it was kind of left in the open last time we talked with them. Mike, I don't know if you have anything else you want to weigh in on regarding the EA or any of the discussions?

Speaker 5 (21:08–21:57)

Yeah, I mean, I think it's important to point out it's really town council who is driving this process with the Senator Timbalty's office and they're really driving it. And, you know, I think our outside time is to get it approved, you know, by June. Because it's not gonna be ready for December, my understanding is there's a possibility that it could be done before that, and town council's gonna try to get it done before June. But it's really in the hands of town council and Senator Timothy's office, and we're just kind of giving them what they need in order to do what town meeting asked us to do.

Speaker 2 (22:03–22:35)

Essentially, our goal is by next July that the legislation or the execution of that would be done so that we basically formalize that thing. I think for the land swap stuff, that kind of summarizes everything, kind of where we're at. We've done everything we could up to this point. Now we're just waiting for the state legislature to push it through.

Speaker 9 (22:36–22:55)

Do we need to vote on the appraisals? We'll receive them, we'll vote on the alternative analysis that you put together at the beginning so that the next meeting we can pull out everything we think they need and then the action steps is just wait and see until they reach out and say we need something else and we'll get whatever else they need.

Speaker 2 (22:55–25:26)

Yeah, exactly. And when we submitted it to them, they said they're required to serve it gets surveyed on as quickly as possible, but we would have time between now and June to kind of do better than it would take six months to do. All right. Item 4E, which is MSBA updates.

So MSBA, One capital check for the one that the district got from MSBA regarding essentially the given informational session for everybody that submitted a statement of interest. And it's just more of a talk in general about the process and stuff like that. The last meeting we had with MSBA, I think it was over the summer, and it was to check in on their statement of interest. They had some questions and stuff like that.

Typically, they follow and making that mark, we haven't heard anything. So I'm not sure if it's a sign of not getting approval. Maybe they changed, I'm not sure. But for us right now, it's kind of been silent from this view, where we stand.

Last time you did give us, they tell us about how many graphics they thought it would fund. Yeah, so they have, they, I don't remember, do they offer any of that? They may talk about that stuff there. I think, as I mentioned before, with the new tax that they have in there, I think it's the millionaire's tax, their increase in funding has fallen roughly, I think, from $900,000 to like $1.2 billion.

$300,000 increase, which has allowed them to kind of open up a little bit more. But, you know, who's to find how many they're going to select, I don't know. So once we get on that call, we'll probably have better information from there. But at this point, none of them.

Just various.

Speaker 3 (25:26–25:29)

But do I recall that we were expecting to hear something this month?

Speaker 2 (25:30–27:36)

That was my expectation. So just going off the previous time we did it, We submitted our statement of interest. They followed up with an informational session asking questions to us. And then following that, a couple of weeks to a month later, they asked us, it was during COVID, so they couldn't do a walkthrough of the schools, we weren't letting people in.

But what they asked us to do was a video walkthrough of the school and submit that to them. So basically, what typically would happen is they would do an in-person walkthrough, see what's going on, see it with their own eyes rather than just the text we put together. and then that would help inform them a little bit further. The fact that we haven't had that request to come to the school to see it, you know, for me, just makes me a little bit weary about the selection process or anything like that, whether we'll get selected.

Yes. All right. Last item under old business, item 4F, which is the discussion of the embassy. I'm joined, sorry about that.

Item 4F, for architectural services for Godward. So this is, I think one of our big things, our main topic for tonight is to touch on, we're gonna have to draft your request for services, similarly we did for an OPM. And if you recall, we started that probably end of, August and run that through September, October. And we're finally on board, you know, a couple of months later for us.

I think we're going to have to get this RFS out next month quickly and, you know, start getting interviewing people and doing stuff like that. So, you know, under item four, if there's probably a bunch of bullet items, but I think so, first thing, Sean Burke, if you don't mind, can I call on you to just kind of go over what a typical RFS looks like or what we'd be asking, just with some framework or context for people that might not have done it before, specifically me?

Speaker 8 (27:37–29:44)

Sure. Typical RFS, you lay out the project, what you're looking to do, as specific as you want to make it, you can. A lot of the times, people haven't done the homework that you've done up front, where you kind of already have a site selected, you already have really a school selected, which you want to build. Oftentimes, you're looking for an architect to help guide you through that process.

So I think To that and it's done so you're gonna lay out, you know which which you intend to build how many students you want in there. If you have some not like wants to have some like to have you put that in there and the architects will take that information, and they're gonna come back to you with really a body of work they're going to show you what they've done they're going to show you. The different projects they've done, they're going to show you different ideas how their buildings look. And then you typically shortlist 3, maybe 4 of the respondents and have them in for interviews.

The 1 thing that's a little bit. Maybe I don't know about different, but something we kind of stress and we'd like to, and this 1 is to talk to our architects about designs that they already kind of have done and have built before in the past. That might be appropriate for the site and for Milton and for the project and to highlight that with the idea being if they have something they've already done recently, and it's something that the town likes, it might speed up the design process, which will get the building off the ground in a much more quick fashion. So.

