Board: School Building Committee

Date: 2026-06-08


Transcript

Auto-generated; may contain errors.

Speaker 1 (00:18–00:23)

So, it is now 6.10 p.m. on June 8th.

Speaker 2 (00:23–03:29)

I'll call the meeting of the Milton School Building Committee in order. As we typically do, we just do a roll call vote to see who's here. I can see that everybody's in the room, if there's a vote. So, easy votes.

Senator Napolitano? Yep, present. Mark Lorin? Present.

Peter Robesheimer? Van Hoffman. Present. Scott Tereshak.

Present. Bob Nagan. Present. And Shada Ward.

Present. All right. We reserve the first 15 minutes of the meeting for citizen speak. If there's any citizen that wants to speak, we ask that you limit your comments to three minutes, and please state your name and address.

Seeing there's nobody in the room and nobody online, I'm going to move on. The agenda item number three, which is our OPM interview procedure. So, I appreciate everybody being in person, because I think it makes the presentation a lot better, a little more intimate. Hey, Tim.

So, for the OPM interview tonight, we've gone through I've gone through the 11 submittals that are there. We've shortened it down to a list of three. So we're gonna get all three of them in tonight. The format by which they're gonna do is about 45 minute presentation and Q&A.

So the first 15 minutes is their presentation. The next 30 minutes is Q&A. So as everybody knows, we have five standard questions, as I put it, for the The last part of this is, I know I talked about the rankings, we're actually going to be scoring. So you're going to be going through the evaluation criteria, the same ones that the BOPM subcommittee did, and scoring each one of these based on those scoring criteria that are going to be there as they're presented, as we have reviewed their submittals.

At the end, we'll accumulate all of them, and there's eight of us here right now that are voting members, five of us chosen to be denied, Total up everything, divide by nine, and then they'll rank where we count the ones. Any questions? Are you going to do it? Is it the same information?

Yeah, so Nick's going over now the printed scoring sheet. I have one printed now, if you want to add it on my computer, too. Oh, no, it's the scoring sheet. It's not the questions.

It's the questions. Yeah, yeah.

Speaker 3 (03:39–03:44)

So with no questions, we've got one minute before we bring them in.

Speaker 2 (03:44–03:54)

So PMA is going to be our first, so PMA is coming in. We'll bring them in and let them get started. Sound good?

Speaker 4 (03:54–04:01)

Yeah. And are you kind of running the time or watching the time and all that? Yeah, if somebody wants to volunteer. Yeah, absolutely.

Speaker 3 (04:02–04:28)

I can volunteer. How was graduation for you? It was great.

Speaker 5 (05:10–05:11)

Can you print them out?

Speaker 6 (05:12–05:15)

I can't, I'm out.

Speaker 7 (05:15–05:15)

Sheldon.

Speaker 3 (05:15–05:20)

Thank you. Never mind. Thank you very much.

Speaker 2 (05:21–05:23)

Appreciate it.

Speaker 7 (05:25–05:25)

Thanks.

Speaker 3 (05:25–05:44)

Thank you. Is this on this side? Thank you. Sharing is not turned off.

Yeah.

Speaker 2 (06:52–07:03)

Sure, I'm Nathan Hutto, I'm a member of the school committee. Mark Thorey, I'm a member of the school committee. I'm the vice chair. Pete Oversham, I'm a member of the select board.

Speaker 8 (07:05–07:07)

Carrie Early, I'm a member of the school building committee.

Speaker 2 (07:08–07:11)

Tim Lombard, I'm a member of the school building committee. Sean Wirtz, I'm a member of the school building committee.

Speaker 5 (07:28–13:05)

First, thank you for having us. I know that our presentation does sit in Milton Cunningham Elementary School. We do realize that this project is not just for Cunningham. It's to alleviate overcrowding in the elementary and middle school across the board.

It's just kind of the nuance of the MSBA. Once they call it something, you're stuck with that to the end. So we'll go through some introductions of our team here. I'm Sean Burke.

I've been with PMA for 21 years, doing mostly OPM work and schoolwork. I'm going to do introductions because we kind of have a short time. We have Seamus O'Connor here, project manager with PMA, been with us for seven years. Both of us are Milton residents.

He grew up here. I've lived here now almost 14 years. Mitch Miller is with PMA for six years, comes from the construction management world. He lives down in Kingston.

And Matt Muto, he's been with us for two years, comes from a geo-environmental background, and he's down in Rockland. Now with us today is Kevin Nigro. We'll be pulling him in to help with if we have any permitting issues. They had a massive project up in Northeast Metro Tech that had to go through some MEPA challenges and things like that.

So there's a lot of lessons learned. So in case, understanding that the project has some wetlands and things like that, if the location by the high school was the location that's chosen, we'll have some lessons learned and some people from that crew to help us out as we go with the rest of our office. Beyond that, we have a site rep, Ronnie Casciano. He's been with us seven years, spent up to 33 years as a union carpenter.

Now he's what we call a clerk of the works, boots on the ground, kind of making, doing the labor counts and daily reports. We have Julia Roverno. She's with our marketing team. She'd be assigned to us to help with outreach, making graphics for presentations, helping with webpages and things like that.

Peter Bradley from PM and see a cost estimator. The architects will likely choose them as well. So, we'll have as a backup to them on site. A queue is our intelligence construction intelligence platform.

We partner with them on most of our projects. They do during construction walkthroughs is basically Google Street view of your construction project. So, anyone who can't be on site. can go and see what's happening and keep up to date.

And we also partner with BDA typically to do third party reviews of envelope, you know, with the energy codes being what they are and stretch energy and beyond. Sometimes we need to have a third party building enclosure consultant to help out with some of those. So it's just another tool in our toolbox that we can use to help out. We'll also have a scheduler assigned to us.

We have a large scheduling division within our brain tree office and we'll have them help us out during the preliminary, but then also mostly during construction to do monthly contractor construction schedule reviews. All right, we are fairly familiar with your preferred project site as we did help out during the earlier feasibility project site. You have control of the site through that land swap, which needs to build on in order to maintain that control. We do know we have an active school around it.

You have a buttress. to the south and on Blue Hill Parkway to the west, and also there's wetlands all around. We have gone through the woods, we've marked out, we've done a lot of research on this and we think it's a great site. At seven acres, it is going to get tight very quickly, so there is going to be some logistical challenges.

I know it seems like a big site, but once you start cutting down trees and putting people in there, it's going to get tight quick. There are some challenges, but we think it's certainly a doable project and it's a wonderful site. We also understand that the MSBA is looking at a couple of different enrollment options here. One is to bring Collicott-Cunningham up to 1,400.

That would be an addition of 400 seats. I know you're at 1,250 now, but it's not built for that. It's really built for 1,000. There would be a significant addition if you could do one there.

While we looked at the mass mapper, it doesn't appear that there's wetlands behind there, but there is an NOI filed. I suspect that there is some wetlands in that wooded area behind there. So if that is not available for construction, it's going to be a very tough site to try to put an extra addition on and parking and all the other things, playgrounds that you're going to need to support those extra students. Also heard that the La Brea College is for sale.

I think the town is potentially considering purchasing that. It's a smaller site, it's just under five acres. It's got some great issues there, but it's certainly something that should be considered as part of this feasibility study. We shouldn't really leave any stone unturned.

We should go down every path for nothing else to show to the public that we've done our due diligence and we've really gone through a full vetting of every option. What we also look at early on and throughout the process is hypothetical tax impacts that these costs are not going to be with this building costs. However, we looked at MSBA data for the different enrollment options you have, what potential size that building might be, what that cost might be by the time you build it, and the potential grant for the MSBA, as well as what the district share would be. While there are some additional funding sources in the town, this would just be a straight borrowing when you would need to level debt borrow 30 years at 4% per year and what that impact would be on each household.

And we do this early just to make sure that when you start thinking about the project, you don't go down a path that's going to be too expensive later on. So at every turn, at every estimate, we'll do something like that just to ground this group so that you're confident that moving forward, it'll pass them. And with that, I will turn it over to James.

Speaker 2 (13:06–21:07)

Now one of the questions in the RFS that asks us to look into is just to highlight our familiarity with delivery method. So I'll just give an overview of PMA's kind of three delivery methods, two that are in the MAP general law, and then a third one that we've kind of been pioneering the past couple years. So design-bid-build is your general, typical construction project where you complete the design fully through 100% and then you bid it. That's kind of the typical process.

Plus size typically favors a lower cost, but you have to wait the entire duration and you can't do any early packages or complex phasing. CM at risk allows you to bring a contractor in early and then you can pretty much have free reign with early packages. The downside is that it typically costs more than the design-bid-build process. PMA has recently been pioneering a third way, where we do the design-bid-build process, but on the side, we also send out an early package to the 3039M process.

That allows us to get tree clearing, foundation prep, all that stuff processed without the added cost of the CM person. And then, so a similar project that we just are now close out for that continue with that hybrid approach, and I think has very similar. that I did this mill project is the Hingham project we just recently completed. So $114 million construction cost.

It was delivered with a hybrid process. And most importantly, we did it all electric with geothermal while we investigated the MSBA's green school program, which I know this project is gonna have to consider as well. So I know considering this project, Next, we have slides that kind of highlight what the preferred site might look like if we did the hybrid process. So this is what the existing conditions look like.

And then if we move to the next slide, we see what we could proceed with moving the access road. That we can do over a summer. That's one of the benefits of being able to plan out early packages. We can target this for a summer when the high school will see a lot less traffic.

This allows us to clear trees, get the building pad open, and get construction entrances off of the main road so that when school comes back in the fall, everything's totally separate. And then the next slide is the final condition. you know, of what the site would look like if this is actually the preferred site. One thing to note before I move on is that we only did this for this site, but we will investigate these options at the other two sites as well.

So just to kind of wrap up on highlighted projects, we have, we are familiarity with all the design, And we have plenty of experience with ad renos and new builds. But just to close out this point, we won't be able to make any recommendation for what this project should do until we get further into design. We don't know what's gonna change from the last project to this project. So we foresee that recommendation coming during the SD phase.

And I'll turn it over to Mitch to talk about project control. Sorry. Awesome. Thanks, Seamus.

Yeah, so the next couple slides I'm going to hit on project control, starting with schedule. So what's shown here is an example of one of our typical project schedules. We'll create this and maintain this throughout the whole project lifestyle. During construction, the contractor will submit monthly schedule updates, which that.

