Board: School Building Committee

Date: 2026-09-28


Transcript

Auto-generated; may contain errors.

Speaker 1 (00:18–00:20)

All right, good evening.

Speaker 2 (00:20–00:38)

Welcome to the Milton School Building Committee. It's September 28th at 7.04 PM. I'll call the meeting to order. As I typically do, we just basically take roll call attendance.

I'll start with people in the room. Bob Mayhew? Yeah. Peter Obersheimer?

Speaker 3 (00:39–00:39)

Yeah.

Speaker 2 (00:40–00:46)

Glenn Hoffman. Here. Tim Lombard. Here.

Online I see Kerry Hurley.

Speaker 4 (00:46–00:47)

Here.

Speaker 2 (00:47–00:50)

Nathan Hutto. Here. John Redden.

Speaker 5 (00:54–00:54)

Here.

Speaker 2 (00:54–01:57)

There we go. And Mark Loring. Here. Make sure I haven't missed anybody.

All right, cool. Second thing on the agenda is citizen speak. So we reserve the first 15 minutes of our meeting for any citizen that would like to speak. If you're online, please just raise your hand.

And when called upon, please just state your name and address for the record or for the minutes. Seeing none, okay. Moving over to agenda item number three, which is discussion approval of meeting minutes. So I know, Seamus, you sent out the ones for the last meeting.

I still owe the July ones. So those are the So I'll let everybody take a minute and see if they have any comments or questions on the previous meetings, minutes that were sent out.

Speaker 6 (02:18–02:23)

Any comments? A lot of silence. Good, okay.

Speaker 7 (02:23–02:30)

Open to any move to approve the September 14th meeting minutes.

Speaker 2 (02:32–02:59)

Second. Second by Tim. Any discussion? And hearing none.

Glenn was actually the second, but I can second if you need me to. That's fine. Second by Glenn. All right, roll call vote because we are hybrids.

So, starting here, Peter Robesheimer. Yes. Glenn Hoffman. Yes.

Tim Lombard. Yes. Kerry Hurley.

Speaker 4 (03:00–03:02)

I was on there. I abstain.

Speaker 2 (03:03–03:07)

Nathan Hutto. Yes. And Mark Loring.

Speaker 8 (03:09–03:09)

Yes.

Speaker 2 (03:10–05:06)

All right, cool. Moving forward, agenda item number four, old business, item A, discussion, MSBA designer submission reviews. So as we talked about at our last meeting, we received four submittals for a designer that we're looking to onboard at an upcoming MSBA designer selection panel. So that panel, Uh, is made up by 3 representatives from the town, which include myself, Glenn Hoffman and Mark Loring, and we'll be partnered with you guys during that whole process too.

So, I know Seamus has sent out essentially 4 packets that were there and we asked you guys to kind of look at them. Kind of what I want to do is just. Let's figure out the best way to walk through this. Let's start with the first one that I was looking at, which was the one from SLAM Architecture.

I'll open it up now. What we'll do is we'll just walk through each one, give some pros and cons, what you guys saw. Overall though, at the end of it, the process, what we're doing with the MSV designer selection panel is going from four to a less amount, so either three or two, right? Probably yes.

Okay. So I'll open it up just for members, you know, give some pros, cons, or whatever you saw for SLAM.

Speaker 9 (05:06–05:12)

Are you looking for folks to comment not on the subcommittee tasked with looking at this?

Speaker 2 (05:12–05:21)

For the most part, yeah, just everybody, or even if you're on the task, too. I mean, it's calling an open house of just comments that we're looking for right now.

Speaker 9 (05:22–06:05)

I mean, I thought it was, were you just commenting on SLAM right now? We're going to run through each one. We're just doing SLAM right now. I thought SLAM had a well put together presentation that was aesthetically very pleasing.

They definitely appear to be architects. I think that they came in with, they demonstrated that they've been following our process, you know, and sort of the parallel paths that we've taken over the course of time and the iterations, so. I think that was more evident in their proposal here than others that I read.

Speaker 2 (06:05–06:18)

Anybody else?

Speaker 7 (06:18–07:09)

I thought they had a good message in their narrative around sort of their process around understanding the educational needs before evaluating facilities, how building community consensus informs their decision-making. I thought it was just a very natural explanation of how they do business as a clear pro to me. I think they were all four really strong. One that caught my attention perhaps going the other direction was Slam.

Others could correct me if they saw it differently, but I thought that their representative examples were a little heavier outside of Massachusetts than the other.

Speaker 10 (07:15–07:18)

Yeah.

Speaker 4 (07:19–07:20)

Sorry.

Speaker 10 (07:23–07:50)

I agree it was a nice presentation. I thought it was heavy on the elementary side. It's my comment. They only used one example of a middle school.

The Greenwich was so it was not a state middle school. which would be, I'm assuming they have different programmatic requirements in Connecticut than we have here in Massachusetts. It all was a really good presentation. It was PMITDI and as an architect, I appreciate that.

Speaker 2 (07:50–08:37)

Anybody else before we move on from SLAM? I gotta admit, when I saw the name, it was interesting. I mean, it's a great name. It sticks.

It's a great name. Great. Appreciate that feedback. So the next one I'll bring up is, let's go with, sorry, JLA, I'm trying to remember what the acronym is for, Jonathan Levy Architecture.

So open it up, you know, for the committee just to, liked, what they didn't like.

Speaker 7 (08:47–09:44)

There's a lot of aspects I liked about their description of their approach. I will say that of the presentations, this presentation, the most made me think about weighing the trade-offs of the different locations. I felt like they, even in a few pages, A few times made me kind of pause and be like, oh, that's like an interesting way to kind of frame when they were talking about the different sites and the different projects at each site. To me, that previewed like a nice facilitator for considering tradeoffs for a town.

I like what they're able to do in a small amount of space. Also, with their prior experience, it jumped out at me with their Driscoll project. There was 50 public meetings. Pawtucket, 20.

where I view community engagement as sort of like a big thing here, they seem pretty strong there.

Speaker 11 (09:50–10:42)

Nathan, go for it. Thanks, Sean. I was going to mention the community engagement piece that Pete just mentioned. Just two things I'll note that were sort of question marks for me.

It wasn't – I saw in their sublist who they would bring in for – I forget what it's called, but sort of like education. But it wasn't really – the other proposals went quite a bit deeper on how they would approach the questions of sort of educational design for the school. I didn't really get that from JLA. Unless I misread it, I think three out of five of their references were non-responsive.

Speaker 2 (10:43–10:48)

We'll go to our OPMs to confirm, just to make sure.

Speaker 12 (10:48–11:21)

Yes, typically we require for reference checks, we typically would reach out to three, and we're really looking for two good or excellent responses, and then we'll stop harassing people and stop chasing. So we did get two excellent or good references for them. So that's when we typically stop our kind of exercise of like chasing people. So it doesn't, but you know, the references we heard back from did reflect on them.

I think they're excellent. So, but you are correct in that.

Speaker 13 (11:21–11:26)

I think out of the five, we reached out to two respondents.

Speaker 4 (11:26–11:52)

Correct. And I would point out that one of the two is a school committee member that's also works for LaMesure. So the person who gave a very extensive review on that, comes from a very reputable structural company. Knows his stuff.

Speaker 6 (11:52–11:53)

Anybody else?

Speaker 2 (11:59–13:12)

All right. So the next one we'll go to, we'll go with DLR Group. You know, just from our past work recently with the LR group, I think everyone has, you know, a good comfort level with them. And I just highlight that because, you know, part of like for me when I was going through this too is, you know, the two sets of architects we've had up till now have done really good work.

But, you know, for me, when I'm looking at this too, I'm also looking for fresh perspectives because, you know, We've got, you know, this is going to be a big project. I think having other looks at different things that we've done before is important, not to take away from the work that was already done too. So it's just, you know, when we're looking at these, I just want everybody to, you know, have the understanding and stuff like that, but really just to kind of dive into these. So with DLR group, I'll open that one up for everyone.