But other than that, it's really looking for their, you know, their history, what they've done, how long they've been in business, all the different projects. So you can evaluate, you know, start doing reference checks, finding out other towns they work with to make sure that they're the right fit for Milton and then interviewing the ones that you kind of rise to the top that you think are going to work best for the town. We would help in that process. We'll set up rubrics and some scoring sheets to try to aid the committee and scoring these, scoring the architects as they come in, how they should be breaking them down, kind of some red light, green light stuff, things that jump out at you as problematic, things that you jump out at you as advantageous and try to help the committee judge who is the best architect for this project.

Speaker 2 (29:46–30:22)

Thank you. So with that, just kind of in general context, I know we've been talking about architectural services are a slight ideas that, you know, I think about being ready for and stuff like that. So not that we have to identify all of them now, but it doesn't know if people have things they want to, you know, enunciate now at the meeting. And then, you know, we can start taking notes on that stuff and start incorporating the stuff into the RFS.

And if you don't, you know, we can use it as we send out the RFS individually. People obviously may get it sometimes there, too. So.

Speaker 8 (30:26–30:53)

I think you're right, it's probably not appropriate at this meeting, but it's coming pretty soon. So I think people should start getting those notes together, what's important to them, any of the things that they find important. So if it's appropriate to include in the RFS, you do include that. But I don't know if you're going to have an open discussion about it tonight, but it is something that everybody should really be thinking about and getting their notes together for.

Speaker 2 (30:54–33:21)

Yeah, so just for a contact shot, we've been talking about it probably for the past like three or four meetings just in general to start thinking about it. So yeah, just repeating it now to let people know probably by our next meeting, we're going to have a hard document that we need to start putting out there some more ways. Questions, comments? I'm really excited, mate.

I agree somewhat about it, but I promise them on TV that we'll do it, so keep that promise. I've got an awesome bat for us. I agree, mate. The butters concerns are very apparent to us right now.

So obviously, as we're progressing through those things, traffic, stormwater management, those two. So the big thing on this too is similar to the OPM, we're going to have a subcommittee that makes these up. So last, you know, we have nine members. I'm not participating in subcommittees, so that goes four and four.

Miranda, Mike, and I thought, maybe you guys want to participate in this, maybe you don't, that's totally fine. I just want to offer the opportunity there. The other four will probably work with, I talked to Glenn Pavlicek, he's meeting with Peter Burrows to kind of go over, there'll be four representatives from schools, principals, and probably a preschool coordinator or something like that to kind of weigh in on that stuff. So that's kind of the makeup of what I was thinking for the subcommittee.

So, you know, knowing this, we'll probably be getting some middles in, my guess, if I'm doing this live off the top of my head, we haven't gone through like a real thing, but probably early January after the holidays, nothing will be happening over the holidays. It would basically be getting those submittals in, digesting them all, scoring them to shortlist them, and then issuing that shortlist in one consolidated meeting. And then after that, it would be the same process that went through with the OPMs, bring the three shortlists of architects in, and the whole group will interview them and pick one from there. So hearing that, we'll get your name at the top, Carrie.

So are you interested in it? You are?

Speaker 8 (33:21–33:21)

Cool.

Speaker 2 (33:23–33:23)

Second round?

Speaker 6 (33:24–33:24)

Cool.

Speaker 5 (33:25–33:31)

I mean, it's not an expertise that I have, so I'm happy to refer someone with more expertise.

Speaker 2 (33:32–33:42)

Yeah, and the way I made it up before was, so school committee representatives, select board representatives, so not you, I'll probably ask Glenn. I'm sure Glenn will be interested for the archives.

Speaker 5 (33:43–33:50)

On this one, you might want to have, I mean, if you want to, because it's so focused on how the school is going to be set up there.

Speaker 2 (33:50–33:53)

Glenn's the only architect we have on the board. Oh, actually, yeah.

Speaker 5 (33:53–33:59)

So yeah, you want me. Yeah. Yeah. And we're going to actually want it on me.

I'll check with them. Yeah. I should probably go on TV. Do you?

Yeah. I should probably go on TV. Do you? Yeah.

I should probably go on TV. Do you? Yeah. I should probably go on TV.

Speaker 8 (33:59–34:01)

Do you? Yeah. I should probably go on TV.

Speaker 6 (34:01–34:03)

Do you? Yeah. I should probably go on TV. Do you?

Yeah. I should probably go on TV. Do you? Yeah.

Speaker 12 (34:03–34:04)

I should probably go on TV. Do you?

Speaker 6 (34:04–34:06)

Yeah. I should probably go on TV. Do you? Yeah.

I should probably go on TV. Do you? Yeah.

Speaker 8 (34:06–34:07)

I should probably go on TV. Do you? Yeah.

Speaker 12 (34:07–34:08)

I should probably go on TV.

Speaker 8 (34:08–34:08)

Do you?

Speaker 12 (34:08–34:09)

Yeah. I should probably go on TV. Do you?

Speaker 8 (34:09–34:09)

Yeah.

Speaker 2 (34:09–34:22)

I should probably go on TV. Do you? Yeah. I should probably go on TV.

Do you I should serve too. I appreciate it. All right. And then with Glenn not being here, it's easy to say he's.

And he loves it. He actually does. He did a good job on the other one.

Speaker 6 (34:25–34:27)

Yeah.