We'll work with them to come up with a complete analysis of that construction schedule and make sure everything's up to par there. What's important that I want to note on this example that we have shown, you see some yellow bars here with some potential cost savings. So given PMA's experience with the designers in the area and our relationship with them, we feel that we can accelerate the schedule during certain phases, such as schematic design and project funding, which versus a typical MSBA job can be potential savings to the town of Milton. On this example, the project costs about 150 million and the savings is projected at 6.75 million.

That's just one of those project saving methods that we think that we can work with the town on and the designer when we get to that point. Then on the next slide, I'm going to talk about a few more of those cost savings and staying on budget and schedule. The first one, we have the designer RFS draft ready to go today. We're ready to issue that, we're ready to work with the town on that.

You know, going along with what Seamus mentioned, another cost saving potential is the hybrid delivery method. So we've had a successful project for that, getting the ground prepared so that the base bid contractor can hit the ground running. We also like to work with the committees to guide the committee to make timely, scheduled, focused decisions. It's a group effort.

It's not just PMA and the designer doing that. We're working with the stakeholders involved. And then lastly, we like, this project had a previous construction costs as well. We know we have to stay within MSBA board dates and timelines and guidelines, so that will always be taken into consideration.

On the next slide, we'll get into our project cash flow. So PMA will again maintain and create the project cash flow from day one. This includes the total project costs throughout the life cycle of the project, including the district costs, which you'll see located with the gray line, and then third party funding, such as the MSBA grant here. And it's important to note that the cash flow is not just for tracking costs.

It's also can inform the town on the borrowing needs when it gets to that point. When you need to borrow, how much you need to borrow. So we like to get that going right away to assist the town as needed. On the next slide, we'll get into our budget.

This is our… Okay. On this slide, this is our total project budget. So this is the summary.

It's an overview. It's about a 10,000 foot view. We can get very granular depending on what we need to do or what the town wants to see. This will be involved with monthly reports to the MSBA as well.

So we track every invoice, every contract in this budget to align with the MSBA cost codes. And so when we seamlessly submit those reports, everything's all aligned. On the next slide for project controls, we're gonna get into contingencies. So with the contingencies throughout the course of the project, we track all the costs as well, as I showed you in the budget, but we also track any changes we need to.

So those changes could include a designer soft cost changes, contract amendments during the design phase, and then getting into construction, all the construction change orders that we have to track, if there are any that were related to the construction of the projects, they could be design, they could be owner requests, third party requests, et cetera. So we'll track those. We also review those changes in detail. Some other competitors might not do that, but PMA team goes through manpower, hourly rates, labor rates, et cetera, to making sure that everything's there's a technical review committee, or if it goes to the select board for a contract change, we'll work with you on that as well.

And then moving into the next step after you hire an OPM would be the designer selection. As I mentioned, we have the RFS ready to go. It's drafted up. Might be a few dates that we have to iron out there as a team.

And then on the left side of the screen, you can see a potential grading rubric that we created to have different criteria for all the designers that submit. And as we get into the designer selection panel, we'll work with those key members to help get this process going in line with those design selection.

Speaker 4 (21:22–21:33)

PNMA is unique in that we have a full marketing department that helps with community outreach. We can create websites or update these project websites with important information.

Speaker 2 (21:34–21:44)

We have video updates, forum virtual tours via Facebook, Livestream, or simple posts on YouTube. And our team usually manages social media accounts.

Speaker 4 (21:53–22:35)

I can attend all community events, whether it's weekdays, weekends, or at nights too. What's on the screen now is the sample community engagement efforts. YouTube videos. And the last thing I wanted to bring up was since the cost is usually one of the biggest factors.

Speaker 5 (22:47–24:00)

All right, and just to wrap it up, just a YPMA, we are an OPM only firm. We're homegrown, we train talent, we don't acquire other companies and use their resumes to try to get work. We've done over 50 MSBA projects. We're the only OPM firm the MSBA has ever hired directly for our Essex Tech project.

Our teams work on site. We don't work remotely. We'll be in a trailer on site. We typically have three or four people there on a daily basis, including the clerk, APM project manager, and senior project managers.

We feel that it's really important when you're paying people to be there, they should be there, not sitting at home. And it really does help form a rapport with the contractor and the designer. It makes for a much better project. So we like to form a team and we like to work to that common goal of getting a building done.

We feel that being on site is one of the key ways to do that. We also have a big bench. We've got a lot of people in the Boston area. So if we need extra people, we can bring their talents onto the site as well.

We're familiar with Milton. We live here. We pay taxes here. So I think we want a robust project that's built, but also built for the right costs.

And we'll be here to also keep everything in check. So I think we've used up our time for that. If you want to roll into questions, we'd love to get into that conversation.

Speaker 9 (24:01–24:01)

Great.

Speaker 5 (24:03–24:04)

Thank you.

Speaker 3 (24:04–24:14)

So essentially what we have is what they call five standard questions. They're standardizing across all the agendas. There'll be follow-ups by individual members of each one.

Speaker 2 (24:14–24:21)

So I'll start with the first. So first question is, we are developing

Speaker 5 (24:32–25:48)

So I mean, we know that we've done enough MSBA work that I think we have a good database and a good information of what the town needs to decide on these. And oftentimes, it's cost is the biggest issue, but it's not the only issue. So we need to work with the design team to make sure that we're laying out all these options and all the pluses, pros and cons, so that people can easily digest it. There's no, you can't go to a committee with thousands of pages of documentation, you need to really Pair it down and given the essential information of what's important.

Why why the decision for the committee is made here? Why is this and not that and hopefully bring them to the right decision? We, even with the voters to, we can't advocate for the projects. We're not allowed to legally not allowed to, but we can do is provide good information, the right information and making sure that.

the Facebook posts that are giving all sorts of disinformation are corrected and that we have a good resource for people to go to and look for the correct information. So I think getting the message out is really getting correct information out at the right time and really helping evaluate these solutions. I mean, we've done enough schools that we know some of the pitfalls, we have lessons learned, we have a lot of people in our office that can help out with that and just trying to help this committee come up with the best solution to present to the town and provide whatever information you need to do that.

Speaker 2 (25:48–26:03)

I'm just going to add in there too, starting from the beginning with open and clear communication, and then starting with a great educational plan that's going to work for the project. It really starts that foundation, and we'll kick off that educational plan right at the beginning with the designer and get going from that process.

Speaker 5 (26:04–26:09)

You already have a pretty good one from the last time, so it just needs to be updated and resubmitted to the MSBA for their review.

Speaker 3 (26:20–26:23)

We'll move on to the second question then.

Speaker 2 (26:25–27:41)

Second question, can you provide an example when an MSBA project you were working on was running over budget? Can you provide an example when an MSBA project you were working on was running over budget? What problem solving approaches did you attempt to implement? And what was the conclusion?

What were lessons learned? Yeah, we've run into this multiple times. Cost is a tough thing to track. But what usually happens is when we're going through, once we get through schematic design and the numbers pass, and we get into DD and all the way to CDs, we'll have to really look at those, and even this can happen in schematics too, but we'll look at the value engineering options that we need to get the project back on track.

and that's not going to take value out of the building or out of the educational space for the town. You have to look at the exterior. Exteriors have large sites. With large sites, you have a lot of numbers there that are not fully reimbursed by the MSBA given their low cost cap that they have and the inaltra cost of the site work.

We look at site items, we look at interior finishes, and those are tough for us. It's tough conversations to have with the designer because we want to get the price down to do what's best for the town, but we are good at having those tough conversations and working together collaboratively to drive those costs down.

Speaker 5 (27:42–28:53)

Yeah, from day one, we always have a VE list. It's always nice to haves, wants to haves, and kind of have those running costs so that at every phase, the estimator gives you a real price on those and what they're worth. We also use alternates. Oftentimes, it's fields.

We'll have an alternative to do a field later on, depending on how the bids come in, because you don't really know where you're at. You can do all the estimating you want. You don't know until the bids come in. So by the use of alternates, you can keep some work on the side, and then even later in the project, you decide that, okay, this is something we want to pursue.

You should re-engage the contractor and talk about adding things back in. But we are, you know, use of contingency early on, having pricing and escalation contingencies built in is a key. Your estimator will start that from day one, and then they'll run that down. That number will start at 10%, then move to eight, and then seven, five, and as you go, closer to construction, the contingency numbers run down, but we want to make sure we have a robust contingency, because if we bid on a project and it's over budget, that is not a situation we want to be in, because then you're either stopping and rebidding and redoing drawings, and then you're losing that window of engaged bidders, and you're losing, you're gonna, you could eat up some of that cost and cost escalations over the time it takes you to do that process.

Speaker 4 (28:57–29:41)

Yeah, just trying to think of what my question is, but it's focused on a follow-up question about communication. And, you know, as you're sort of troubleshooting that, you know, being over problem-solving phase, what's your communication look like with whether it's a school building committee or whoever your point person is with the town? Is it, you know, I know you'd already mentioned your monthly, you know, budgets that you're providing at MSBA. So maybe that's one touch point to just be communicating to you, you know, do any kind of special communicating during those phases, you know, probably not phrasing this perfectly, but yeah, I think so.

Speaker 5 (29:41–30:17)

Well, I think our channels of communication is typically through this committee. Yeah. And sometimes there'll be like a working group or a subcommittee, if you will, to have You know, if we get into a situation where we think we have budget problems, you may pull some members of this committee off and have, you know, a separate working group and we communicate directly with them more intimately instead of the, or we have the full committee meet more than once a month. I mean, there's no, particularly around budget.

You may need to have additional estimates. You may need to meet more often. And if that's what needs to happen, but we will not go outside the committee and start talking to other people in town about costs. It's the channel of communication needs to stay here.

And then what the committee decides and how they decide to present that is really we'll,

Speaker 2 (30:25–30:54)

when you're in the feasibility study and schematic design. So I've had an example recently where we've had to summarize what happened during the PDP, which is the Preliminary Design Program, and PSR for the school building committee. Because sometimes people volunteer in these committees, they don't have the time to look at all the thousand pages of the PDP. So we're summarizing, we're moving fast.

But then it's like, okay, we have to slow down, but make sure everybody's on the same page. the important data that's going to be going to the MSBA.