Speaker 11 (13:23–15:28)

Nathan, you're up. Sure. I don't need to go first, but I just figured I'd kick us off. Just looking at our notes here, or my notes, sorry.

You know, overall, I thought it was a very strong proposal. They know us, and so, you know, we have more information on them because they've worked with us before. When they did work with us, I was very impressed at their sort of working knowledge of kind of innovation in school facility design, and I thought that came through in this proposal. They seemed to understand.

They just spoke to a few particulars that I think some of the other proposals didn't get into about the degree to which different options would alleviate or not our crowding challenges. A couple of their examples, at least my interpretation and some of the designers in the room might say otherwise, some of the examples they shared kind of illustrated the interplay between the built school and the natural environment around it. Both at Guile Road and at Labouret, there is a lot of kind of natural beauty surrounding those sites, and I think it'd be interesting to… They also, like, the proposals, the projects they listed had sort of great changes that were interesting, and probably hit play on both sides.

The one thing I, you know, DLR stood up to me as having a lot of projects not in Massachusetts. I think they're a national firm. I think I just wanted input from the group and maybe the PMA group about how much that matters in this decision.

Speaker 13 (15:30–16:06)

I think not in Massachusetts is less problematic than not having done MSBA projects. The MSBA system is robust. There's a lot of submissions that have to go on to the MSBA process. Knowing that is certainly helpful.

Having an architect that's gone through that before and has done it a few times for a project of this size and complexity, it's certainly a big benefit. I do think that they have some designers here, if I'm not mistaken, that have worked for other companies that have done MSBA projects, but they just, I don't think they can use that on their submission because they're not DLR group.

Speaker 9 (16:06–16:23)

But, you know, Shenali came from- I think they did include, so like you're referring to something like Swanham School, which appears in their proposal under Shenali, having worked for- For Ericsson. exactly what you're speaking to, MSBA projects, that's a very current project.

Speaker 13 (16:23–16:28)

Right, so that's what would be more important to us, is to have people who have done that process before.

Speaker 10 (16:28–17:35)

My other concern is the project that I was sent from Massachusetts is a renovation project in Cambridge, which is a very different animal than we're dealing with here. And their credentials, too, they didn't list where they were educated, which I found odd. The reason I bring it up, and it's not a snobby thing, I went to the Boston Architectural Center. I did not go to an elite architecture school.

But certain educational backgrounds lead to certain styles, so to speak. That's why I was curious that they didn't list that, because they usually don't. Yeah, I agree. I don't think the out-of-state thing is a huge issue.

I think the MSBA thing is a huge issue. Massachusetts is pretty unique in how we do things. Are we still the only state in the union that has file sub-bid laws? I think so, right?

Little things like that. There's things in Massachusetts you don't see in other states, and they're big issues. If we go see them at risk, it's not a non-factor, it won't matter. But they still filed something.

It's still filed something. It's wrong.

Speaker 2 (17:36–17:42)

Just something to keep in mind. Okay. Kerry, you had your hand up. I apologize.

I missed you.

Speaker 4 (17:42–18:24)

No, that's OK. The one thing that I did note, I had a similar question about not a lot in Massachusetts, but also I know we're familiar with Shonali and Jonna, but Shonali was showing that she is only 50% available for our project. I just want to point that out. And Jonna, I think, was 60%, which is the principal.

I don't know. what's a good percentage, but you know, like, I think it was JLA. I think the principal was like 80% available. Yeah.

Speaker 6 (18:27–18:30)

Exactly.

Speaker 4 (18:31–18:50)

But, um, and I forgot to mention on JLA just Levy, uh, yeah. Uh, the energy and green projects. the geothermal and all of that, I thought was, it appealed to me quite a bit. Sorry, I missed it on round one.

Speaker 2 (18:51–19:00)

No, no, no, no. That's fine. You know, feel free. I was just trying to organize it, but you know, people have ones that they missed and we move by them.

No, no. Feel free to chime in.

Speaker 4 (19:03–19:04)

Yeah. That's all I had to say on that.

Speaker 2 (19:06–19:35)

Okay. Anybody else? Hearing none. All right, our last one that we received was from Arrow Street.

I think he forgot to lower it. There he goes. So our last submittal that we received was from Arrow Street. So, you know, again, I'll open it up just for discussion.

See what people saw out of that.

Speaker 7 (19:37–19:51)

I had a question for the group and I didn't understand what they meant about teaming up with the Rennie Center and MLP as part of the assembly. Is that just the subs or am I misunderstanding something?

Speaker 2 (19:51–20:02)

I think MLP is the educational planner. I don't know who Rennie is. It just might be another sub, but MLP is the educational planner.

Speaker 7 (20:04–20:16)

I mean, it's not obvious. It's just presented upfront in a way that I didn't know if that meant it was like we're not just hiring your street work. I don't know. I didn't quite follow it.

Speaker 2 (20:16–21:47)

The other one that I did too is I looked – so my big one when I was looking at all these is Honestly, all four firms presented really well, so you're trying to find differentiators as you're looking through some of this stuff. The biggest cost, when I went back and looked at our cost estimate that we had for the previous project, MEP is the biggest cost in the whole thing. When you aggregate all those trades together, it's like $34 million or something like that. Yeah, it was like 33 million and a half from that last estimate.

So I put a weight on that, you know what I mean? Just looking at, you know, we got four good, really good architecture firms and like, who are their subs? The one thing I noticed just for everyone's kind of consumption in case they missed it. So Arrow Street had a different sub last time for MEP and they're presenting a new sub now, CMTA, that's there.

Nothing against it, not saying it's wrong or anything like that. And then as I dove deeper into it, Arrow Street CMTA, and I think they had a different fire protection plumbing sub, all look like they worked together either on the Squanam project or the Dighton project that they were doing. So, they must have had good experience with them. So, continuation with the team.

Yeah. And that's some of the other work. And we're not taking a vote tonight, we're not doing anything, but just giving kind of a preview or some of the work.

Speaker 10 (21:47–22:00)

You make a great point though, Sean, because you'd be amazed at how much of your change orders still attest come from MEP. stuff that was missed or not coordinated properly. So having a team in place is a plus.

Speaker 6 (22:00–22:01)

Yeah.

Speaker 11 (22:07–24:22)

Nathan, go for it. So overall, I appreciated Arrow Street's proposal for a number of reasons, but I do want to follow up on On Pete's comment about the Rennie Center, which both got me really excited and raised a bunch of questions for me based on the extent to which they didn't really provide information about what that would look like. The Rennie Center is a education policy and research nonprofit in Massachusetts, probably one of the most important ones. And I've long followed and really like their work.

They're highly reputable firm. It's like a think tank, basically. But it so it looks like and I think I think in their proposal, they referenced that. And so Rennie is working with Dedham.

I think as a direct contractor, so not as a sub to a designer, to do kind of like a sort of, it looks like, I couldn't get all the information, but it looks like a very significant study of their enrollment and sort of cohort patterns through the school, like a really broad kind of school design analysis. I don't know what the questions are that you might answer in that. And so I assumed that by having Renny, I just sort of transposed what they're doing in Dedham to this, and that Renny would be kind of their analytical horsepower on this project to study enrollment patterns and cohort patterns and stuff like that. But I don't know.

And given how much they highlighted it, but didn't really provide any information about it. I was a little bummed. I don't know if we have an opportunity to, we probably can't ask them clarifying questions, but I think knowing more about what that means is really important for… I don't know.