Speaker 13 (34:28–34:28)

OK.

Speaker 6 (34:28–34:31)

Yeah. I was at the airport.

Speaker 2 (34:31–34:45)

I know you were. I thought you were doing it remotely. Fast riding from Boston. Yeah.

So we just you yourself. We've cut their fee to allow you to be secretary. I hope that's false.

Speaker 12 (34:45–34:48)

It's all good.

Speaker 2 (34:48–35:16)

Just kidding. So we were just discussing the RFS for architectural services and stuff. So essentially, the subcommittee is going to be made up of Kerry, Selina, Glenn Hoffman, to be determined, and Acklin, and then it will be four members from school department. most likely principals or pre-school coordinators or something like that.

Right?

Speaker 6 (35:16–35:23)

Congratulations.

Speaker 2 (35:23–36:29)

Just a quick recap for the RFS for architectural services. Probably by our next meeting, we're going to have some type of mainly because you look at the timeline it took to get an OPM under contract. Sean Burke's with us tonight remotely on Zoom. You know, it's about a two month window.

So we'd like to ideally have an architect on board end of January, beginning of February. So we've got to kind of get moving on the architectural RFS and stuff like that. Am I correct in recalling that you sent out a sample? Correct.

Yes. working on, and Sean you can jump in if you want to, so he started working on what a sample one from Oakland looked like with kind of the overall program of what we're doing and stuff like that. So then that's, it's a draft one that I sent out. We're still going to get Nick to review it and weigh in on it too for contractual language and then town council, their office to look at the contract.

Speaker 8 (36:30–37:00)

Yeah, the question is, you know, what contract are you going to use? You can use the basic contract for architect services through the MSBA, which is a pretty standard contract that you can pull out MSBA specifics if it's on an MSBA project. And then if you're not using an MSBA designer selection panel, the town needs to adopt designer selection procedures prior to advertising the bid. So it's pretty straightforward.

There's nothing really challenging about it. It just has to be done. There's a process that needs to be followed and needs to be done in order.

Speaker 9 (37:01–37:54)

Thank you. Can we just walk through the timeline? So if we want them on by January, we'll say February 2nd rather than Friday. Once we post it, we need to get three weeks for responses.

And then the in-person interviews, And we made the decision there and make the recommendation to the select board. Maybe that week, maybe the following week, I think we're going to hit the holidays here. So it kind of depends. Assume that's like all together kind of five weeks from the point in time we have the RFS.

How long is it going to take us to put together the RFS? I think it was a little bit longer than that.

Speaker 2 (37:54–39:58)

Yeah, probably. Yeah. I think we had a week or to evaluate and make recommendations before we got to the interview process. Then we had to go through the interview process to make recommendations to the select board.

six of those courses, eight weeks. So we don't have eight weeks to get the notes. No, no. Well, I mean, that's where, you know, for me, this is becoming more real quicker.

December is coming around, though, like we need to, you know, the math you're doing, you have to be where you're going, but this is why I'm like, yeah, we're going to need to jump on this fairly quickly. So I'll be talking to Nick. leading up to it in our next meeting. When we get there, my goal is to kind of have one solidified.

So the, I'm looking at the overall project schedule. When we put the RFS into the central register for OPM was the 27th of October, I mean of August, sorry about that. So if you look at that, you know, beginning of September, call it, and now it's the beginning of November. So it's six weeks, you know what I mean?

And that was from when we issued the RFS. We still have to get to that point to build it up. So I think for us, knowing specifically it's going to be over the holidays soon, it's probably going to stretch longer than six weeks because you don't get many people able to respond to things that quickly. So I think for us, you know, a realistic one probably isn't February 2nd, but the end of February.

So I don't think we can put together pretty quickly. This is the outline that Sean sent out. It's a real good baselining. I mean, it's drafted well.

I think we need to customize it a little bit for our needs. You know, there's a lot of things in there for a feasibility study that we have to balance with what we think we can get done for our budget. So, you know, maybe prioritize the things that have to be done for the budget versus the things that we can let go a little bit longer.

Speaker 8 (40:00–40:01)

But other than

Speaker 2 (40:02–42:56)

Other than that, I think it's, you know, maybe the other thing we need to do is put in that specific timeline of our goal to get to what are the things that we need to get through town meeting and approval. That's really what this is all for. So if we can highlight that and put that timeline into it, I think there's not much else The one thing that came up when I was looking at the RFS is, and I think we do want to do this, and I'm open to suggestions, but, you know, most of the time when we asked for the additional funding for this, we assumed a 25% discount because we're not going to go with the duration that we would do for these things. I think it would be good to kind of list and we have to come to some agreement probably by our next meeting, but we can discuss it now, is what that contract value is going to be.

What I mean, because we've got PMA now, once we go up to the select board with this recommendation for 160,000, we have other things that might come up for appraisals and stuff that would, you know, take out some more of that funding. What do we have left over and how much do we want to spend? Do we want to spend all of it on the architect right now for this? and keep something in case something pops up because I think as everybody knows with this project there's always something that pops up and having a little bit of money in reserve because I don't, you know, I'm not anticipating in May to ask for additional funding again.