Speaker 5 (30:54–32:03)

I think there's two numbers you really need to look at. Once you submit to the MSBA at your SD, they lock in at project scope and budget what your budget for the project is. But before that, the committee really has to make a decision what they think the budget can be and what that can support. And we'll do lots of effort with the engineers of lifecycle cost analysis of the HVAC systems.

And that's usually the biggest part you go from a geothermal system to an air source down to a system, it's millions of dollars just by changing the mechanical system. But if something, you know, having a geothermal building is something that is a strong tenant of the project, we need to keep that in there and find other things to do. So really understanding the cost early on so that you can set the budget correctly, which you think the town will support is really we have to value each year down from that. But at that point, we should know enough about the project to have a pretty good estimate from our estimator and that our designers estimate that the CM comes in their estimator, that we should feel pretty comfortable going into that.

Unless you have some string feeding environment, we usually within our contingency, we haven't had, I don't think anything recently that we had to go and rebid.

Speaker 2 (32:05–32:14)

So one question I have is outside of like third parties. you mentioned geothermal.

Speaker 5 (32:14–32:41)

Geothermal right now, there is huge IRA rebates, but we just don't know how long those are gonna stay on the books. So once we get into the design and the mechanical engineers will have a lot of information, I believe we'll have a lot of information and they'll build that, those rebates into the lifecycle analysis where right now it's very favorable to do geothermal if you can fit it on your site. But if those grants run out before your construction starts, then it's gonna be a totally different story. So we just have to monitor that as we get closer to construction.

Speaker 2 (32:42–32:53)

Right, and we typically include sustainability consultants in with the designer RFS, so that they'll have someone on their staff who can help guide and tell any process for any grant applications.

Speaker 5 (32:53–33:15)

Could you just share any of your experience on, obviously, like we've talked with y'all previously, you supported us with the 6-7 upper middle school project, but in terms of the Laboree, that's a little bit different in that it's a potentially, in addition, we haven't quite figured out, but potentially, in addition, renovation of existing space. Can you talk about like a project you've done on that, specifically as it relates to the ability to kind of maintain budget?

Speaker 2 (33:15–33:27)

Because I know one of the concerns we've had on budget is the idea of The energy code right but you were just kind of hitting on like the implications of that for a quarter renovated space.

Speaker 5 (33:30–34:49)

We're looking at the site of generally speaking if you're renovating any building and when you start touching it and ripping it apart you gotta be careful because once you're gonna trigger you could trigger lots of energy codes so like if if you were gonna if you had an existing building that you're renovating it's likely that you're gonna have to strip it down to the steel and for not only energy but for seismic and everything else and so the cost savings 15%. I mean, it's minimal when you look at it, you may be better off, you know, knocking a building down, but it's something you have to do. I know that there's certain sites you have to store, you know, you've got on, you know, I'm sure you get this historic building, you might not be able to knock that down. So there's a lot of different factors in here where like the Cunningham Collicott site, if you look at that, you may be able to add on to that as a quote, unquote, separate building structure.

So you wouldn't trigger You certainly have to build a new section to all the new codes but that's something you'd really have to talk, we have to talk to the engineers and the design team about how the permitting we go with that to make sure that we're not triggering, you know, every thing you upgrade an entire building because that would cost far more than building a new section. renovated 25 years ago, so they're probably not, I mean, HVC systems are probably coming up in windows shortly after that. The rest of the building is in there, for our show last week or two weeks ago, it's in pretty good shape.

Speaker 2 (34:49–35:06)

Yeah, just to put things in context, so for MSVA and Laboratory, they'd only be able to look at the way the RFS was written, the K through five, the whole school there. not be part of this process.

Speaker 5 (35:06–36:35)

Yeah, I understand that. I'm just, again, as a potential site for the project. You would likely be able to, before like the pre-k through five option, you would likely be able to renovate that, but you'd have to include all the grades. It could not just be a standalone kindergarten, pre-k, early education center.

Yeah, I was just worried about your experience with managing budget on that type of project, right? Not just a kind of ground up. Yeah, I think it's similar, but typically you have more contingencies upfront for the unknowns and you do more upfront work. You try to spend some money on the designer to get in there with some people, poke some holes around and really figure out what that building is.

Do some fact finding, you know, or you make an assumption that everything's going to go except for the steel and build it back up from there. But then you come into asbestos problems and PCBs and mitigation and things like that. I think I know the answer to this, but what's your experience with the tech? Because that's a change of use.

This isn't renovating a school and expanding it. What's your experience with a project where you're actually changing the use of a building to become an elementary school? We've done it temporarily, which I think for CodeWise, there is no temporary. We've done it where we fit out extra buildings to educational spaces, swing space for some projects.

But I think generally, we don't change a house into a school. I don't know that it's very common to happen. It's either you renovate an existing school or sometimes district will have an old school building that hasn't been used in a while and they'll use that, either a swing space or they'll renovate that spot and then flip-flop there.

Speaker 2 (36:35–37:42)

Thank you. Any other questions regarding costs? I just have an answer to you. I worked in the town of Saugus.

We did the new middle high school for them. And then in addition, we did two smaller ad rentals right around COVID times. And controlling costs for ad rentals is really important to get the building officials walking through the building and just saying, hey, if you had to update the code, what would you do now? Before we even got up to bid time, because it's easier for them to walk around and say, oh, add a fire alarm there, oh, that should have a different exit device, that sort of stuff during design, so we can include it in the bid documents, versus it comes time a month before move-in and the inspector walks in for the first time and says, oh, that's wrong, that's wrong, that's wrong.

Get it early, put it in the documents, and that kind of helped us. Third question, what is your closeout process to close the project quickly and avoid a drag-and-drop? That's a great question.

Speaker 7 (37:43–37:44)

It's a tricky one.

Speaker 2 (37:44–38:25)

No, but honestly, staying organized from the start all the way through the closeout. If you drop off, if you miss one invoice and if you're going to close out and you have to backtrack and find where that invoice was, it creates a whole bunch of havoc with the MSBA system in the final audit. I know because I'm going to, but like, yeah, stay on that. And yeah, the MSBA closeout process is, it can be fast or it can drag out, like you said, but we want to turn them around as fast as possible.

You know, there's some things that are out of control. If litigation happens, you can't close out. about the experience as well.

Speaker 5 (38:26–40:00)

Even for the builder proper, I think the key is you got to keep enough leverage on the contractor to keep them interested, to keep them engaged. And if their work isn't done, then you just don't pay them for that work. That's kind of the only way to keep work going is to make sure you have enough leverage over them so they don't disappear. The other thing is scope creep.

At the end of the project, sometimes you have money and the owners like to add more stuff. Let's put a softball field in, let's put this in and it's fine if you want to do it and not an issue but trying to close it out and trying to get contractors to re-engage when they're already kind of a you know they've wiped down the last shelf and they're walking away it becomes very problematic so to the extent that you can keep your scope to within whatever the project is, and then maybe bid that out separately. It's probably a better suggestion than trying EDL. And when they tell you, we have the contractor here, it's going to be easier for us to do it now.

But then you're not getting competitive bid pricing oftentimes. And I think it's much better just to close out the project and then move on. The other thing we've been doing recently is we'll have an APM go through the entire spec book and pull up every warranty, every closeout item, we'll make our own binder, and we'll turn that over to the contractor. We won't wait for them to do it.

We'll say, hey, here's all the stuff you owe us. We expect you to fill this out and give it to us. Help them help themselves, making sure that we're on top of what we understand what we expect. And then the trainings too, is making sure that we have the right people being trained.

It's videotaped. And then even with these new projects, often you have people leave and then the next people who come in haven't been trained properly. So make sure we have copies of all that documentation. And then we'll sit through the trainings as well so that we can make sure that we understand how these systems work, that we can help train new people in the company.

Speaker 2 (40:00–40:29)

And then lastly, to build on what Sean said, is just stay on top of GC, the architects. Often, we have weekly owner-contractor meetings during construction, and often after closeout, people want to go every other week or once a month, and it's really just stay on top You keep them engaged for longer, keep demanding updates from them as often as you can.

Speaker 5 (40:29–41:05)

It's kind of a double-edged sword too, because there's stuff that they would prefer, little low-hanging fruit that they would prefer just to have someone else do. So there is an option, you can bring in another contractor and do it and take it off their tab as long as you have the money to do so. We prefer not to do that, but we don't let stuff go. If the talent paid for it, we expect you to do it.

And just because it's been six months, it doesn't mean we're going to let you off the hook for it. But I think that it goes back to having a good relationship with the contractors and building that rapport on site. And then usually that people want to help you and they want to continue and they want to close with the project so they can move on to the next one. Nobody makes any money when these things drag out.

It costs everyone an awful lot of money to not finish projects.

Speaker 2 (41:11–41:44)

To the extent that you're carrying scope of services that are redundant to their capabilities how effective GCCM might be. Are you guys comfortable with shedding what comes to you? Matt had said that in terms of project outreach and engagement, that it's kind of your services are a menu of options, but I don't know that that extends to, for example, when you're talking about the onsite IQ, if that's redundant to at a cost-effective kind of level.

Speaker 5 (41:51–42:08)

Yeah. Yeah. I mean, so onsite IQ, they'll, any projects that we work on, they'll do a one month collection at no cost and their ideas, they'll, they'll sell you how great it is. And then you'll want them to come once a week, right?

That they want to get their foot in the door that way. But if you don't want any of the services, you don't have to, we'll take it.

Speaker 2 (42:08–42:13)

Or even the converse. I mean, you advocate on our behalf.

Speaker 5 (42:14–42:20)

Yeah, they probably wouldn't, but yeah, no, I have an experience with that as well. So we, um,

Speaker 2 (42:21–42:45)

light on the GC to use another similar one to OnSiteIQ OpenSpace. And that's the camera strapped to your head and somebody just does it like an APM walks around and the footage was not free and it's blurry and everything. And OnSiteIQ, on the other hand, is a professional with like a different camera set up that's walking and knows what to do. And from our standpoint, it provides a better service than what the GC is.

Speaker 5 (42:45–43:22)

So, yeah, we could potentially flip-flop and not duplicate services for sure. The nice thing with onsite IQ is why we recommend doing it is that after the job's done, you can go anywhere in the building and then it'll give you a list of dates for the So, when the facility's director is looking for, hey, where does the pipe go through, they can go to that on-site EQ, they can open it up, and they have a full time lapse of how that room is constructed, and it has been helpful. It's not super expensive, even the weekly walks, and it's probably on most of the projects paid for itself with change room reviews, and then just aftercare for the facility's part, and being able to really kind of dive into what's behind walls in their buildings.