Speaker 2 (24:22–25:46)

It could be great and it could be like a… Yeah, so just on like next steps. list and we're allowed to ask questions in the interview process yeah yeah during the interview process so you know I think That one, Nathan, for your questions, if they do make through the kind of initial cut of the shortlist, that's a question that we can pose to them to get some feedback on it. I didn't catch that because I was diving deep into more of the analytics of subconsultants' costs.

just overall makeup of the teams where there were – for similar sub-consultants on multiple teams and stuff like that. That one is interesting. I only bring it up because of discussion and the next couple of topics we're going to be talking about too. Just in regards to would – I a think tank like this be helpful, you know, I mean, as we're looking through the kind of options that we have at the, you know, potentially two sites right now and figuring out which one, which one would be most advantageous, honestly, from a third party perspective and not, not coming from us.

Speaker 9 (25:52–26:09)

Keep going, anybody else has anything? Am I correct in noticing that they were unique in not listing the specific percentage of availability of their team members? I think so, I'm not sure. I didn't see it.

Speaker 13 (26:22–26:25)

You just know they're available to work on the project, right? Yeah.

Speaker 9 (26:33–26:36)

They do have their educational backgrounds.

Speaker 10 (26:38–26:42)

This is Arrow Street, yes. Yeah. No, they all do. It's very typical.

That's why I was surprised.

Speaker 6 (26:45–26:45)

All right.

Speaker 2 (26:48–27:25)

So with that, you know, let's Honestly, each time when we look at this, there's a new option here and there. The one that the DLR group put together, I don't know if you guys saw it, but it's an option that keeps the road aligned as it is, and has two separate buildings with a bridge across it. It was interesting to see. Moving a road is also that too, which means two buildings, two systems.

Speaker 10 (27:26–27:29)

Great, it would look awesome, but it would be very expensive.

Speaker 2 (27:30–27:40)

But my point is having four different groups of architects look at the problems that we have with these sites. It's cool.

Speaker 10 (27:40–27:50)

It gets us excited. It's not unusual if you see something another architect did, and you liked it, to bring it to another architect and say, hey, have you thought of this?

Speaker 2 (27:52–28:08)

And that's part of this, too. We don't just throw away these options. We can keep them. The selected team, if there's certain things that we like as part of this, for example, the Rennie Center, we want another firm to pull them in as a separate sub-consultant, we can work with that.

Speaker 7 (28:11–28:40)

Yes, sir. The Arrow Street seemed like strong Massachusetts prior examples, although I wasn't studying as closely whether they were middle school or elementary, but just looking at kind of the costs And also, I imagine a high level of familiarity with us, given the prior work on Guile schematics, but I wasn't involved in that. So I don't know how that went, but it seems like a positive.

Speaker 6 (28:44–28:47)

All right. Anything else?

Speaker 2 (28:50–29:14)

Hearing none. The designer selection panel is next week, next Tuesday. Glenn, you and Mark will be on that Tuesday. For you guys, just procedurally, I won't be here, I'll be in Denver.

I've got to double check, make sure I'm not flying home at that time too.

Speaker 13 (29:16–29:36)

If you want to co-locate somewhere, we can open up our office. We can sit at a conference table there. If you think it's better, I know if you're not here, but if the other two members want to be in the same room, we can certainly do that. Just let us know.

Sometimes it's helpful to put everyone dialing to the call together. We're just down in Braintree up to sweat.

Speaker 10 (29:38–29:55)

So I don't know yet. I have a, um, close friend's mother passed away and I may have to go to a wake that night. Can we call in if possible or this is in the morning person. Okay.

Yeah. So it would be a zoom call. We can get it's very much in flux right now. I'm not, nothing's setting stone.

Speaker 2 (29:55–34:58)

Okay. Yeah. Let me, you and Mark kind of coordinate offline and then we'll touch base with you guys. If that means, I know I will not be there, but we'll see if the other two need to be in person.

All right, moving on. So agenda item number four, B, discussion, MSVA pre-KK enrollment discussion update. So at our last meeting, we talked about potentially approaching the MSVA about adding a pre-KK enrollment to our kind of current program that we have now, and there were, essentially four questions that the town administrator asked the MSVA through email. And to simply put it, and I'll do my best to summarize it, and I think the big one is, if the town decides that Pre-K, K is an enrollment educational program they want to roll into this project, how will we do that, and what type of delays would we incur to do that?

So we had the initial meeting with MSVA, There was representatives of the town, superintendent, myself, school committee, and essentially at that meeting, there was discussions back and forth. But essentially what the MSBA does is, those are all call it off the record because they're non-official, and they would respond formally by letter. So we send them written correspondence, they send us back written correspondence. Initially, we were hoping to have something back from MSBA soon.

We received a follow-up email the other day. I think it was either Friday or over the weekend. They'd like to schedule another meeting, like a follow-up, another meeting, and that is coming up in two weeks, I believe. For us right now, I don't have much that I can say MSBA said this or this is directly what's there, but what we're looking to do or what we're trying to do is take the process by which they described it would be.

I'll do my best to walk through it. The first step in this process, if the town wanted to consider pre-KK, MSVA said they need action from the town. They didn't say exactly what, but the anticipation would be a vote from school committee. School committee would take that vote saying we want to look at pre-KK as part of the MSVA program and we want to go back to module one.

That's first step. Then that would go to the MSVA. It requires a board vote of the MSVA to move us back to module one. That's the next step.

The board meets every two months. So whenever that initial vote from school committee happens, the next step would go to MSVA. Once the board of MSVA votes to move us back to module one, we now move all the way back to module one. We start module one, and they will redo our enrollment analysis.

So, and these are the off-the-record things. They already have an enrollment number for kindergarten, because our program right now includes K to five. So it's a matter of pulling that enrollment number out, and then for pre-K, they don't prescribe what the enrollment number is for that. If you recall, it was always plus pre-K.

We determine that. Once that enrollment number is done, we go through the same process where we have a meeting with MSBA. They present the enrollment. We agree to it.

It comes back formally. The select board would sign the letter. The superintendent would sign the letter saying we agree these are the options we're going to look at. After that process, it would then go to the next board meeting of MSBA.

They would vote on it. And the other kind of off-the-record comments was like, do we go back now? We have to re-procure OPM and architect like we're doing. Off the record, they were saying we might not have to, most likely.

So that's a good big step that we wouldn't have to do. And then after that, board vote we would go back to kind of where we are now ready to hit the ground in module three the feasibility study. So it's a lot of steps and We don't have, I don't want to be definitive of we're definitely doing this. Here's the defined process, which we're doing.

I'm just giving you, for all of you, a kind of download from what I see that process being. So I'm going to pause and see if anybody has comments or questions, just in regards.

Speaker 10 (34:58–35:12)

Sean, MSBA does not approve it. Can we go back to our original plan or are we signing all over no matter what? So I don't, when you say not approve it, like the pre-KK option. Yeah, if they don't approve that option, where does that leave us?

Speaker 2 (35:13–36:38)

I would assume we would go directly to the next board vote and kind of return with the options that we have. You know what I mean? Sean's not an expert. Sometimes things in the state don't make sense.

Yeah, well, part of it, so part of it is we submitted a statement of interest that they accepted us to a program based on a statement of interest. that we said we had of overcrowding at these levels. If we go back to say we want to do pre-KK and it doesn't address everything that we say to our state of interest, they may say that or they may understand like we might want to do something else that doesn't address everything. Again, mind reading here, but I don't know what's going to happen with that.

My concern is once we enter back in with MSBA, we're not in control of our path right now, whereas the path we're going along right now, we do have that opportunity. The key thing that I think keeps getting missed, I'm just going to repeat it for everybody, is if we're successful in purchasing Laboré, we are going to be looking at Laboré under our current options. We are going to look at a K-5 at Laboré. We are going to look into middle school at Laboré.

Because again, we have these enrollment options, two of them, but we can look at any sites we want. So once we own Laboré and can say we own it, then we can dive in and start looking at those sites there.

Speaker 6 (36:52–36:53)

Any questions?

Speaker 7 (36:56–37:48)

This is the first time I've heard that it's just essentially automatic to go back to module one. That makes sense to me. I don't know. I guess there was the hope you could try to save as much time as possible, but is that sort of what – so just kind of confirming that's the indication that no matter what, you're kind of stepping back.