So this type of funding that we have would at least have to write us out until after, until next December or even further to next May. So after we execute this contract, do everything there, what additional funding do we need to keep in reserve to kind of make it through, you know, call it September till So those are the type of things, for us, I think we need to look at, and we're talking with the architect, they're thinking of this RFS, you know, what dollar value to put on it, and figure out, you know, how much we're gonna keep in reserve, what do we spend it all, and then, you know, see where we're at at the end of the day with that, too. And you think the budget we have now is the last time, right? My guess is, typical appropriations are done in May.

I don't believe we'd be asking for additional funding this May. Again, it's open to the committee. That's just my read on it. We've got a funding article this December, so I would assume it would be May 2025 by the time we ask for additional funding for, you know, these design services or anything like that along these, these that are there.

However, you know, depending on how all of this goes at some point. It could be funding earlier or something like that. I don't know.

Speaker 9 (42:57–43:26)

I think if we said it was our goal for our funding to last us to May 2025, we reserve the right to have that discussion and make a request a year from this December. What are your thoughts on that one? I'm sorry. If we said our goal, our stated goal, is to not request for anything further until May 2025.

But we may come, we may find that we have a need to come back in December 2024.

Speaker 6 (43:26–43:32)

Yeah, we need to, we're gonna need more money before May 2025. Yeah, I agree.

Speaker 2 (43:32–43:43)

I think that what we need to do is for us to high level identify what we need to do.

Speaker 6 (43:46–44:00)

Make sure we get money for that. I agree with you, we should be going for money every time. But I'm afraid the amount we mentioned may not come to that goal.

Speaker 8 (44:01–44:05)

We already locked into that goal. We asked for more.

Speaker 2 (44:06–44:40)

The $405,000? Yes. Can we ask for more clearly amended formality? Potentially it could get amended, but I think that would cause some probable controversy.

If we were to amend our number, or our ask, then we would go through all the votes again. I'm not sure the support would be there to do that. That's just my read on it. We could, at the back end, as well, to suggest that we would remit the request for the act to whatever we can find.

Speaker 5 (44:40–45:21)

I mean, you know, I think what we've said is that this is the amount of money that gets us through the architect and gets us through the architect, presuming that will be done by the end of the summer and then the fall. And then the question is, at that point, you've got your estimate, right? You've got your design and you've got your estimate. So the issue is joined.

So we may be ready just to go and go to town meeting and ask for So that's the big ask. It's the big ask, yeah. And so if that's ready at the end of the summer, you can see when you can do it next fall or later.

Speaker 2 (45:22–45:31)

And that's right. If we want to spend all the money and go for it, that's kind of what we can do.

Speaker 6 (45:32–45:50)

So that's what I'm wondering, to think about the big ask, what's our goal and how do we work from that? I mean, we both are sort of like, we would like to do it sooner rather than later. And so I like the idea of sort of trying to aim for the fall.

Speaker 5 (45:52–46:20)

We're ready for that. Yeah, I mean, a big ask would be, you know, town meeting and then and then a vote. Right. Right.

So, I mean, conceivably, we do have a vote in the fall of 2024. You know, November 2024 will be an election. And we certainly wouldn't want to to spend more money to have an election outside of normal town elections. So if we have an election in November, that would be an opportunity.

Speaker 2 (46:21–46:33)

I like your thinking. I think everybody does. My question is the money will be lost. Will it take us to having the right document to make the big action?

You know, we left with a good wish.

Speaker 6 (46:33–46:37)

We have $50,000 more because we don't

Speaker 5 (46:41–46:52)

I mean, I think the idea was this would get us to the point where we have a design and a constructs tool, which I think is what we need at the level of design.

Speaker 2 (46:54–47:59)

Yeah, for the most part, it's going to be more than a feasibility study because we've done a lot of the feasibility kind of study baseline there, but probably not a full 30% schematic design. But essentially what we're looking for At the end of these two contracts, the one we have with the OPM and the one with the architect would be a set of construction documents so we can put a hard number to, you know, a realistic, here's what we want to build, have that hard number. And then, you know, once we have that stuff, I'm not sure what we'd have to do. the information we need to make that call up the big ass.

And at that point, we'll be better informed on total costs of the project, what it looks like, stormwater impacts, traffic impacts, stuff like that. Basically, I believe the answer to some of the questions that came up. The big ones is I've always said that every presentation since I started on this, where is it going, how much it's going to cost? You know where it's going.

You just got to figure out how much it's going to cost. And that's what this next effort is for.

Speaker 6 (47:59–48:06)

And I think the last part, which is the impact, right, to sort of the butters that need to be ready to answer that.

Speaker 2 (48:07–48:33)

Yeah. Yeah. Part of the good thing of having Sean on board and or whatever architects there. Now, as we meet with the butters, we have meetings with them, informational sessions and stuff like that.

It's not us guessing on what's going to be constructed or stuff like that. It's the actual people who are designing and constructing it, not constructing, designing and managing it. those concerns that you know will be relayed.

Speaker 5 (48:34–48:51)

As a recent model, we can look to the fire building committee and what they had before they made their ask. Which I think they were designing across an estimate, in that case, for all three. Because the ask from the fire building committee was for all three.