Speaker 2 (43:47–43:52)

designer and general contractor can be strained. How do you work to maintain strong work

Speaker 5 (43:58–45:32)

So I think the first thing is, like we said, we try to form a real team on site. We try to engage everybody. So, you know, you're not talking across a Zoom, you're not an internet tough guy, right? You're sitting in a room with someone and having a human conversation, and that's a big part.

And I think beyond that, if we've had a job, there's a Belmont Wellington school where there was, he was getting to the end and it was getting contentious on certain items. And we actually brought in a partnering facilitator who they had a session where everyone came in and we kind of, You know, it's festivus here. The grievances brought up the aluminum bowl and everyone got to kind of talk about what the issues were. And I think it helped, certainly in the short term, just to kind of ground people again and understand what the goal is here.

We find, too, that I've been doing this long enough that when I first started, I'd be looking for every dollar in a change order and say, oh, they're charging us this now. We certainly do that and we keep them honest, but it's really the bigger goal is to make sure that this project gets built on time and on budget. And there's some small stuff that maybe you can let go for a bigger goal and service of the bigger projects. And I think when you get people to buy into that mindset, you certainly have a better project on all ends.

I don't know that we've had some super issues with the design team. Sometimes in design, there's things that they would want to have in the building that maybe we would say this doesn't make sense or it's too expensive. At that point, if we were at an impasse with them, we'd certainly come to the committee and try to have a session where we talked it through and did pros and cons of both of it and maybe have the committee try to facilitate what's the right decision for the town instead of letting one party decide either way.

Speaker 2 (45:32–46:26)

We have had a recent experience in the Bristol Moor Project with a designer, where there was a small change order thing where the contractor had one view and the designer had another, and they couldn't come to a compromise or really be in the middle. So what TMA did was we asked separate independent architect that we were working with on another project, just to kind of help us out and see what their independent high-level view was. And they helped us reach a goal that got us to a recommendation to the owner that resolved the issue. I think everyone's now happy with the resolution of that.

Good question, Sean. You kind of partially answered the question I was gonna ask. I was a CA architect forever, so I know these conflicts are brutal, and 95% of the world will change orders. So I'm curious what you're changing the process is, how do you?

Speaker 5 (46:27–47:38)

kind of avoid these conflicts that are inevitable between the architect and the contractor. I mean, step one is merit. We always, we don't even look at the costs until we decide whether or not it's an actual change, which seems pretty basic, but you have to, you have to do that. And if it does have merit, then we have different tools.

I mean, we have strong front end language that we've added to over the years that go on top of like the standard DECAM form of contracts to limit like labor rates and to limit what your markups are. And if you're very clear about that, a lot of that fight goes away and then it's purely what's on the drawings. And we do rely on the architects and engineers. They are the, by and large, they are the arbiter of their drawings and specs.

But we also have an opinion on that. So we try to work with them and sometimes even play devil's advocate. If they think their contractor owns it, we may take a position of why we could see the contractor not owning it. So when we go into the meeting with them, we have some better negotiating point.

Also, nothing against architects. Sometimes they're black and white. You know, you're a CA architect, right? This is the way it is.

And I think the contractor is also the same way. They have very black and white, and we try to meet in the middle. And sometimes you come up with some sort of compromise between the two parties where neither of them are 100% happy, but that often means that there is a right solution.

Speaker 2 (47:38–47:56)

And we also like to control the master log of all the change orders, and we never let any change order go, or potential change order PCO be unreviewed by us. I think you threw in a fault. Did you track fault in your change order log? Like this was a result of design or design?

Speaker 5 (47:56–48:07)

MSBA requires you to, yes. But it's more, there's like five categories that it goes in. Is it a design issue? Is it an authority having jurisdictions in order to change?

Unforeseen condition, things like that. Yes, we do track all that.

Speaker 1 (48:11–48:11)

Thank you.

Speaker 2 (48:12–48:25)

Last one. So question five, community outreach strategy. What expertise does your team have in bridging information between design construction teams and the community as the project evolves?

Speaker 5 (48:26–50:21)

So, I think we work, I mean, the design teams nowadays are very, I mean, they're very sophisticated in their graphics and their 3Ds and their flybys and things like that, which is great to show. So, we bring that forward. And then with us, I think we try to pick with the community, pick the facts that we want to get out there. And like I said, we can't advocate.

We're not allowed to present one, but what we can do is present information. We can correct information. So one of the things we find really powerful is just on a website having frequently asked questions. And sometimes we'll see that with questions we know, or we'll see some misinformation out on some Facebook site that says, hey, do you know they're doing this?

And so we can throw that up in the frequently asked questions and answer it. So if somebody wants a real answer, they can get it. Also getting people to come to the building meetings. I mean, they were very sparsely attended.

the last go around and then you go to town meeting and apparently everyone has lots of opinions on different things. So, I mean, to me, I don't think town meeting is the appropriate place to have those conversations. I think in a room like this, we also host, like Mitch said, community forums where we'll have an information session. We'll try to get people out.

We'll do it in different areas in town so that at different times of day, sometimes you can have them during the day, sometimes you'll have them at night, you can have them on weekends. To try to get as many people involved and to come to those so that they have a really good sense of what the project is, and they have the correct information. So that when people are telling them now, do you hear the building 12 story dealing with the pool on the roof? They can say, actually, they're not because I was there and I asked a lot of questions, but.

Really, we're here to give the correct information and not sugarcoat anything or hide anything because the people in this town, they're very smart and they're not going to believe you if you lie to them. And I don't think you have anything to gain from by twisting any facts or things like that. You come up with a plan, you present that plan, and you stick with the plan. I think that's the best you can do.

And provide accurate and real information is 100% the way to go from day one.

Speaker 2 (50:21–50:30)

And sometimes it's as simple as just inviting them to a site to work. You know, you show them the Cunningham library and they go, oh, or, you know, Muir's library.

Speaker 5 (50:31–51:00)

Like, oh, okay. Yeah. This isn't just academic. And you have the video too, which is pretty compelling when you go through it.

And I've got both my kids went to Cunningham. One's in fifth grade now. So I know for the past six years, how tight that school has gotten and even more so in the last couple of years. So, um, um, I don't know who in the town doesn't think you need a new school.

I mean, if the MSBA is inviting you to their program, and approving you and telling you you need a new school, then you need a new school. They don't give money to towns that don't need new schools. It doesn't happen.

Speaker 2 (51:02–51:08)

Any follow-up questions?

Speaker 5 (51:10–51:22)

All right, excellent. So my contact information is here. If you email me or Milton at PMA Consultants, we'll all get that email and be happy to provide any information you need. And thank you very much for your time.

Thank you.

Speaker 4 (51:59–52:08)

Are we on schedule for the 15-minute break here? How are you? OK.

Speaker 3 (52:13–52:23)

Is everybody here? Shall we meet immediately? Yeah, I'll need to change my mind.

Speaker 2 (52:26–52:29)

There's one each? Three each.

Speaker 4 (52:30–52:31)

Oh, three each, right?

Speaker 8 (52:32–52:41)

Three each, yeah. Two more. Can I need to back down this way, sorry?

Speaker 3 (52:41–52:50)

No problem. Do you need two more? Thank you. Three short.

You got some extras over there?

Speaker 10 (52:50–52:52)

I just got done looking at John's picture.

Speaker 2 (52:53–53:11)

Of course. I can do it. I can do it. No, Nick did it to me.

I'll talk to you soon. Oh, what do you have? You're not in the game. That's why.

I didn't count you. You're here for fun. They schooled me in. I took out a note.

Speaker 3 (53:41–53:43)

All right, excellent.

Speaker 2 (53:43–56:36)

So we just got done finishing up our scoring. I'll call the School Building Committee back to session next. How are you guys doing? Good.

Where is the best spot for the person that controls the presentation? You just log in to the Wi-Fi? Yes. We got that in.

While Brendan is connecting, would you mind if I make an opening statement, please? All right, beautiful. So good evening and thank you for having us here tonight. We're excited to be here in person.

So you can put faces to the names of the team members. Before we begin, I want to note that Jim Rogers sends his regrets. He couldn't be here tonight. Jim had a long-planned family commitment that he just was unable to schedule.

I've been with left field for 10 years. This is probably a second interview. He is not able to make, but he's fully engaged in the opportunity has been involved in preparing tonight's presentation. My name is David saying, and I'm a senior project director with left field.

In addition to my role as project advisor. on the project, I will also be Joe Rogers tonight. So we understand and respect the 15 minute presentation timeframe. That said, we kindly ask if questions would be held until the conclusion of the presentation.

We may be moving through the presentation fairly quickly. If we go through a slide that's too quick, just let us know and we're happy to come back to it during Q&A. Thank you. Yeah, so as you noted, you get 15 minutes for the presentation.

I'll give you guys a five-minute heads up. We need about 10 minutes or something like that.

Speaker 7 (56:36–56:36)

OK.

Speaker 2 (56:36–56:46)

I apologize if I interrupt. No worries. But just as far as the committee here, I'll let us introduce ourselves. Hi, I'm Nathan Hutter.

Speaker 3 (56:46–56:51)

I'm a member of the school committee. Mark Loring, member of the school committee, lecturer of the school building committee.

Speaker 4 (56:52–56:56)

Pete Obershamer, member of the select board and of the school building committee.

Speaker 8 (56:57–56:59)

Harry Harland, member of the School Building Committee.

Speaker 2 (56:59–57:19)

Tim Lombard, School Building Committee. Sean O'Rourke, Chair of the School Building Committee. Clyde Hoffman, School Building Committee. Scott Terschak, School Building Committee.

Bob Mayhew, Town Facilities and School Building Committee. And there's one member of the School Building Committee, Akbar Obama.

Speaker 3 (57:19–57:23)

So with that, I'll let you guys take it away. Like I said, I'll keep times, but I'll give you guys a heads up.

Speaker 2 (57:28–58:27)

Jim Rogers established Left Field in 2007 with one employee. 19 years later, we're 73 employees strong. Our focus has stayed the same since day one. We put the client first.