I understand the logic of why you need to. I just – if it's so straightforward, I don't know why I haven't heard that for sure before. Yeah. So strike the last part.

I mean, I know we speculate, like, I don't know. But if it's becoming a little bit more clear, that's what you'd have to do. That's helpful to know, you know.

Speaker 2 (37:49–39:47)

Yeah. And I think that's the good thing that kind of came out of that meeting. You know, we presented with essentially four questions. And even on those fours, there might have been an A, B, and C option on each one of them during the discussion.

But I think that what we're trying to get to is looking at You know, the goal is if school committee, Nathan, Mark, and the others from school committee say, we want to look at pre K. K. what's the best way of doing that? It's honestly ripped the mandate off now, roll it into and go down that path because we're going to talk about article 7 next, which is the other way.

And. Yes, so when we do that, the MSBA process for where we got to where we are now, they do this enrollment analysis for the enrollment options that they prescribe us, the K-5 or the middle school, and they develop the number of students they're putting in each of those options. So when we go back, they're not going to redo the K-5 in the middle school, but they're going to try to fast track it. What we're requesting is they fast track it as best they can.

Whether they can or not, I don't know. But yeah, it would essentially be we're about to start module 3. If we do this, we go back to module 1, probably not on the same 270-day timeline that we're going to be doing, hopefully a much more condensed one, because they acknowledge. I think one of the things we're trying to get from them is acknowledgment that we're not trying to restart the entire duration of module 1.

We just want to go back to the small piece, jump in and jump out. But those are kind of the further discussions we're having with them. And that first meeting was good, too, because it presented a forum that we started asking all these questions, getting feedback, which then led into follow-on questions that they had there, too. But for now, for me, that's kind of what I'm seeing is the overall process.

Nathan, you had your hand up. Sorry, I didn't see it.

Speaker 11 (39:47–41:00)

No, I just put it up. This is really helpful, Sean. I'm glad you've had, you all have had all this communication with him to clarify these questions. I'm trying to get a sense, so, you know, we are aiming, this project is on a process where we're hoping to put this to a vote in November of 2028 so that we can sort of keep on time with a construction timeline that we're hoping for.

If we go back to, I think our current process has feasibility study for the next year and then schematic design for six months, which gives us a pretty minimal amount of wiggle room in our current schedule. If we were to reset to module one at some point in the near future, How far off? I know this is a hypothetical question for you, but maybe we can talk about as a group, or maybe you may have an opinion. Can we still hit that November 28 deadline?

Speaker 2 (41:01–42:51)

So, the good thing with PMA is we have some schedule nerds with them that are pretty good at this stuff. So, they were on the call with MSBA. So, what we've started doing is looking at potential board meetings that we enter, that we call it exit out back to module one and re-enter back to module three, if that makes sense, you know what I mean, from a timeline perspective. If you guys want, we can go in detail into those schedules that are there.

But I was hesitant to really dive deep into it, mainly till we get kind of clear direction from MSBA, because the next meeting may take everything that we're about to show and just throw it off. So I'm hesitant to do that. But to answer your question, Nathan, is, and Sean, correct me if I go wrong, if we were to hypothetically have those steps that I was saying, school committee vote at their next meeting to a pre-K, right? Not for Article 7, but to say, we want to roll in pre-K as part of this analysis.

Then it basically puts us on a path for, like, an upcoming MSBA board meeting. And then we would go back to Module 1. So, the MSBA board meeting, I think, is October? October 28th, yes.

October 28th. That would put us back into the module one, and the next meeting for MSVA would be January? December 9th. December 9th.

I'll let you talk about it for your schedule.

Speaker 13 (42:51–45:18)

The board meetings are October 28th, and then there's one December 9th, and the next one after that is February 24th. I'm saying is you have to it's one to get out and then enrollment study and then one to get back in. So if. If they could turn around within that month and you got back in on that December 9th date, you could make the presidential election without – you have some wiggle room, but it seems okay.

That would mean you push your board approval to August of 2028, but that should give you enough time between August MSP board approval and the presidential election as long as you have your ballots and all that lined up ahead of time. If it gets pushed to the February one, that's where it gets a little bit more difficult in that you would submit in August. The MSBA's approval would be on October 25th. So, you would have to, ahead of the MSBA process, With confidence, go into town meeting and go into the select board and put things on the presidential ballot with the assumption that the would approve it.

And when you submit it on the 24th, you're already going to know the number. You're going to know what the total cost for the project is. So all that's known. It's just you if the time sometimes until after the.

gets the approval to start doing the ballot action, sometimes actually do it before. They'll do a ballot vote before they even submit to the MSBA. And oftentimes it's around presidential elections because they know they get good turnouts. And we've been on some projects that have done that, and the MSBA is a lot of it.

If you go four meetings, then your submission to the MSBA becomes that October 25th submission, and they wouldn't approve the project until that December. That's where you get a little bit tricky. You've submitted to the MSBA, you haven't heard back from them yet. You're not even going to know the number, which you don't put that on the ballot, but you're not going to know how much you're going to spend on this project until two weeks before the election.

I don't know that that's the time would have to decide whether that's the right messaging of how they want to proceed with the project. So then beyond that, I think you've then missed, that's pretty close to missing it if it's not a miss right there. So any date beyond the April or the February date is the one you can kind of make it the April date is one where you've now pushed kind of beyond. So anything beyond April, 2027, you've missed that window in that election, which means you have to then go to like special election and you'd run it on a separate cycle.

Speaker 11 (45:19–45:40)

Sorry, Sean, do you mind if I just ask a couple of follow-up questions? Sure. First one, Sean, thank you for walking through that. I missed something you said.

You said something like the MSBA We'll accept something before it goes to a ballot or some.

Speaker 13 (45:40–47:04)

So the way the process works with the schematic design, you submit the schematic design to the and then you have a board meeting with them roughly 2 months later. So, at that board meeting is where they approve your project scope and budget. They sign off on the document that here's your budget. This is the grant that you're going to get and all that information.

So that's the point where the space now approve the project to proceed into detail design. And that's where you kind of start getting the funding. So, in the scenario where. you know, you're kind of pushing up against the election, you would submit that.

The submission deadline would be August 24th, 2028. The MSBA board meeting for that submission is October 25th, 2028. So you won't have full sign-off by the MSBA until October 25th, and then the presidential election is November 7th. So you would have to basically, you know, set your ballot, set your town meeting votes and all of that before the MSBA has signed off on the project.

You know, historically, if you're submitting to the MSBA at that point, you know, we could talk about that, but they don't often reject projects at that point. They do, you know, we've done a due diligence. We've never had a project go, we submitted on SD and then had any surprises and then push us to a front-falling board meeting. It's always gone very smoothly.

So I would anticipate that to be the same process here.

Speaker 11 (47:04–48:01)

Okay, that's helpful. And then my second question, and sorry to be hogging the mic so much. It's not really a question, maybe it's just a reaction slash question. I think to me, number one, it feels risky to make a change like this, to go to an MSBA board meeting in October or December asking for a change before we even own the property.

Like I could see a situation where we, let's say we go to the MSBA in October, we request an early childhood change. And then in December, they approve it. And then the Labor acquisition fails at the ballot box. And then I don't think we know what happens there, sort of to Glenn's question earlier, like, do we just go back?

Or are we at some sort of, are we in some sort of like dead zone?

Speaker 13 (48:02–48:26)

If from the aerospace perspective, if they allow that enrollment, and then for something happens in the library, you would be required to study that option at available sites. So you would then have to submit a pre-K early education center at Guyot Road or potentially at over at the Collier-Cunningham. It would make you go through with the study.

Speaker 11 (48:26–49:01)

And that's helpful. And then, I mean, kind of related to that, like just I'm just one school committee member, but. I think I would need to think about how I feel about deciding on an early childhood program. You know, it's driven by, you know, we wouldn't be having this conversation if not for the acquisition of labor.