Speaker 2 (48:53–49:40)

This whole discussion too is predicated on the fact that we don't get accepted to MSBA. So if we didn't get accepted to MSBA, this is kind of, I think, what our path is. If we do get accepted to MSBA on the 14th of next month, then we get a kind of reset. And it's a good thing with the RFS for the architect that we don't have them on board or under contract with them or anything like that.

And that if we do get accepted on the 14th, it gives us enough time to kind of pull work with the OPM to try to figure out how we best navigate going forward and then make a decision after that. So that's one big decision point I got to put in that. And that the land swap goes through. And that the land swap goes through.

Correct. And in July.

Speaker 10 (49:40–49:43)

Yeah. I said and that the land swap goes through. That's another big.

Speaker 2 (49:43–49:49)

I think the land swap. I think Kerry is referring to the special legislation.

Speaker 10 (49:49–49:51)

The special legislation. Yeah.

Speaker 6 (49:53–50:10)

we could line up well with everything else we're trying to do. So that's what I see we really need to put comments on. It should really reflect what we're trying to do as far as getting to a ready for an election of next November.

Speaker 9 (50:11–50:46)

Yeah, I think I'd also lean on Sean to provide that guidance, like what do we cut, right? What do we cut? Like, you know, what is the schematic design? Sorry, Sean, go ahead.

to help provide, based upon the funding that they know we have, what are the things within this we should be pulling out. Obviously there's some costs like the cost estimate, we cannot get rid of them.

Speaker 2 (50:46–51:00)

We can't get rid of them. Sean Burke, while I do have you on the line, the RFSC is sent over to, for like services, the architects would be providing also that cost estimating, but that would be you guys, correct?

Speaker 8 (51:01–51:08)

We would have a third party estimator. We already have them lined up with quotes to provide early estimates for us, yes.

Speaker 2 (51:09–51:14)

Yeah, but for the architects, they wouldn't have to carry another estimator under their contract.

Speaker 8 (51:14–51:56)

It's up to, it's really up to you. MSBA requires two estimates. Early on, it may not be necessary if you're, it depends what you're trying to do with the number. If it's a ballpark number to get you moving to the next phase.

So you can present to the town. Maybe not. If it's a number that you're looking to go to a vote with to approve the entire project, then maybe it is a good idea to have a check estimate there early on talking on estimate. You're talking 10, 15 grand.

It's not a ton of money, but it's not all that detailed either. It's square footage based on very high-level design, how many rooms, really early in site numbers. It can have a benefit to it, but it really depends on what you're using it for.

Speaker 2 (51:56–52:06)

Yeah, I just started on there. I just wanted to make sure having two is fine. What you just described is perfect, so no comment on that.

Speaker 8 (52:07–53:32)

Yeah, the as far as the cost goes, we've been talking to some architects, and I think as far as money go, they talk about like a full SD package through all the way through fully developed as 1% of the total estimated construction value, which would be more than you have. So I think if you're looking to do it at the budget, they're going to have we're going to have to. come up with the scope of work that's appropriate for them using what you've already done to feed into their, you know, to what they want to do. An article 97 is going to require a MEPA review, it's just by statute, it's going to require, and then this site's going to require a lot of study, so it really depends how much upfront you do.

If you don't have the money, you're going to have to do that in a later phase, which is okay as well, but just to tailor the expectations to the funding available. When we talked to some architects early about this project, They would want to do even more than a feasibility study over the next nine months. They would take you all the way up to maybe a DD. But the amount of money to do that is significantly more than I think what you're budgeting for.

And their minds are looking to push the project and get it as fast as possible. But I think the committee is probably correct in that if you don't have the land under agreement yet, that might be a little bit premature because you don't want to go ahead and start designing a building on land that isn't yours to build on by right yet. I think by the time we get to May, we'll have a pretty good idea of how much funding we need.

Speaker 2 (53:32–54:18)

And we'll find out a lot going through the, just bringing on the architects. I think a lot of the interviews need to be based on what services they can provide based on how much money we have. And that'll tell us something. And then the feasibility can go that quickly.

Maybe by Maytown meeting we have. you know, not enough to get anything voted on, but enough to give an update of what to expect in the next couple of months in case we need a special vote. We have a good group, but I think we'll have to do some sort of presentation because, well, we've had a pretty good spot. You know, we can say we're two months away from having a completed feasibility study and the land swap approved.

We're going to be ready to go at that point. It looks like you're presenting it to me. You're ahead of me. I like that.

Speaker 9 (54:19–54:39)

The issue with this is going to be The RFS, we can't take costs into consideration in the selection of the architect, right? It's a qualification. Right in the RFP itself or the RFS, it lists the way you can show it as an element. It lists what the budget is.

It cares what the budget is, yeah. Right.

Speaker 2 (54:39–56:02)

So that's, we're basically saying this is how much money we have. These are the services we want for it. You tell us whether or not you, can provide all those services for that budget or let's prioritize the services that we can do for that budget. That's why the interview is going to be really good.

Yeah, it will probably be good. I'll see if Nick's available to attend the next meeting just as we're diving into this for some of these questions too. I met with Nick and John to talk about the list at one point, and it was mainly just to review high-level stuff. And with that, the same question came up.