We bring significant MSBA experience across all school levels from elementary, middle to high school. A vast experience allows us to help communicate and procure a designer, evaluate the right construction delivery approach, manage risk, maintain control of the scope, schedule, budget, public communication, and most importantly, public outreach. Recently, Leftfield joined Cumming Group, which provides our clients with access to a broader project and cost management resources while preserving the local hands-on approach that Leftfield has been known for. So while we are 73 employees strong locally, we have the added support of a 3,000 person global platform.

Speaker 11 (58:27–58:42)

A few statistics that we are proud of, 75% of our business comes from repeat clients. We currently have about 4.4 billion in active public projects, and we have a 97% employee retention rate. For Milton, that means team continuity.

Speaker 2 (58:42–59:46)

The people you see in front of you tonight, with the addition of Jim Rogers, will be the same team throughout the entire project, and closeout, and through the MSBA audit. In short, Leftfield brings a deep pool of talent and experience, MSBA knowledge, day-to-day project management expertise needed to support Milton through your MSBA school project. In short, that's it. Next slide.

All right, we're gonna do a quick introductions. So thanks again for having us. We're excited to be here. It's really an exciting project.

The core team is here. We bring together a broad range of experience on our core team. So between myself, Jen and Matt, we have backgrounds in engineering architecture and construction management, and we all have deep experience with MSBA public sector school projects. I'll be your day-to-day point of contact from the beginning of the project all the way through the end.

So, as David said, continuity in our team is our strength.

Speaker 7 (59:49–59:51)

I was actually particularly excited about this project.

Speaker 2 (59:51–01:00:55)

Being a close by neighbor over in Rosledale, it's kind of exciting to have a project right down the road. We're used to traveling, but being able to be to the site in 10 minutes is definitely a nice advantage. So, what I'm going to do is have the rest of the team introduce themselves, and then we have a few folks that I want to highlight that are on our team. Yeah.

Hello, everyone. My name is Matthew Delino. I will be working very closely with Tim. I'm closing in on 15 years of construction management experience.

100% of that has been in the public sector, and about 95% of that has been K-12. school building projects in Massachusetts. Like Tim said, we're very well versed in the MSBA process. It is really what a lot of this team has dedicated their careers to, has been to the betterment of public education.

So I'll hand it off to Jen.

Speaker 6 (01:00:55–01:01:26)

Hello, Jen Carlson. I am the project manager on the project manager team. My background is in architecture and construction, and I did I've worked at the MSBA for a little bit. So I've been working on MSBA projects for the better part of 16 years.

And I've actually probably been working with Tim on and off for about the same amount of time. And with Lufffield for seven years. Again, all of this was in public realm of work.

Speaker 2 (01:01:26–01:01:56)

So I'll hand it off to… Hello, I'm Brendan Walsh, Lufffield MEP coordinator, got over 25 years Construction and Trade Experience represent a team of four MEP experts in mechanical, electrical, and plumbing. We work very closely with your project to identify opportunities, deficiencies, et cetera, to try and shape that program feasibility and schematic study the way that you need to deliver the proper building.

Speaker 7 (01:01:59–01:02:29)

Good evening, Josh Brewster. I'm the relocation manager for left field. My career began in the United States military, where I trained in aviation operations, completed 3 consecutive tours in Baghdad, Iraq, and upon coming home to the civilian sector. entered the commercial moving industry where I've been for the better part of the last 20 years.

For the last eight, I have been specifically focused on municipal and education projects, and over the course of my entire career have successfully relocated over 45 K-12 schools.

Speaker 2 (01:02:30–01:03:40)

All right, so not here tonight, but you can see on our org chart some of the key experts that we have on our team. Andy, up in the top right, he'll be our site rep. He's a former architect himself. He's got extensive experience and brings a great perspective to the project.

We engage them early. They participate in our design review process and then come in full time during construction. Kevin, who you can see in the second row there, Kevin Sullivan, he's our public outreach expert. Kevin's background traces back to the MSBA, so he has lots of great insight on consensus building, so helping us get the public support and get to the vote.

Adele is our education liaison. She is a former school superintendent, so she brings that perspective to the project. She's involved really early on and throughout to assist in the visioning and community outreach process. And finally, Terrence, he leads our design review and value management process, which occurs on a rolling basis throughout the design phase.

Next slide. The next one.

Speaker 6 (01:03:42–01:05:30)

All right. Your project has the potential, so much potential, to reshape education in Milton, while also solving several other issues you have around town in different buildings and different grades. And this is your one big shot to really get that right. We have a team that has a lot of experience working on projects that have complex variables and helping communities like yourselves work through the analysis of those variables in the public eye.

To start, I will talk a little bit about my project in the Galvin Middle School project in Canton, Massachusetts, right up the road. That project started out with the question, do we bring grade five into the middle school? Long story short, yes, the answer was yes, they did. And that came through a process of a lot of community engagement, which is very important.

It was very important that the project team listened to the community, provided a lot of opportunities for feedback, while also giving them the information that they were asking along the way, so that there was really an authentic bond between the community, the project team, and the local leadership leading that project. It was really important, I think, to go through that process and make sure that we were working hand-in-hand with the community so that there was that early trust that was built between the community and the project team so that later on down the line when we were telling them how much the project's going to cost and things like that, we were credible source of information for them. The others on my team have also been through the process.

Speaker 2 (01:05:30–01:11:20)

Matt, did you want to add something? Yeah, excellent. Yeah, so these three elementary schools that you see up here are all very similar to what Milton is looking at. They all study multiple grade enrollments.

There were some consolidations of schools in some of them. So they all, or all three of these, went through a very similar process that we'll be going through. The Brown Elementary School consolidated three schools into one. That freed up some space in one of their elementary schools that was now being consolidated to keep their pre-K program in.

East Bridgewater did a very similar thing, consolidating their grades. They brought pre-K into their elementary schools as well. They did elect to stay at K-2 rather than going to three. A lot of those decisions do come around potential costs.

As these buildings get bigger, they get more expensive. So that's something that we'll certainly work through with you. beyond the best plan forward for what needs. All right, so we're gonna talk a bit about your project.

And we're gonna try to get through this quickly and welcome more discussion as we get to the Q&A. But we know the big driver here is overcrowding, right? That's a district-wide issue that you're grappling with. And not surprisingly, there's huge demand to get kids into the middle school system.

And you've done a great job in maximizing use of available spaces. From what we understand, it's pretty maxed out. in the middle of summer, Cunningham for the third and fourth floor reconfiguration. So that would be a great near term fix.

And we see from that, that there does appear to be some good community support. So that's a good sign, sort of an understanding of the problem, also a good sign. So we're excited to kind of build upon that, right? So as we continue that community engagement, maintain that support, and then sort of the community behind the larger investment in the long-term plan.

So the long-term plan, got a bit of a jumpstart there, too. We've gotten familiar with the work done previously, and we know that you've looked at a number of middle school and pre-K building at the Gallo Road site. That's a great way to comprehensively address the overcrowding issue. We know you faced some challenges as you worked your way through that early phase of that project.

You have the land swap and of course, cost for a new construction of that size, but excellent job and kind of two big wins there. The land swap is approved and now getting into the MSBA program is a huge win in terms of bringing down the local cost. So great starting point as we get into the feasibility study phase. Next one.

All right, so we're into module two of the MSPA process. You can see here it's kind of mapped out, right? We're in the beginning. It's structured, a bit protracted, but we know how to navigate it efficiently.

And we really use it to our advantage because it was a systemic approach that builds trust and credibility, right? So the community will know that we're not just rubber stamping an option. I will document that we've done a thorough review of all the options and the preferred option truly is the best one for the school district. Next one.

We've thought about what's going to drive success on this project. We've outlined in detail here, I'm just going to quickly run through, getting the right team on board early is going to be key. We need to have a credible and objective team, and we know the MSBA process and have a great track record of building public trust. We'll take full advantage of the work completed today, but we want to validate it through an open and comprehensive review of the options.

We need to continue that clear community engagement and maintain support as we get closer to asking for funding for a larger project. As we move our way through the process, schematic design is a huge deliverable, and that's what we form the budget based upon. It's early in the process, so it's important that we get that right, but we have tools to make sure. That budget is comprehensive and valid.

We stay on track as the scope moves forward. Every milestone we check in and we make sure that we're not varying from that approved budget. We're the gatekeepers. We let you know in advance.

This is a cost impact. This is a schedule. I think you all have seen the feasibility study agreement, and we've dissected it as well. We understand there's a complex set of enrollment options to look at.

We also anticipate looking at several sites, and we saw a little bit of a wild card with the Labore College site. I think as you heard from us earlier on, we've done this many times. a very simple decision-making process so the public is clear on what's driving the decision. Ultimately, we want to make sure we have conclusive support across all of the town management, as well as with all the constituents.

I'm happy to come back to this in more detail, but I know we're running short, so I'll stop. All right, so this slide quickly, we have a lot of different vehicles that we can use for public outreach. Next slide.

Speaker 11 (01:11:22–01:12:02)

This slide highlights our recent experience with two, with Social Tech. Over roughly two months, we participated in 48 community touchpoints across the region, ranging from PTO meetings, advisory boards, veteran events, community events, market school events, town meetings. The takeaway here is that the outreach was not limited to formal meetings. We went directly to where the residents were already, helping the community understand the project need.

The effort supported seven successful regional agreement town meeting votes and ultimately the project passed. Next slide. This compares two elementary school projects in neighboring communities with very different outcomes, particularly those with public communication.

Speaker 2 (01:12:03–01:12:22)

Preparation we had and overall approval strategy matter. In West Bridgewater, the project did not advance beyond town meeting, While in East Bridgewater, where Leftfield served as the OPM, the project passed both town meeting and the ballot measure. Next slide. This slide shows a similar comparison of the regional location of school level.

Speaker 11 (01:12:22–01:12:30)

Old Colony Regional did not pass at the ballot, while South Shore, the previous slide showed earlier, supported by Leftfield, passed overwhelmingly.

Speaker 2 (01:12:30–01:12:42)

Again, every community and project is different, but this reinforces planning, clear messaging, consistent outreach, and helping voters understand the cost schedule and benefits of the project. Next slide.

Speaker 11 (01:12:43–01:12:53)

This slide is my project, Wilmington Elementary School. This project received overwhelming support at a special town meeting and carried that momentum into a successful ballot vote a few days later.

Speaker 2 (01:12:54–01:13:20)

with 62% voting in favor of the ballot. One data point to mention here is that not only, that's not in the slide, is that we were hired as a replacement OPM right after the systematic design. We quickly had to get acclimated to the project and then participate in a robust community engagement process to get the successful vote. So a common thread through all these examples is that local approvals require more than a good project.