Right now, we we don't own like, there's just like several, there's like a chain of hypotheticals there that I think I personally, I would just want to. you know, get comfortable with. I'm just processing this kind of live for the first time.

Speaker 2 (49:03–49:40)

Yes. Sorry, Nathan. So yeah, I know it's a lot that we're doing here. And, you know, I think our overall goal is, you know, as you said, it was, you know, the presidential election.

So the first option that you talked about, John, that you said it wouldn't be like, actually, don't take a further step back. From your guys' experience, has any other town done this? Gone from module three, about to start, back to module one, back to module three, and if so, what was the time duration for it? Not that I know of.

So we're in the middle of it.

Speaker 13 (49:40–49:54)

We've had projects where much later on, they've asked to see if they could pull a grade out, and that's when they said, well, then you have to start all over again, and then we're talking years delay. Where the conversation with the MSA was slightly,

Speaker 2 (49:54–50:25)

different slightly more promising than other districts because you're not you're not that far down the road yet yeah yeah okay okay and then so the the the original question i was going to ask too is so for that you know everything lined up we made the december meeting i think was the one you were saying the first one for like to to come out of back to module one or what was the first schedule one that you said it would like?

Speaker 13 (50:25–50:55)

Yeah, one meeting shift, it would be two meetings would be the coming out on the October 28th meeting and back in on the December 9th meeting, you could pretty easily keep with your schedule because you do have you had about 120 days after the SD approval to the presidential election. So you would just kind of shrink that time up a little bit. When you shift another meeting to the February one, that's where you run into some issues and you have to decide if the town will be comfortable putting it on a ballot while awaiting MSBA board approval.

Speaker 7 (50:59–51:41)

Just processing that. Could you just say – I know we're in like the three tiers down of speculation but could you say a couple more lines on being in the situation where – that Nathan feared or not putting words in your mouth Nathan but like where MSBA approves that going back to module one, the town doesn't approve the acquisition, but you said you're still bound to kind of continue to study pre-KK options at other locations.

Speaker 13 (51:42–51:50)

Yes. If they add that enrollment option as a viable enrollment option, you will be required to study that at any available sites.

Speaker 7 (51:52–51:52)

Right.

Speaker 5 (51:53–51:53)

Yes.

Speaker 7 (51:53–52:04)

I'm just trying to picture what that would look like. That would just be kind of going back over that option at each of our existing locations, basically.

Speaker 13 (52:04–52:17)

Yeah, you would look at a – it's probably a 500-student pre-K, early education center at Guile and then potentially as an addition to the Cunningham – because those are your two sites that you have filed right now, right?

Speaker 2 (52:17–52:27)

Yeah, but I mean for – just to simplify it. Colley Cut Cunningham is only the ad reno. So they're not talking about adding a new school there. Right.

So it would be on Guile Road then. It would only be on Guile.

Speaker 7 (52:28–52:38)

Yeah. Could anyone just explain what that This was good discussion, but what does that mean?

Speaker 13 (52:40–53:19)

They would develop a full educational program to support a pre-K and K school at Guyle Road. They would also develop an educational program to support a 7th and 8th grade school and develop all the classroom sizes and do layouts and all that. All the things they did for the middle school, they do that for a middle school and they also do that for a pre-K, K option at Guyle Road. And then the committee would then decide which options they want to bring into the next phase, which is PSR and further study.

And then out of those further study options, you would decide on your preferred option to continue into SD.

Speaker 2 (53:21–53:34)

Thanks. So just kind of reiterate, all of that process that I was talking about there has to start with the school committee vote. So, you know, MSBA could say tomorrow, do this as an advocate.

Speaker 10 (53:34–54:19)

Yes, sir. Is there any advantage to just keeping these as separate projects, whether it's MSBA supported or not? Where I'm going with this, we're so far along, right, with the middle school project. We're going in the right direction.

If there's a need for the pre-K, historically, correct me if I'm wrong, that's an easier sell to a town typically because it's usually such a need for it and there's such a demand for it that You know, I think, I don't know, I'm just putting it out there. Is there some advantage to staying on track with the middle school and keeping the other project as a separate entity, whether it's part of the middle school or separate, that's where it gets a little confusing, right? It's because we don't even know where this thing's going to be located.

Speaker 2 (54:19–55:04)

So just in regards to the options that we have right now, just for everybody that's listening too, right? The middle school also has preschool as part of it, right? The K-5 also has preschool as part of it, right? So the preschool thing that you're talking about, we're going to have that regardless.

Correct. And those two options, grade 7 and 8 with preschool or grade K-5 with preschool, we're going to look at Guile. And then if we're successful in Labor-A, we're going to look at Labor-A, both under the kind of process that we're doing. The difference is the programming now of a preschool K only, what would that look like and everything there?

Speaker 10 (55:05–55:46)

And that alternate path or that parallel path that you're talking about is essentially… But the LaBarre site is very different design-wise and cost-wise than doing it all on one site. Correct? Say that again.

If we're doing everything right on Guile Road, that's very different than doing Guile Road and… So you're talking split the projects? I don't know. That's what I thought you just said.

No, that's not what I said. Sorry. No. So like those…

Explain how LaBarre, I think I know, but explain just so we're all clear, how LaBarre ties in with our current project. Let's go to the next agenda item, which covers it. No, it's a good point.

Speaker 13 (55:46–55:48)

I think it's, is it too simple to say either or?

Speaker 7 (55:49–55:52)

Does that answer your question?

Speaker 13 (55:52–56:49)

With the MSBA process, they make you study enrollments on basically available sites. And if the town is going to bilaborate and they're going to indicate that that is an available site for construction of the school, the MSBA is going to want you to program a building on that site because you've You know, it is a viable, even though we logistically know it's really not a viable option for a middle school, but that's what the study is supposed to prove, right? Like this, that you have to go through the study because, you know, it, but we've got an indicator that based on the acreage and topography of the site that it's not right. So, what normally happens, it's a, it's a light study and the PDP process and that's what gets submitted on that.

It would be a. you know a seven-story building on a site that can't support it and it just doesn't work and then that will be ruled out but they make you go through the process because they want you to study it and they want you to prove to yourself and then to the msba that it just it just doesn't work so on that same note we have to study an addition and a renovation to collicott cunningham which right which we all know we're not going to put 1400 kids at collicott cunningham

Speaker 2 (56:49–57:51)

I mean, it's just – but it's a required kind of check that we have to do with MSBA to say, this is the school we submitted on. We have to look at some type of ad reno as part of this program. We're going to look at it, but we all know, we don't think that's going to be one of our preferred options. So, we're going to check and say that's where we're going.

To Sean's point is if Labra is successful, we can add it now to our portfolio list of land that we want to look at the options that we have. Again, we have two options. The talk, this whole agenda item we're talking about is layering a third option in there. Now we would have three options at two sites, so six designs plus, call it Guy Cunningham, so we'd have seven options instead of five.

The question I have, too, is at what point is it too many options? That's the other one that we're not talking about is summer liquid 19. Yes. Okay.

Speaker 13 (57:51–58:13)

We're not doing 19, but well, but it'll be iterations. You know, you'll have, you might have a couple of different options. You might have with a pre-K without a pre-K, you might have a pre-K as a freestanding building. So those all count as options, but your base building and the base square footage is the same.

And then you're adding, you know, little bits onto it. So as part of the study, and those will, because they're different square footages and different Estimated values the log attract is a separate option.

Speaker 2 (58:14–58:40)

It's like, you know for a for B for C at different sites So just Glenn to your point of like, you know looking at lab array pre KK is like a separate Lane or something like that. That's essentially What article 7 was having us to which is the funding article? So if everyone's okay with the MSBA pre KK, let's kind of move on to that Yeah

Speaker 10 (58:40–58:44)

I think I was confusing the pre-K with the pre-KK, to be honest.