Do we list it and list an allocated budget, or do we just leave it open, as you mentioned, similar to what we did for the OPM? So I think we have the ability to go either way. And that's why we're going the way, like I was saying, we should come up with what that dollar value is. So we're all in agreement, whether it's all the funding or the majority of the funding, however we want to do it there.

So whatever it is, it'll be the same for whatever it responds to. So then it'll be really important for the subcommittee to be leveling that scope, because the firms will look at it and say, OK, well, we can do something for this amount of money, and here's the something that we can do.

Speaker 5 (56:04–56:13)

And the benefit of anything was something they know he wasn't in the school building authority. He was prior to John, but he had some facility with these things.

Speaker 6 (56:19–56:23)

Any other questions, comments on old business? That was the last one.

Speaker 9 (56:24–56:37)

Sorry. Our next meeting is, at our next meeting, you're for this, for the architect thing. We expect to have a kind of initial draft. from Schomburg.

Speaker 2 (56:37–57:19)

I think that would be our goal. Between Nick and Sean. Between Nick and Sean. Yeah, because the previous RFS was involved by Nick and his assistant, Colin Collins, along here.

Yeah. Hopefully, after the next board meeting, he'll put him under contract. Yeah. So we can start.

Schomburg, sir, please. They can work together on standard language, have the town contract officer review some of the stuff that's there. I think the big one that Sean Berg mentioned is the MSBA language. Do we keep it in?

Do we keep it out? We're trying to find some hybrid in there that allows us to escape from it if we're not selected.

Speaker 9 (57:19–57:34)

Yeah. So we'd have a draft on the 27th. We'd discuss it. We'd have edits and feedback we'd need to consider.

following the week, because we need to finalize the draft.

Speaker 2 (57:34–58:26)

We need to select four to go. I can't remember. The following week is town meeting on the 4th. Yeah.

So I think our goal would be on the 27th to have it final. So, you know, working with Nick and Sean, you know, together, and then through individual emails, our group emails, for that, send me your commentary. So typically I always send these out, as you saw, I BCC everybody, so nobody can reply at all. So there's no meeting log thing.

Everything comes back to me as individual edits, and then we can kind of run through those, incorporate stuff that's there, and then ideally on the 27th have a pretty final one that's there. And if we have to make live edits there, we can make live edits at the meeting too, you know what I mean?

Speaker 12 (58:27–58:30)

So he's been staying there.

Speaker 9 (58:30–59:06)

Yeah, I mean, I mean, we probably would want to draft sent out to everybody to review by next Monday or Tuesday. Yeah, I was thinking of the next Monday. Yeah. And then the week would be great if we could do that.

So we finalized by the 27th. and they're yelling at me or something like that. So we haven't finalized on the 27th. Does it need a select board approval?

Speaker 5 (59:06–59:16)

So we recommend a select board, select board that hopefully meets the 29th. We meet on the 28th.

Speaker 9 (59:16–59:24)

Yeah. So it goes out the bin on, it's posted on like the 29th, 30th.

Speaker 5 (59:25–59:42)

Presumably, some actions taken by this group doesn't take action.

Speaker 2 (59:43–59:54)

Yeah, for example, the PMA contract that we voted on earlier is on their agenda coming up as a basic placeholder. If we didn't vote on it, they would just kind of skip over it.

Speaker 5 (59:54–01:00:04)

Yeah, we've got it on tomorrow night. So Sean could be on board as early as Wednesday.

Speaker 2 (01:00:05–01:00:11)

He's already working on it, which is a good thing.

Speaker 9 (01:00:12–01:00:25)

Great, and then so again, three weeks takes us essentially to the 21st, which, yeah, maybe we ask for it to be done by, before the holiday break by the 22nd.

Speaker 2 (01:00:27–01:01:37)

We're not gonna review anything probably in that period of time, so. Yeah, I think the scheduling that you're doing right now, I think we can leave that to Nick and Sean to develop one. Our goal, I think, is sometime in February to have an executed contract with the architect. So what that might mean, too, is our meetings have been pushed off the execution of the contract.

We've interviewed PMA a couple of weeks ago. It was presented to the select board. It was just the timing that it took to get us this long. We can fast track some of these meetings and have a dedicated meeting to review the RFS or the architect contract for there and then follow along with the select board after that to kind of fast track this end of it.

But I agree with you. Selecting the work they have to put in to develop proposals, submit the proposals, review them, score them, shortlist them, interview them. That's where the meeting every day is.

Speaker 9 (01:01:41–01:02:06)

Yeah, I just think every month, every pre-op, it's all really going to matter. I mean, if we need a town meeting, the town-wide election is in November. Town meeting, I assume we do a vote before town-wide election. The election is next November, correct?

There is an election, yeah. Right, so there's an election next November. If we had a vote during that, so we'd want to do a town meeting vote before the town-wide election?

Speaker 5 (01:02:06–01:02:24)

Yeah, you typically do. I don't think you have to. I mean, it's possible to do the town meeting after, but typically the normal course is to But it's not, I don't think it's, as I recall, it's not a requirement.

Speaker 9 (01:02:24–01:03:17)

You can do the town election first and then subsequent town meeting. I guess the thing I'm just thinking of is, again, the community engagement piece, which can start a little bit, but it starts even more once we have kind of a more robust plan, right? Once we get it right, we're going to do the schematic design. And so at that point, not just two weeks, but probably a few months.