Speaker 11 (01:13:20–01:13:28)

They require preparation, organization, clear communication, and a project team that understands both the MSBA process and public facing process.

Speaker 2 (01:13:29–01:13:38)

We want to help Milton stay ahead of the process, and I always tell clients, you need to tell your own story before someone else tells their story.

Speaker 11 (01:13:39–01:13:50)

We will anticipate questions, support the town and school leadership, clearly communicate the need and facts, and keep the community informed on feasibility through local approvals.

Speaker 2 (01:13:50–01:15:49)

With that, I'm going to turn it over to Tim to wrap this up. All right. Just a quick closure. We know that you have three capable firms that you're considering, but we're confident.

We're the best team for this job. With us, you'll have the highly qualified core team on the project that you're hearing from today. We're going to be the faces you see from start to finish. And we have the support of significant internal resources, which I think really separates us from the competition.

Our secret weapon in educational visioning, our MVP experts, our MOVE experts, our community outreach experts. are critical in getting that community support. Together, we bring a fresh perspective to restart this project. We have plenty of capacity to do that, and we're ready to get to work tomorrow.

Thank you. Thank you. to facilitate town officials' decisions on final project options? So, I'll start, and I'll let, obviously, my colleagues pipe in, but I always tell clients that we can sit around the table, and we can always think we're the smartest ones in the room, everyone, but I always say on certain decisions, you have to look through the lens

Speaker 11 (01:15:50–01:15:55)

what's going through the minds of the individual at the ballot box?

Speaker 2 (01:15:55–01:18:35)

Because we may think, oh, this is the best solution, but is that gonna pass the measure? So, I mean, not every decision has to look through that lens, but certain decisions, big decisions, and have a certain trajectory with cost and so forth, and it always, I say, what's gonna pass at the ballot box? Not necessarily what's gonna pass here at this table, So that's just my two cents. Yeah, no, I agree with that.

Ultimately, whatever the option we select, we want to make sure that there's a clear process that was followed so that we can explain to the voters why we landed there. You know, as I said before, following the MSBA process gives us that kind of, you know, we can point to that process and say, this is a fixed process. You know, this requires that we look at all of the options. We've done that.

We've satisfied this body of government. They agree that we've looked at all the options. You know, it gives us a strong case that we're not just jumping to conclusions prematurely. In bobblehead with consolidation of three schools, three different sites, multiple enrollments.

I remember at the Preliminary Design Program, the PDP, which is the first deliverable with the MSBA, I think we looked at 20 options, which I think is probably my personal record. I wouldn't necessarily recommend 20 options, but that's just organically how it happened. And then from 20, we narrowed it down. But we want to, turn over every stone.

Sometimes even we may know that that will never have legs, a certain option, but you still have to study it because someone will bring up, why didn't we study that? So you still have to go through the process. Yeah, we're really excited to get to talk to you and understand the basis for some of the options that were laid out in the feasibility study agreement. Interesting idea of a fifth new construction, would it be something you're considering for the board of ecology?

We have lots of questions that we're excited to talk to you about. such as what change between these projects to get it to go from a no vote to a yes vote. So I'm going to hope my team members can comment.

Speaker 11 (01:18:35–01:18:55)

I was not involved in the software tech project and I was not involved in the the two Bridgewater projects at the West and so forth. So while I put those slides together and presented them, full transparency on my projects. So I'm gonna hope someone from my team, our team, can answer that, you know.

Speaker 7 (01:18:56–01:19:09)

Yeah. The key difference here is that left field was the OPM on the successful boats and it was other OPMs on the non-successful ones. But in the extensive relations would change the programmatic view of the project.

Speaker 6 (01:19:11–01:20:09)

So I will say, so I worked on this project and that I think kind of in the case of one of David's projects, it had a lot of options to start with. They studied. many different enrollment configurations across six different options. We wound up having 30 options, not to put a little thunder in my cap there, but we did get down to one.

But really, it did come down to the community, the nine communities that were providing feedback. hearing what was going on in other vocational technical schools in Massachusetts in general. There was a lot about cost and taxpayer, you know, what was meant for the taxpayer themselves, and do that across nine different communities, you know, but also in a simple way.

Speaker 2 (01:20:09–01:30:16)

On the Bridgewater Projects, I can't comment. Maybe no one here at this table can comment. I can't speak to the program of one Bridgewater Project versus the other one. I just don't know if the program will survive or not.

I can tell you from our colleagues who worked on that project, it was all about So that was the differentiator. Yeah, I was very heavily involved with East Bridgewater, especially around the boat. And that's definitely an approach that left field takes on all of our projects, you know, leading, you know, starting in PDP and PSR, the first two, you know, feasibility phases, but certainly ramping up community outreach and schematic design. You know, that's when we start to really understand what costs you know, the total project cost will be, that's when we start to understand what the MSBA's reimbursement will be and how that shakes out to a tax impact.

So really making sure that, you know, the community is aware is, you know, you've heard a very common theme here, but it's worked for us, you know, and it is an effort that I think that left field takes very seriously. into the community outreach. And I know Kevin Sullivan wasn't here today, but working very closely with Kevin on that project as well. He's a big factor in helping with those.

And like Tim mentioned, he did work at the MSBA for 14 years. So he's very familiar with that process and just what he has seen throughout most of his career on projects that failed liaison goal because it is a huge factor. The secret sauce. One data point analysis that I always recommend that projects do is the opposing advocacy group that's going to go against the project, they're going to dissect it.

And they're going to look at costs. And there's a lot of costs that are available in the space. and I always will dissect the cost of projects and say, there's a cost to the project, then there's the cost of what I call the box, the building. So if this is an elementary school here, it shouldn't be that much of a difference of an elementary school somewhere else, with the exception of if it's built on the tip of the cake, that's a different price.

Because every project has different, We'll call it luggage for the project. And I tell clients that I personally think you want to be in the middle. You don't want to be known as the most expensive project now. From a local level, if the town or the committee or the community is saying, don't worry.

That's what we want. It's going to pass. That's OK. We don't know the community like you know the community.

It's always good to have those optics to say we're not the most expensive project in common. We're right in the middle. There's nothing wrong, in my opinion, there's nothing wrong with being in the middle. Yeah, we'll use that benchmarking data early to kind of set expectations, manage expectations going forward and then at some point we fix the budget and we live within it.

what problem-solving approaches did you attempt to implement, and what was the conclusion? What were the lessons learned? We try, as I said, we try to fix, we do fix the budget and schematic design, and that's somehow so much really important to make sure we right-size the program, squeeze the buildings with the gross up as minimal as we can get it, because the biggest place to save money is in the square foot cost of the building. We also look really closely at the site huge drivers.

I think you probably all know that the MSBA has certain caps and SAIT is one that's very easy to hit that cap. The costs go directly to the town. So it's during that milestone before we fix the budget that we make sure there's a little extra effort put on both of those fronts so that we're getting the budget right sized. The other thing we do, we want to make sure we do a schematic design And as we get through the project, all the people come out of the woodwork and we get a lot of asks if we haven't asked them early on.

department, beyond all the educators. Lots of people will have things they're looking for. We want to get that input early. From there, we want to try to just manage that budget.

We stop at every milestone, and we do a cost estimating exercise with a check estimate, the CM's estimate, and we run through a reconciliation process. That process is hugely And then that process gives us a check on that. If the cost estimators aren't getting it, then the bidders are certainly not going to get it, right? You could overpay, you could underpay and deal with it by change order, but we don't want to do either of those things.

So it's very important to get that input. And again, that's the time to do value engineering. We don't want to get to CDs and say, no, we're over budget. Let's reduce finishes.

That's not the place we want to get to. So we work really hard at the beginning to make sure we get the budget right in schematic design. Yeah, in East Bridgewater, they had pretty significant budget restraints. Early in the PPP phase, we were looking at roughly $160 million project.

And just hearing from the community and the leadership there, they're like, no way this is going to pass. It's just way too much tax impact. Excuse me. We were over $1,000.

So we really needed to figure out ways to condense the building without Having any negative impact on the educational program. So really looking at building layout, we made it much, much more condensed. less corners around the building at the end of the day, made it a more simple design. We did end up taking some space out, so there is some compromise that the district will have to look at, and that's the decision of the community.

But we were able to shave out about 30,000 square feet of that building and got it down to $125 million. total project costs. I think I had about 850 average tax impacts, which was really the goal of the town. So yeah, throughout the entire process is really making sure that we're meeting all of the educational needs of the school.

I can add if time permits, if that's acceptable. So I have three things. I always tell clients it's discipline that makes a successful project, the ability to say no, maybe not no all the time, but that's important. And then making certain key decisions early on.

As an example, with the work on Memorial High School project, it's one decision that Unfortunately, we lost with the designer. They wanted to do a four-story atrium, and I said, make it three stories so we don't have to do a smoke-and-vac system. Brendan, well, attested this, or his colleague. So now they have a very complicated smoke-and-vac system where they could have avoided that, and it was extremely expensive and something that they now have for life to manage that.

And then the third thing, you know, VE is important, but we did have two projects, just first-hand experience with the timing of COVID. Two of my projects, Florence Roach and Broughton in Tinsborough Middle School, there were two projects among 30 MSBA projects that went over budget. And we were adamant that we weren't going to change the scope. The scope was appropriate.

In fact, Florence Roach, They had no ineligible square footage. They were exactly in alignment with the MSBA's prescribed template. the only project in my career that was able to do that. And that's not the norm.

But MSBA did come back. We implemented an enormous amount of VE without sacrificing the scope of the delivery of education. The MSBA adjusted their reimbursement formula for 30 projects. And that was the saving grace.

and implement until you're now just copping obstacles. So question number three is, what is your closeout process to close the project quickly and avoid it dragging on? Well, do you want to touch on that? Why don't you go ahead and introduce it.

Sure. Closeout is something that we are big advocates for you because you want to closeout.

Speaker 7 (01:30:16–01:30:17)

We want to closeout, right?

Speaker 2 (01:30:17–01:34:15)

We want to closeout and move on to the next project, so we all have a vested interest in a quick closeout. The MSBA process does protract it a little bit, but that doesn't slow us down with working with the CM to make sure, of course, that we get all of the required closeout materials, right? balancing reports as builds. We want to make that final payment because that final payment to the CM is what triggers the clock to get to the MSBA audit.