Speaker 2 (58:44–59:35)

No problem. This is a lot. And I appreciate everybody trying to keep up because it does get cumbersome kind of running through everything. So, for item 4C, which is discussion, approval, fall town meeting, article 7, SBC funding.

So, you know, I put approval on there too, because at some point, you know, we may have to take a position on this. And I think this is our first time really tonight taking a deep dive on this. So I'd be very comfortable not taking a vote on this and ideally scheduling our next meeting sometime before town meeting to, you know, dive a little bit deeper into this to take a position on it. So let me just share my screen and I'll kind of do my best to walk.

Speaker 6 (59:39–59:46)

Yep, so. All right.

Speaker 2 (59:48–01:00:00)

So I'm not sure, have you guys shared the overall schedule for you guys? Have you guys seen the overall schedule that PMA put together? I think it might've came in our last packet or something like that.

Speaker 12 (01:00:00–01:00:07)

It was in the designer RFS as well as the pet. So it was sent out in one of the early things, which is maybe the last page.

Speaker 2 (01:00:08–01:07:31)

So with this schedule here, I'll highlight the purple or pink line that's on the left is kind of where we're at today. The yellow highlighting on the right is that presidential election. So what we're looking to do is these first two bars that are here, is our feasibility study. You know, look at this bottom line here.

What I've tried to do is take kind of the highlight of this overall pretty complex schedule and simplify it a little bit just so we can look at it, you know, in the near term of what we're doing. I'm going to do my best to kind of focus in on this. So, under what I call lane one, MSBA process, which is the process we're doing right now, We're about to onboard an architect to join our OPM, and we go into what's called the PDP, and again, acronyms help. Preferred Preliminary Design Program.

Okay. So as part of that first program, we're going to look at these four options plus the ad reno. But for new construction, at Guile Road, a K-5 plus preschool. At Guile Road, a 7-8 plus preschool.

if we're successful with LabArray, and I'm just using that we are right now, a K-5 plus preschool or a 7-8 plus preschool. And as Sean was saying, as we go through this process, we'll filter down, go into the preferred schematic report, and then by the end of that report, this time next year, we're going to have a kind of selected program that we're doing. I just use the next year as like a timeline. I'm trying not to go further than that, but just for focus.

Part of what we're looking at, too, that we just talked about, and I don't have timelines associated with this because, as you just heard, we're still waiting for kind of concrete stuff back from SVA. And then when we have this, we should lay it out. But essentially, that process that we're talking here is taking this MSBA first lane and then layering in the preschool, the pre-K and kindergarten, the Early Childhood Education Center at both Guile and LaBarre. So as we get that stuff, we'll do it.

The one other that we have is essentially Article 7, and I'll pull that up to the middle. Article 7 right now, so just to give everybody an understanding of the origin of Article 7. Article 7 was developed that if this point in time we're successful on Labor-A, and the school committee and the select board wanted us to run with Labor-A as a non-MSBA project, we needed funding to run that path. Everybody understand that?

So, there would be like a declaration that we want to do leverage, you know, that decision was already made. And we're not there yet, which is fine. But what it does is complicate it a little bit, because essentially that decision to leave or not leave has to come later. So, for this Article 7, when we're looking at it, This is the parallel path that everyone's talking about.

So under this parallel path, in November, assuming Article 7 is passed as a town meeting and we're allocated $1.2 million, we would onboard a new OPM and architect, potentially PMA, potentially somebody else, potentially the same architect we were just talking about, one of the four, or potentially somebody else. So I know the town administrator at a select board meeting mentioned like three to four months on board. I carried four months only because we're spanning across the holidays and I don't anticipate much going on during that time. That would lead us with an architectural team starting in March.

and then giving them four to six months. I'm showing six months here and these are all hypothetical durations and I'm not trying to drive this for schedule or stuff like that. But essentially what happens is at the end of this process, we come to a decision point, and that decision point has three kind of ways we can go. At one, we return to the MSBA program.

We don't want to do a pre-KK at Lab Array for whatever reason it is, and we run back to our parallel path, and we jump back in with the MSBA process that we're doing there. That's decision one. Decision two is, you know what? we think it would be faster and less expensive to do it on our own.

So we leave the MSVA program, we run with Lab Array as a pre-KK, and we go on our own path, and we leave MSVA and kind of go on our own path to go faster. And at the end of the day, by the time we do this analysis, I assume that decision would also require us to save money, so we wouldn't do that and lose money. But the third option, is if they decide that a pre-KK at Laborere is the way to go, and they want to go back to MSBA as part of this, so this middle lane doesn't exist. At this point, if the elected boards of the town, school committee and select boards say, all right, here we are, we finished this program, this parallel path, and at this decision point, we would like to go back to MSBA at this point.

that's where it becomes troublesome because now the discussion we were just having and going back to module one, we are now going all the way back to module one after we probably finished a majority of the schematic design. So that is kind of something that I don't think everybody was anticipating with article seven. Like I said, article seven originally was we were just going down this path and we were leaving MSBA. So again, for that, if we were to do this and go back to MSBA, it's that process I talked about.

School committee vote, MSBA board vote, we go back to module one, we redo an enrollment analysis, we come back, and then we go back to module three, and then redo it again for all these elements, similar to what we were doing up here. So this, purple or bluish line that you see down here has a much longer duration or delay. I bring this up for people because Article 7, again, the origin of it or the thought behind it was we would have direction on a specific path. Where we're at right now, we don't have that specific direction, so this introduces a decision point call it months down the line, six to eight months or a year, whatever it may be.

And then at the decision point, there are very difficult decisions that need to be made. So I'm just going to pause there and let you guys take a lot of that in because Article 7 is a little more complicated than I think originally when it was being discussed.

Speaker 10 (01:07:32–01:08:07)

I think visually this is very helpful, the diagram. And if I'm missing something, please chime in, because this is, you know, when this is… Covering it well, it's just like, okay, if we do this, I see this advantage and this a disadvantage. We do this, it's, there's a little…

Yeah, so… I think we've got a real challenge to figure out what's really the way to go here, right?

Speaker 2 (01:08:07–01:08:12)

I agree. And just to be clear, we don't decide. No, but… Yeah, yeah.

Speaker 10 (01:08:12–01:08:16)

I think as a town, it's… We're gonna try to lead.

Speaker 2 (01:08:18–01:09:59)

The biggest thing we need to do, and I've heard this from multiple people and I fully agree with it, is we need to ensure, and I've said this with every alternative parallel path, this is like the eighth time we've done a parallel path on this project, right? And I say that mainly because when this goes to a vote at the very end of this for whatever project it may be, we'll get crucified if we say, you know, they push back and say, you didn't look at this, you didn't look at this. So part of me, and again, what I was talking at the beginning of, With our current MSBA process, we are looking at Labor-A. So I just, again, I'm gonna repeat it for everybody.

As part of our current progress, if we are successful at Labor-A, we will be looking at it as a K-5 plus preschool or a 7-8 plus preschool. So the only thing it doesn't have is that pre-K. And when I talk through or think through this decision point, if the decision point for Article 7 is going to be, you know, and I push this out graphically mainly for select board and school committees so people can kind of see what the process is. You know, this all hinges on do we want pre-K, K, early childhood education center as part of this overall project.

So, again, I'll pause and just see if anybody has comments or questions.

Speaker 6 (01:10:01–01:10:02)

Oh, Nathan, thanks.

Speaker 11 (01:10:04–01:12:25)

Yeah, thanks, Sean. This calendar is very helpful. You should think about becoming an engineer. It seems like one of the questions we collectively as a town need to ask ourselves is, or like, there's like a vector we could look at here, which is do we value What do we value more, timely completion of the project or cost savings?

That's one sort of – those are two variables to look at. There's multiple other ways you could look at this. If we value timely completion of the project, like let's say having a vote in November of 2028, then we should assume that if the Article 7 study leads us to believe that early childhood at LaBarre is a better choice, haven't studied it under MSBA, we should assume that we will not re-enter MSBA. If we think that cost savings is more important, then under the scenario I just described, we should assume that we will re-enter the MSBA project or attempt to, And, and I'm not sure that that's a guarantee.