So I have multiple information sessions to get that information out to folks. And so that means that essentially it's starting in August. So we need to have something in the summer month, you know, not as much gets done. So all of those things just compound.

It keeps me up at night. Because the beginning of March versus the beginning of February, middle of February matters, I think. So I guess I'm going to try to get good feedback and make a lot of the alerts.

Speaker 2 (01:03:19–01:05:41)

And then that's where for me, you know, as I was looking through these, I'm looking at, you know, overall schedule, just onboarding the architect and stuff like that. And I didn't want it to overlap a lot with holidays because everybody knows, you know, that makes it a little bit tougher. But, you know, we got to get this done. The RFS, one thing I would say, I am a proponent of letting them know what our budget is because otherwise, We'll spend, we'll bring them on board and we'll spend them off trying to figure out what they can do for what money we actually have.

So we just tell them upfront and put a plan together as part of the whole process. I think that I support that, that it would make us scoring a lot easier than doing the budget work in YouTube. So one says, I only do one item, but you're scoring yourself out, right? I'll push Nick and Sean and myself to get this RFS there.

That dollar value, what I'll do is send out to everybody, here is what we have budgeted, assuming the article passes the town meeting, I'm not making that assumption. And then the money that we've allocated for PMA, money that you have to allocate for the appraisals, potential surveys, like I said, in the EA land, and whatever's left over. And then whatever's left over there, that's money that we should decide as a group what dollar value we want to invest in that contract. We'll discuss that at the end of the session.

Correct. We'll be live at the next meeting and we'll have all that and there'll be a blank number that we'll put in there. And then we'll figure it out in that meeting what that number should be. Just in case I missed that, let's not log in such that when we pay the OPM, I'm paid.

The architect, no money spent at all. You know, just a lot of money, just a lot of money. It's always doing more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and more and

Speaker 6 (01:05:41–01:05:57)

We were just talking about approving the RFA on May 27th. Our next meeting. But we don't go before town meeting until the 4th.

Speaker 2 (01:05:58–01:06:20)

So is that putting one thing before the other if we are trying to issue something with an Approval but not issuing it until after guidance. Correct. It would be a disclaimer. Very good one.

Speaker 6 (01:06:27–01:06:31)

Any other questions on the architectural services?

Speaker 2 (01:06:32–01:06:46)

Seeing none. Item 5A. the school committee facilities subcommittee update on temporary space per user.

Speaker 9 (01:06:47–01:10:07)

Great. It's called the facility advisory committee, not a subcommittee, and that's important for the board. It is. So facility advisory committee is a group of members of the school committee, the school public school system in Philadelphia, and Peter Burroughs, and then a number of community events that engage members of the community.

So we've done, we did walkthroughs of all the school sites earlier this year. We did a full day of visiting, looking at things, been talking about temporary space. We're working on the capital improvement budget, facility capital budget with Chris Hayden facilities and we have an initial plan. Some temporary space needs.

to do something with the board floor coming in that seems to be kind of unanimous across the committee to look at that. The other thing we're talking through is just other ways to kind of pull out ancillary services from the schools, given the spaces are so tight. Other ways to give space back by pulling other pieces out, such as, you know, central office from the high schools, give the high school a little more space. So things like that, and then the third area is like.

Are there alternative sites we can temporarily put part of our programming, such as the pre-K programming, off-site in order to gain some space across a few of the schools that would help Tucker and Cunningham. If you help Cunningham, you kind of help Cali Cop by connection. So those are the things we're all simultaneously investigating and working on. But the key thing that's coming up in our meeting on Wednesday is the capital improvement budget and kind of what we can do to get some funding, we can put towards this.

A member of our ECO school committee member is the other school committee member on the committee with me. And I'm also looking into some of the temporary pods, modulers, and I've talked to a couple companies about that. That hasn't, to this point, seemed to have gone anywhere due to some costs, but it's still something we're looking at and looking at. But all the principles continue to, which I know on the table, like just space is really hard, especially like just meeting space, office space, small group space for kids, not to mention just classrooms, just classrooms are getting bigger.

It's slightly easier to manage when you just make classrooms bigger, but you know, you just need, if you have more kids, you can have more services and you just need physical space to provide those services, and that's something that's not as easy at this point, given all the spaces we've taken up. So that's it. Any questions?

Speaker 6 (01:10:07–01:10:21)

You might have questions, but what you're doing is great and happy. We've taken on that challenge, but maybe we want to draw from past history.

Speaker 8 (01:10:21–01:10:23)

One of the roadblocks

Speaker 6 (01:10:23–01:10:37)

discussions on this issue many years back was the, if I remember correctly, the bottlenecks were like the, where they eat, what's the right name?

Speaker 2 (01:10:37–01:10:43)

The cafeteria. So actually free up space which would potentially allow more plates.

Speaker 6 (01:10:43–01:10:59)

The bottleneck then was kind of decreased by I'm not pushing back against it, I just want you to be aware. Once you plan, you take that into consideration, because you probably cannot expand the criteria. Yeah, just take that into consideration.