It's that audit that then allows the release of the final 5% reimbursement. That usually happens 12 to 18 months after I'll add that it's really strong team participation that's helped us out to work towards the closeout section of the process. So once you get to closeout, you want to have all of the issues that you have encountered and all the hanging punch lists, rolling completion, open items, commissioning log, you want to have all that ironed out. We've got a very strong team, right?

We bring all our MEP experts in. We also work with our site reps very closely. Stay tuned as to what's going on site daily. My team gets out into the field and we're physically looking at all these items.

And I'll tell you that today I was cataloging fire smoke dampers that had been left open by a CM and they've turned a blind eye to them. So we cataloged 50 fire smoke dampers. I've got photos right up. It's a unique condition to fix each one.

That's sort of like a look technically at these things and try and knock these birds down. It's through the process, so when we get to the end, we don't have a big plate with a mess on it. So. If I can add, it's having a reality, a real schedule.

I see a lot of general contractors or CMs say, oh, we can build it in 24 months. Yes, if the planets are in alignment. The design and construction industry is not perfect. Life is not perfect.

So they put these schedules together that it's just, life is not that, we're not that lucky. So I think having a real schedule. We like to implement smooth landing, we like the client to, we like to have FF&E and tech deployment. It's not like a CM or a GC is gonna turn over the building and say, OK, you have two days to deploy the equipment.

We have a graphic that we do where we lay it out in a couple months. So tech and FSD deployment. The administration arrives, they live in the building for a week, they acclimate. Teachers arrive, they unpack.

Along the journey, Josh is there explaining how the move is going to go. It's always explained as it's like moving into a new house and you're just bringing your personal belongings. The TV's all set up, the cable works, the phone, like everything works. You're just putting away your belongings.

And a big thing that we push for, as Brendan said, is we want the commissioning to be done before the client moves in. The punch list should be done before the client moves in. So when the client moves in, it's now you have a live look. And that's where you're fine-tuning.

Because you're never going to deliver a building and when you move in, everything's perfect. No matter how much design, planning, and commissioning happens, there's always fine-tuning. But you want to be fine-tuning. You don't want to move in and we've got to fix this, we've got to fix this, and this never got done, and that never got done.

So that's my secret sauce. Yeah, we work very hard at that.

Speaker 3 (01:34:15–01:34:24)

Any follow-ups? So could you just touch on the locations for what exactly you do?

Speaker 7 (01:34:24–01:35:23)

I'm excited to hear about it. Yeah, sure. So about module seven, or what we call the seventh inning, I'll typically come on board and start learning about what's being relocated, whether there's new furniture, whether we're reusing furniture, we'll do a complete comprehensive inventory. We are very green, so anything that leaves the old site, we typically like to try to find a home for, whether that's within town, as far as anything usable, Whether that's in town, in the school district, or even globally, we work with a lot of charities to try to send items to third world countries and things like that.

But we also, after the comprehensive inventory, we'll conduct workshops with all of the staff members, which clearly designates their responsibilities compared to the responsibilities of the mover. And just making sure that the anxiety that comes with relocating a school, it's kind of on me to try to take that anxiety level down as low as I can and make sure that we have an efficient relocation for all staff members.

Speaker 2 (01:35:23–01:36:39)

Thank you. We know there's scenarios here where it could be a fairly complex move, right? You may have folks moving from a variety of different buildings. Josh has certainly experienced those logistically challenging multifaceted moves.

One item that we do that helps the teachers and administration greatly is we do a white paper for the teachers so they understand. It's almost like when you buy a new technology device, there's the manual and there's the quick start guide. We do a classroom quick start guide. So this is how sometimes the lighting controls in classrooms, in my opinion, are overly complicated.

We try to keep them simple. But even the simple, with just the building code today and the energy code, it's not just the light switching anymore. So we will have a very clear, this is what this button does, this is what this Sometimes you push it, it's not going to go up or down. This is how the projector works.

The administration loves it for the first month because they're not getting the calls. The teacher knows exactly how it works. We do a classroom quick step guide.

Speaker 7 (01:36:40–01:37:02)

It's always my goal to try to deflect as much away from the principals and the administration as possible because they obviously have other things they need to worry about than the relocation of the school. So it's always my goal to try to be of assistance to them. So as I mentioned, I've moved, you know, 45 K through 12 schools. I have 45 principals in my cell phone at this time just because of how close we need to work with each other.

Speaker 2 (01:37:03–01:45:30)

Yeah, we may need a little help forcing them to purge because that's always a challenge. They tend to always make orders. Nice. We've got about 10 minutes left and two questions.

So, question four. During the course of a project, tensions can rise. Relationships among owner, OPM, designer, and general contractor can be strained. How do you work to maintain strong relationships?

Tell us about a project where there were issues among the team and how they worked. Our mantra is always firm and fair. We sort of live that in the good times and the bad times and remain even keeled throughout. We're, as we say, can be the referees that have to sort through the issues.

We're fact finders and help facilitate solutions. by remaining calm, fair, and transparent. I think that's how we get to the best solution, right? We don't build up a defensive reaction from the other parties.

Everybody comes to the table constructively, working towards solutions. So we try to facilitate solutions and, you know, I guess I can relate one recent experience with a GC who had some problematic staff. It was one of those things you want to try to avoid at all costs, but we ultimately had to bring the president of the firm in and have a heart-to-heart that it was time for some change. They had to replace the staff because it was just so problematic.

It's not somewhere we want to be. We try to avoid that. We try to work with them to improve their capabilities. At some point, it just has to be done.

It was effective in that case. They brought in a new team. The project caught up a bit. We're still about a month behind, but ultimately got it done on budget.

90% of these problems come with changes, as you know. Absolutely. Could you discuss your change in our process? taking that, how you review them, how you track them.

Yeah, happy to. We'll review all of your change orders, right? So we're going to maintain our own risk log throughout the project. As issues come up that we foresee, we'll log it on the risk log.

It may not be a real change yet, but we try to anticipate it ahead of time so that as things do come up that are inevitable, we can help you make informed decisions about what may be coming, right? So we're managing against the contingency. As changes do come in, we review them thoroughly alongside the architect, and we confirm, is it a legitimate change? Do we own the scope?

Do we not own the scope? What's causing it? Is it a request? Is it an unforeseen condition?

Is it something the building inspector asked for? And share requests, as we call it. And then we dissect the cost. We look at all the stuff that the design team actually may not look at.

We make sure the labor rates are right. We make sure there's backup to support the material costs. We make sure the markups are consistent with the contract terms and conditions. So we do that real detailed review and make sure everything's priced fairly.

and keep you apprised of this on a regular basis. We'll work with you to figure out the best way to communicate that, but it'll be something that will be sort of a rolling log that we'll discuss with you, review with you, and you'll always be aware of what the risk is when you're making decisions on changes, whether they're effective or not. Yeah, we, as Tim indicated, firm and fair with change rules, and we also make sure that or not job. I won't mention names, they are some subcontractors and they know the business well and they're creative and we have experience to know what to look for.

Sometimes they may be They will say, we need a certain feed, and the only way to buy it is to buy a whole reel. And we'll say, hey, you only need 50 feet. You're the biggest electrician in the commonwealth. You just need 50 feet of it.

We're not going to buy a whole reel. So we've seen the movie. And again, we want to be firm and fair. We like to track the origin of change of risk.

Let me back up. We manage the budget in a manner where we look at where you are with risk and a certain decision-making. Because sometimes clients will say, you know, we want to add this. And I'll say, well, we don't want to add a bit.

We have to control the budget. I've had some clients say, we want to land on fumes. I don't like landing on fumes. There's nothing wrong with landing with a half a tank and say, there you go.

You don't have to nourish the ball with that money. You were approved to, it's appropriate. It doesn't mean you have to spend it all. But we track the origin of change loads.

Sometimes at the end of a project, someone would say, oh my God, we spent a million dollars on change loads. And you look at the log and it's like, respectfully, you asked for half of it. And then the other half, you know, unforeseen conditions, it could be the local governing authority. Respectfully, sometimes, you know, this is minor, but the fire department comes in and says, we want a device here, we want a device there.

I mean, it's minor, but. Things happen. So, you know, your log will actually track our general emissions in order. Oh, yeah.

Yeah, so you'll be able to get a snapshot of that. The other thing we break down, which is important in terms of, you know, managing towards that expected townshare is we, you know, we foresee this is going to be MSB or reimbursable or not. So we can give you that snapshot of what we're projecting the townshare to be. I forgot about that.

Yeah, that's something we have a lot of pride with, how we manage our budget. We always say we manage two budgets. One is the total project budget, as if the MSBA doesn't exist, and the other one is what the district shares. Because the district shares is based on the tax impact.

And we use our crystal ball, and I think we're pretty good at what the MSBA is going to determine as eligible and non-eligible as part of their final audit. Because a lot of times towns, cities, they'll take out a ban, a ban, a ban. And then they're ready to do the final borrowing. And they're like, how much money do we really need to take?

And we'll do that analysis for them. So they're not borrowing one of the banks. but fair mantra and change work and reprocessing, and the last point you made before that about working with the selected GC to sort of replace or address issues with personalities and how to be collaborative. All of your examples that you list in here are all chapter 149A.

Do you find that to be a more collaborative environment? I do, and I have to say probably the team's gonna say we do. Yes, there's pros and cons, and we're happy to walk the committee, if we have the opportunity to do that, there's pros and cons. But as far as to answer your question, is the CMR process more collaborative?

Yes, it is. That's been my experience. Yeah, I mean, as you know, the CM comes on during pre-construction, right, so they have So they take on a little bit of ownership there with the design. Ultimately, once they sign the GMB, they're essentially a GC at that point, but they still have a more robust team approach to the way they manage projects.

Speaker 6 (01:45:30–01:45:51)

I would say, if you're able to, and you've led it a while, it can be helpful to bring them on even during feasibility study, during the flatter half of the schematic design process, so that they can help really nail in It can happen.

Speaker 2 (01:45:51–01:49:04)

We've done it both ways. From my experience, the biggest driver for clients to kind of make that decision is a lot of times the school projects is the largest project the community has ever done. And with the CMR process, you can interview them. You have more control of selecting who you're going to work with.

a higher bid process, you have to pre-qualify. And the way the statute is written is that it's almost like a pass-fail, you have a threshold of a score. So you have a pool of certain general contractors that might have scored high, and some, they just go over the threshold. And then it comes down to whoever's got the low bid.