And then the project will stretch out, you know, another couple of years, probably. I think, you know, and there's reasonable people who might believe on either one of those, I know which one I think is more important. But I think that's like, that's, that's something that like, we or town meeting or whoever needs to ask themselves in order to decide whether Article 7 is a useful path to explore. Because if you don't have a prior on that and you vote for Article 7, then you're leaving open one of the biggest questions until the completion of the Article 7 work, which is, do we want to have this complete by a certain date or not?

Does that make sense?

Speaker 2 (01:12:25–01:13:43)

It does. Again, for me, I'm taking in all the feedback just essentially for some of this decision point. Because for me, and again, I keep repeating the origin of stuff like this, because I think some people might… I think Article 7, as it's been discussed at previous meetings, was a little more, call it generic, as people's understandings to it of like, hey, we're just going to study Laboret, pre-KK.

And honestly, for lack of a better word, it sounded innocent. But I look at that article that it's going to force the town to a much more bigger decision after that initial study is done, like that decision point that goes in three directions. And it kind of is kind of the premise to where we're thinking or trying to work with the MSVA now for the previous agenda item that we discussed in regards to trying to layer pre-KK into MSVA right now and, you know, what are our delays associated with that. So, yeah.

Speaker 7 (01:13:52–01:13:57)

Any other questions? I'm going to have to look at that timeline a few more times.

Speaker 9 (01:13:57–01:14:01)

Yeah, it's a lot. It's a lot. Where is that? Can we access that?

Speaker 2 (01:14:01–01:16:04)

I'll forward it to everybody so they have it. I wanted to describe it first. And that's the other reason, too. I think it's important for everybody to go through and digest.

But the hardest thing with this is, To Nathan's point, I should be an engineer, but it's just like when we're juggling. multiple, call it design options or requests that we're looking there, and they go down these kind of separate paths. They're all intertwined somehow at a certain point, or one's going to rely on the other to feed into it. And for me, you know, the way my mind works is like, as I'm hearing discussions and all this and putting stuff in groups and trying to associate times and durations for all that stuff, That essentially was the output of where we're at.

What those durations are, it isn't something to show that we're going longer, but the reality is the Article 7 path, if we went down there and got to that point and said we want to go back to MSV at that point, my guess is definitely a year, probably a two-year delay to go all the way back. The other component that comes in there too, so this is the great thing about having an OPM on this project. We're going to pay as part of that parallels path under the MSBA progress we're working under. We're going to pay $1.5 million that we have allocated right now for that study.

Then we get to the end, and in that parallel path, and we want to add pre-K in, we're going to have to go back and redo that. We're going to spend another $1.5 million, because we already did it. Last one, before anybody jumps in. that other article seven funding was 1.2 million.

So now the millions start adding up on just studying where we're getting to.

Speaker 9 (01:16:04–01:16:44)

So the millions and the years, I think it might be important for us to start framing this when we're talking about it, not as a one to two year ad, but as a comparison between horizon of four years and instead we may have a completion horizon of six years. Like I would say that our current completion horizon is already somewhat unacceptable in terms of like solving the problem that we were assigned to solve. So I think maybe we should start talking about this rather than one to two more years. That doesn't really give the right context.

Speaker 2 (01:16:46–01:17:53)

Yeah, and part of that, you know, the town administrator, we've been working with him to understand for these different options, durations of kind of where these things are for the landing point of, you know, where we'll end up, you know, for that completion point. Because as I noted is, If we went down the Article 7 path and got out of MSVA, the point might be closer. We might have a shorter completion because we're not in the MSVA program right now. That might be something that some people might say, listen, I'm fine not getting the reimbursement for MSVA.

We're going to build this building. We're just going to go down that path and have it done sooner. That's essentially what I'm trying to do with that. them to everybody.

Just as we're having these discussions, having a visual as you're having those discussions I think are helpful because what I've found is a lot of people have a theoretical vision in their head of how all this stuff's going together and everybody's is a little bit different.

Speaker 5 (01:17:58–01:18:20)

I do like that you have a decision point in there and If questions are answered, we could finally get to a point. There's a lot of balls in the air. And the way you laid it out was really good. But it'd be nice, like you said, it's going to be two months or it's going to be four months before we get answers to the meetings.

But having that point of decision to get there, you've got to get there.

Speaker 2 (01:18:21–01:19:58)

Yeah. So I don't tap into my 9 to 5 that often for stuff we're doing. For me, on a daily basis, we deal with very large-scale, complex projects, like the dwarf, this one. Even in the planning phases, as we're coming up to a point where we hit a point and we go, once you hit that point, the what-ifs or the alternates or stuff like that, you've got to follow essentially the path that you're on.

The reason you do that is, we get to a point of analysis paralysis, or we try to look at this, or what about this, and you never make, your progress to complete extremely slows down. So, you know, for me, This isn't new for an option or something that pops up. But my take is typically, you want to digest that option as efficiently as possible, figure out the best path forward for that, and then just keep moving forward in whatever path that may be. But for us right now, it's not us that gets to decide on that.

What we're trying to do here, is digested come up with our advice or feedback to select board or school committee and provide them you know here is you know what we're seeing for these options that are here and you know scheduling implications that we're doing.

Speaker 7 (01:20:01–01:20:12)

Why is the set the delay an option to like kind of shorter than lane three?

Speaker 2 (01:20:14–01:22:03)

I'll show you. I think I know, but I would like to make sure. So essentially, and I'm using these as like theoretical timelines, right? So what you're saying is, if right now we're at this point, and we say we want to include the early childhood education center into this MSBA process, we're making that decision to revert at this point here before we start any of this work.

So, yep, I see. Yep, no, I'm going to keep going. So for that, this is where this process of school committee vote, MSBA board vote, that whole thing going back and forth, we would jump down into this. And once we get those decisions on that and we have those solidified or better ideas for them, our schedule nerds, as I referred to them, will develop nice schedules and we'll look at that a little bit more.

But The reason it's such a longer delay, just to Pete's point, I know you got it already now, but we're going to, under this parallel path, while we're progressing the work here in orange, we're also progressing the work up here in green. And when we get to this theoretical decision point, if we want to go back to MSVA, back to module one, all this work that we paid for here essentially gets scrapped. we go back to module one, we do hopefully the quick couple month delay that we were talking about, then we get back in this process, and then we do another year of the same green path, just now with pre-K rolled into it, or with the early childhood education center enrollment option layered into it. So that's why the delay becomes so much longer.

Speaker 9 (01:22:03–01:22:08)

Yeah, because the current one does contemplate a pre-K portion.

Speaker 2 (01:22:08–01:22:33)

Correct. Yeah, it's just not the pre-K individual school construction that's part of it. Did that answer it? Yeah.

If you have more, keep going because at some point, you may have to describe this and select words. I want to make sure. It's a lot to take in right now. We can ask questions.

Speaker 7 (01:22:33–01:24:25)

I think it's more of a side comment, but I think Like, we need to get everybody up to an adequate, like, informational level. Correct. Which is hard with all the moving variables. That's not, like, a comment to, this is complicated, you know?

But one question I'm going to spin to, back to. I'm just trying to think about any downsides to lane one. Could the, if let's say the MSBA, when we request to go back to module one, is there any sort of path where like, you know, we get a rejection, I guess you could say from the MSBA that, you know, you can't sort of reopen to add this pre-K option such that we would want that. allocated money just in case.

Because I think some of the genesis for wanting that study money was just the level of uncertainty with interaction with how it would go with the MSBA coupled with an appetite to further understand the ultimate comparison before decisions are made that you can't go back from. So in that way, you could see how it could make sense to have available money. Is there a scenario where you want to have that available just in case even if you're someone who likes trying lane one?