Speaker 9 (01:11:00–01:12:41)

Totally agree, Akbar. Yeah, I don't see those as temporary. space needs, because the only way to do that is to do enormous construction projects, to expand cafeterias across multiple sites, or expand gymnasiums across multiple sites, or build new bathrooms across. And that's not temporary.

That's very much permanent. And so to me, the solution to that is this, right? Is the new building and the school. The solution is to pull some things out just to give a little bit more breathing room.

The kids are there. It's not adding more kids in. Unfortunately, they're kind of suffering through it as they are. So it's how do we provide them some reading room and how do we provide some flexibility in a situation which especially like Cunningham, which has some of the substantially separate like green school programs or other programs where student teacher ratios are very strict and you can't just add another kid in.

You have to physically create another classroom. And so what happens when the threshold and now it's only two more kids but it's an entire another classroom that now and we can't put those kids in closets right there's all kinds of federal protections on those so you gotta put them in a real classroom and probably kick a different classroom over to the the library or somewhere else so like that resiliency piece is the other thing we're looking at and so You know, putting up more permanent walls in some of the library spaces too, where they've had temporary walls for years and years now, is also something we're looking at. Just make that more resilient. Thank you for the work.

Speaker 6 (01:12:41–01:12:48)

Any other questions, comments?

Speaker 2 (01:12:50–01:13:29)

Agenda item six. As we mentioned already, Monday, November 27th is our next planned meeting. I didn't list anything after that because essentially we had a town meeting on the 4th. But I think, you know, just to be safe, we'll probably hold the 11th.

December 11th as just a placeholder. Right now, we'll know better more on the 27th. But just in case everything for this RFS doesn't kind of go as planned, I would just say expect the 11th just to be safe. We don't have any calendar.

If we don't have it, I'll cancel the meeting quickly.

Speaker 9 (01:13:30–01:13:34)

Do we need a vote on the group for the subcommittee?

Speaker 2 (01:13:35–01:13:52)

I don't have it as a vote on here, I just wanted to discuss it. Yeah, but we should vote on it. And if you could just remind me of that when I'm putting the agenda together, like when I set out the draft, if it doesn't have that on there, yell at me.

Speaker 5 (01:13:53–01:13:57)

I couldn't vote going on too many.

Speaker 2 (01:14:01–01:14:29)

Yeah, I talked to Glenn earlier just to give him a heads up. He was meeting with the principal, so I just told him, I was like, for the subcommittee, this is going to be our asset. Like the timing was, he was like, yeah, I'm going to be into a meeting now. Perfect timing.

That worked. So I think for future meetings, we're good. Any other questions, comments? This is a placeholder.

Speaker 5 (01:14:29–01:14:37)

Yeah, maybe that may be the second item. I thought it would be the fourth.

Speaker 2 (01:14:37–01:15:14)

Yeah, it was scheduling issues. Okay, so then. Not even later that week, I'm thinking the 6th or 7th, maybe. Yeah, okay.

I apologize. I was blocking out the week of the 4th, mainly for town meetings, but it's stretching to that. I think the 27th will give us a good idea of kind of where we're at. And then if it has to be the 6th or 7th, which is the following Thursday, Wednesday or Thursday, we'll know that on Monday and I can post the meeting pretty quickly.

Speaker 9 (01:15:17–01:15:21)

the whole town meeting will be just in and out.

Speaker 5 (01:15:21–01:15:29)

I don't see any reason. Yeah, it's not much. Yeah, your presentation.

Speaker 2 (01:15:32–01:16:24)

So, okay, we'll probably aim for the seventh. I would say, you know, we'll know the 27th better and we'll discuss that on the 27th when we get here. So all our meetings are still here. Glenn Pavlicek also let me know that the high school, the school committee we've known actually sat at the studio before is now open for us.

So we want, if this works well for everybody, we can bring it in the air. We want to be able to open public access and be in a bigger room, we can do that. let me know if there's anything to, you know, for me, I think this room works fine for us, for what we're doing. Yeah, it works great.

Speaker 9 (01:16:24–01:16:30)

Okay. School committee's going back over there on Wednesday, so we can let you know if it's nice.

Speaker 10 (01:16:31–01:16:39)

I think we'll be adding people, though, to your team. We'll have Sean and maybe, I don't know if that's new.

Speaker 2 (01:16:39–01:16:41)

No, that's a good point, yep.

Speaker 10 (01:16:41–01:16:43)

Because we don't have fun here.

Speaker 2 (01:16:43–01:16:59)

Yeah, the only one we're seeing is Glen. That would be a full table. Yeah, and the other way is maybe we hold the 27th meeting over there if it works fine. Test drive it and see if it works.

If we like it over there, it's more space that we can do that.

Speaker 10 (01:16:59–01:17:23)

One thing, Glen… Going into cold and flu season, I don't really want to be cramming in with a million people and just throwing it out there. No, that's… Exactly.

Yeah, good ventilation in there. Something I know is dealing with ventilation. I just know that every time I've gone in there, it's freezing. So dress warm.

Speaker 2 (01:17:23–01:17:51)

So I think that's it on future meetings. Item seven is adjournment. and there's nobody remote anymore, so. All in favor.

Yes. Thank you very much. Have a good night.

Speaker 1 (01:17:52–01:17:54)

All right, thanks.