Speaker 2 (01:24:25–01:25:52)

Yeah, and just to be clear, green is Lane 1, blue is Lane 2, and then orange is Lane 3. So to that point, what I would say is the funding article that we have for Article 7 Could be brought at any future town meetings and I mean, you know, probably leading up to this town meeting, we wouldn't have kind of direction of whether we would get kicked out or what this looks like here. And then if we needed that to start that separate 1. I'm just asking out loud, is the next tell me the schedule of like February or something like that?

I don't know if it's locked in, but probably. Yeah, yeah. Sorry, I'm not trying to – I'm just trying to think hypothetically of like when will be the potential next time that we'd be able to do it and how that would play in. But no, that's actually a good point too.

So if for some reason, We were here, we asked MSVA, go to module, go to lane two, but they wouldn't allow it, meaning they don't let us study the pre-KK and pushes us back to our current timeline, what we're looking at with some short delay. And we still want to study a pre-KK at Lab Array. It would be good to have the funding down here to start that analysis.

Speaker 7 (01:25:53–01:25:59)

Yeah, no, I'm just trying to kind of look at the pros and cons of each.

Speaker 2 (01:26:00–01:27:03)

Yeah, and the other word, I mean, your point probably didn't enunciate that either is the origin of that Article 7 was to have funding to bring that initials to three-week study that we did up to a certain level to allow school committee to make a decision on where they want to go. And that's essentially what this decision point gets here is like, We, you know, potentially look at the pre-KK, the option, I'm just going theoretical now of, it went from 85 billion to, you know, again, because I'm theoretical, 180 million. And it's like, well, no, it's not worth it. And we want to go back to what we're doing, you know, on this process.

That's a very, exaggerated analysis, but that's essentially where you would follow that path. Or do they want to go down this road because it's at the same price tag and they're comfortable not pursuing MSBA reimbursement? Or at that one, they go here. I don't know.

Speaker 7 (01:27:14–01:29:38)

So I think another thing that would be helpful to hear from this group on is sort of, you know, what's, is it realistic to get to a decision point or to have information that might help a decision point in that lane three time period that's potentially allocated? My understanding is that potential – that sort of time estimate I think originates out of a group that's working on considering what that further study up would look like that I believe Nathan and Mark and Sean are part of and select board representatives are part of or not. sort of almost a work plan arising out of that a little bit that I think Nick Milano pulled up at the last select board meeting. But, you know, anything that can kind of be surfaced for input in terms of having kind of from these very experienced boards on, you know, pros, cons, concerns, not only of some of these underlying strategic questions, but pressure testing the process.

Does that look like a good plan? Is it doable? I think that would be helpful feedback to have from groups. Is that a fair ask, like maybe might help if next meeting, you know, we pulled up that Excel and just had the group kind of comment on, you know, what's being asked of them for this.

Yeah, definitely. Or maybe that's just what that work group is for and it's duplicative to talk about in this group. I'm not sure. But, you know, I just am of the view that, you know, these are complicated, very important decisions.

So the more, you know, I know it's all kind of intertwined with the political, but like it would just help to just kind of have everyone sort of surface their thoughts on it.

Speaker 2 (01:29:39–01:32:09)

Yeah. And part of that, so what Pete's referencing is essentially, to kind of review and discuss how we integrate all this stuff for different things there. And it had essentially action items or deliverables by each group. And I forget exactly what school building committees ones were, but it wasn't anything that I wasn't anticipating.

So I wasn't really stressing about it and stuff like that. But I'll put that together. I'll share it. So you can actually see kind of what that was.

But essentially what it does is, you know, it's in general asking us to take that previous study that was done and build it up even further. You know, refine the cost, refine the program. We keep talking that we built Galbraith, we spent $450,000 on that initial concept design, and we spent $30,000 at Labyrinth. They wanted to get them at the kind of same balance point there.

And I'm fine doing it. It doesn't bother me. But again, it's the getting direction on that, you know, from school committee and then having everybody understand that if we go down this path with Article 7, at the end of Article 7 or the work associated with Article 7, there's a decision point there that some people might not be anticipating that's there. They might just think, oh yeah, we're just going to roll it into MSVA at that point and it's not as simple as I think some people may have considered originally.

So that's my long-winded way of saying more to come on Article 7 too. Any other questions or comments? Also checking online, make sure I'm not missing anybody. All right, seeing none, we will move over to item five, new business.

None. So we're good with that. Item six, future meeting dates. So I think it would be important to probably hold our next meeting about two weeks out And I say that mainly because we have town meeting in three weeks.

So having, I think, a meeting the week before town meeting.

Speaker 9 (01:32:11–01:32:12)

That 12th is a holiday.

Speaker 2 (01:32:12–01:32:27)

Is it a holiday? Sorry. At Columbus Day. Oh, is that Columbus Day?

Mm-hm. OK. Well, let's aim for, I'll try to coordinate it with everybody, but at some point that week. See, there's a- Mm-hm.

Speaker 7 (01:32:29–01:33:02)

I don't know if it's tentative or locked in, but I believe there's a select board meeting on that Tuesday the 13th. And it could be advantageous to have school building committee and school committee discuss what they can on these things prior to that. You know, I'm not sure what's doable.

Speaker 2 (01:33:04–01:33:26)

Yeah, so I can make myself available. So I'm looking at the schedule next meeting with MSVA, or at least the proposed days and times that they had. So the 13th was the earliest date they had. So it might be good for school committee and school building committee to be in attendance.

So happy to do it if you guys need me to. Wait, sorry, can you say that again?

Speaker 5 (01:33:26–01:33:26)

Yep.

Speaker 2 (01:33:27–01:34:10)

So our next meeting with MSBA, not School Building Committee, right? The follow-on meeting with MSBA is actually, I'm looking it up now, is they gave us three options. Tuesday, October 13th is the earliest one that they have. Okay.

So that's more important to sort of not get ahead of that. Yeah. So I think what might be good is, so for us, would Wednesday or Thursday of that week work for everybody? I'm not trying to schedule back-to-back nights, stupid, sorry.

It'll either be the 14th or the 15th.

Speaker 14 (01:34:15–01:34:24)

Gentlemen? I can probably not meet in person those days, but I can likely call in those days.

Speaker 10 (01:34:24–01:34:39)

Remote is totally fine. Well, it's gotta be out by 8 on Wednesday, but… We'll do our best. Usually we're done by then anyway, so it shouldn't be an issue.

OK. Greg? This one was a little longer, I think, because we've been going over proposals.

Speaker 2 (01:34:39–01:34:48)

Yeah, the design of proposals. Carrie, Nathan, Mark, any problem with the 14th or 15th? Any preference?

Speaker 4 (01:34:52–01:34:54)

Right now, they're open for me.

Speaker 6 (01:34:56–01:34:58)

Thanks. Nathan?

Speaker 11 (01:34:59–01:35:02)

I would have a preference for the 14th.

Speaker 2 (01:35:02–01:35:12)

I can check with Mark after.

Speaker 8 (01:35:13–01:35:20)

Yeah, it's 14th would be preferable, but I could make the difference with Mark.

Speaker 14 (01:35:33–01:35:35)

All right. Either of those is good for me.

Speaker 2 (01:35:35–01:36:13)

All right, thank you. All right, let's aim for the 14th then for now, that Wednesday and we'll be good. So last agenda item, item seven is adjournment. So entertain any motion to adjourn.

That's all I know at once. All right, made by Pete. I'll second it. Seconded by Tim.

No discussion. Roll call vote. Pete Obersheimer. I'll put it on install.

Glenn Hoffman. Yes. Tim Lombard. Yes.

Kerry Hurley.

Speaker 4 (01:36:14–01:36:14)

Yes.

Speaker 2 (01:36:15–01:36:23)

Nathan Hutto. Yes. Mark Loring. Yes.

And myself, yes. Thank you very much. See you in two weeks.

Speaker 1 (01:36:23–01:36:24)