So sometimes we tell the client, you're about to award the single biggest project the community is ever going to undertake to someone who caught a C. But there was a cost premium to go CMR. So that's part of the pros and cons we'd have to accept. I'm sorry, I'll stop talking.

I just want to get through the last question. Question five is, we're going to just limit this one to like two or three minutes. Community outreach strategy, what expertise does your team have bridging, bringing information between design construction teams and the community as the project evolves? Don't worry.

What we've recently utilized a service of trying to, we're using it on all of our projects in Rhode Island, but it's these short videos where they will take something that could be a half hour presentation where I don't have to speak for a half hour. They condense it to like eight minutes It's amazing because we'll have one presentation that's set up for the finance committee. It's all about tax impact and the numbers. We have some that's set up about the scope, and they call it pillars.

So you'd have a five-minute pillar, and a five-minute pillar, and a five-minute pillar, and then you put them all together. You could have a 20-minute video. So we've engaged this third-party company to do those videos for us. They obviously can't say, vote yes.

Our job is to educate, and the community and the advocacy group, their job is to advocate. But it's been very successful. We used it in Wilmington. If you Google Wilmington, probably can find some of those videos.

And in fact, the company is called Cartooning Education. So that's kind of something that I think is missing. Yeah.

Speaker 6 (01:49:04–01:49:30)

And one other thing, just on the slide with the slide for you. Yeah. Sorry, there's a QR code, and that will take you to the websites that we put together, and that's where we house all of the documentation for the projects, so that you can direct the community to one location where there's facts about the project.

Speaker 7 (01:49:30–01:49:36)

And that is a live QR code for the Pickering Middle School, so you can certainly look at that and see what's available.

Speaker 2 (01:49:37–01:50:26)

I think also just on the community outreach, the MSBA requires you to do three community forums in feasibility and schematic design. I think that's laughably too few. And that's just, you know, we set up an auditorium, then we give a presentation, maybe we get some people who'll come, you know, really kind of depends on the community. We find the most success is when we go to events, you know, that are already scheduled in town, set up a table, be able to share the information with people that are already out in the community.

It's much more engaging. You actually do get to talk to people. So that's the approach that we'll use. And you'll see on the South Shore Tech example, the majority of those are just talent.

Yeah, that's huge in getting to the people who may not be as engaged.

Speaker 7 (01:50:26–01:50:42)

They may not be coming to those scheduled presentations. By hitting as many events as you can, you're trying to hit every demographic within the town. So whether it's a baseball tournament or a farmer's market or a veterans event, try to make sure that we're hitting everyone.

Speaker 2 (01:50:49–01:50:57)

Fantastic. Thank you very much. All right. Thank you.

Thank you all for your time. Thank you. Likewise. I assume you're delivering tonight?

Speaker 3 (01:50:57–01:51:18)

Yeah. Good luck. Thank you, Jeff. Good luck.

Thank you very much. Perfect challenging moments.

Speaker 2 (01:51:50–01:51:57)

Thank you, appreciate your, I'm sure your two hours of these are the last thing you want to be doing.

Speaker 3 (01:52:39–01:52:49)

Hi, I'm Nathan Otto, I'm a member of the school committee and a member of the school building committee. Mark Loring, member of the school committee, member of the school building committee.

Speaker 4 (01:52:49–01:52:53)

Pete Obershamer, member of the select board and also the school building committee.

Speaker 8 (01:52:54–01:52:57)

Terry Hurley, member of the school building committee.

Speaker 2 (01:52:58–01:54:39)

Tim Lombard, school building committee. to consolidate facilities and experience. So well, good evening and thank you very much for having us. We appreciate being shortlisted.

Very excited to be in Milton again. We were involved with this project, as you may know. I'm Tim Bonfatti. I'm the project director for the project.

So my role is to be with you and the town in terms of this process all the way through the feasibility phase. I'm the founder of Compass Project Management, so I started that 17 years ago. I've been 30 years in educational construction as a builder and as a project manager, so it's something I think dearly of. I was on school committee for 13 years in my town in Medfield, so it's something I'm very excited about.

You'll hear from everybody here, and then predominantly because of time constraints. You'll hear from Mark and Chin and I in terms of the presentations.

Speaker 12 (01:54:40–01:55:13)

So my name is Mark Roberts. I'll be the project executive. As Tim said, taking it from feasibility study all the way through construction and project turnover. My background, I'm a civil environmental engineer by training, been in the business similar to him over 30 plus years, spent about a dozen years at DCAM and that's my last 15 or so years, close to 20 years at Harvard University managing capital projects.

I too have been involved in my town politics. I was on the municipal building committee and I also spent close to 15 years on the conservation committee.

Speaker 11 (01:55:14–01:55:39)

Chin Lin, and I'm a registrar architect. Prior to joining Vertex seven years ago, I had over 20 years of designing and constructing public schools in Massachusetts. And since joining Vertex, I have done multiple projects, multiple MSBA projects with enrollment or consolidation issues.

Speaker 6 (01:55:40–01:55:58)

I'm Meredith Gordon, I'll be the assistant project manager, focusing on the transition, as well as the, which includes the furniture, equipment, technology, and management process. I've been with Vertex for seven years, since a high school internship, and then internships through college, going full time, and then getting my master's degree.

Speaker 13 (01:56:00–01:56:16)

I'm Suzanne Sorrels, I'm a mechanical engineer, and I also have my construction supervisor's license. I will be the onsite construction site manager, I'll be there every day representing the Tom Milton and being your eyes and ears on the site.

Speaker 2 (01:56:18–01:59:15)

So a little bit, we're not going to spend a lot on us, it's mostly in our proposal, but Um, I wanted to focus on a couple of things in the next slide. Oh, I do want to introduce some, sorry. Apologize. Bill has joined us as the, he's our, uh, interval data systems as our automations and energy efficiency.

And we have a piece on that in our presentation. So Bill's here to answer some questions on that. If it comes up during the Q and a. key parts of our division.

As mentioned, so we are a leader, obviously, in the K-12 market. We've done a lot of schools. But the thing that I think we specialize in is the sort of complex district-wide enrollment reconfigurations and consolidation like Milton's dealing with this, whether it's over-enrollment or under-enrollment or how the impacts of that. And that's a little different than a lot of other sort of easy, simple build and replace kind of projects.

The other thing I want to mention is we really value being a trusted partner with our clients. I work with them pretty consistently throughout the whole process, both in terms of working with the MSBA, but also interacting with the town and kind of translating that process to the town. political, you know, to the boards and also to the public, frankly. And as I mentioned, we're very proud to have been part of the, we understand Milton through all the members of our team and have been very happy to have been part of that process of the fire station rebuilds.

We have a very, I think, simple but kind of not so easy to execute management approach to what we call our formula for delivering successful projects, team, plan, execute. So we really focus on creating a qualified team right through to the subcontractors and the sub consultants that are involved in that. We try to make sure that team is aligned and has the purpose and shared value and purpose that is key to a successful project. We obviously create in the feasibility phase, it's very important is to have a plan, a budget, a schedule, a scope that works for the town, but also communication and engagement.

a risk management plan and a QA, QC plan. So that's something that is critical to set up. And then day in, day out, executing, fostering in the team a project ego, making sure people are thinking. It's a great way to make judgment because if it's in the project's best interest, that's generally where we come down.

And accountability, making sure that everybody is accountable, including us, to you and to the rest of the town in terms of our work product. So then the rest of our presentation is completely about the Cunningham Elementary School project, and I'll turn it over to Jay.

Speaker 11 (01:59:15–02:01:47)

And this project, in a very, very simplicit term, is just that this is a, you have a population growth, and so you need seats. And the question is where, and in the, what we have done in many projects is where this is coming up, So on the left-hand side of the chart, there are three options in the enrollment letter. And on the right-hand side, each column represent one of your schools. And what this is representing is that what would happen to each of the schools should you choose one of the options.

The green is always the project, and then the orange is the area where changes will be needed, whether it's a configuration of grades, or the redistricting, or modification that you might have to do, and then should you go to, and then the rest of it is what is not changed, is also clearly shown in the color. And this is the kind of things that we present to the client, and in this case, Westwood, where the solution is in the elementary school, all five elementary schools are listed, and then how they're impacted, and then what kind of redistricting effort or not, also spelled out. And then that allowed the town to look at it in totality, so that you understand what are the issues and potential impact. And in Norwood, where the problem is really in the elementary school.

They are missing the number of classrooms in every single one of their five elementary schools. And then what we did here is show if you were to go about adding modular building in each one of the schools to meet the need, and compared to if we were to move the fifth grade into a middle school project that is already in the process, how does that comparison compare and then what kind of impact, in this case financially and obviously in this case, that you don't need to do construction in most of the buildings. So that's what we bring to the table.

Speaker 12 (02:01:50–02:06:08)

So while enrollment is the primary focus to help the town solve their issues relative to the influx of students, it has to be done sustainably as well as cost effectively. So today's systems are more complex than ever. between fire dampers and VRFs, et cetera, it's just a very complicated system. So, the way that people manage those, I'm sure some people may know, is through a building management system, which are basic data points through each system.

So, they operate synergistically amongst themselves. I think we've all seen this, especially on this side of the table, is that buildings have not, when they've been turned over, they don't normally operate when they're supposed to. People are too cold when they need to be warm, too warm when they need to be cold. So what we take pride in is developing a QAQC program to manage all that.

Starts with the contractor, have to make sure that, you know, with Suzanne's help, making sure that we pay attention during the installation, as well as start up, and that everything's ready for testing, that the contractor does their pre-functional tests, and we review that. Then partnering with the building commissioning, building commissioner, building commissioning agent, to optimize the performance of the building itself. Next is the third, oh, sorry. Sorry.

The third-party BMS review, which is where our partner Bill comes in from the IDS aspect, which I'll get to on the next couple of slides. And lastly, as I said, the systems are so complex, more than ever been before. The key to this is making sure we provide the proper owner training through videos and multiple training sessions to make sure those that operate the building understand what they're getting into and know how to operate on a daily basis. Lastly, I have here is, due to all these efficiencies, there are several mass-save rebates and IRA tax credits that we get back, potentially hundreds of thousands of dollars from mass-save program.

And we ourselves, to our credit, have incurred over $10 million in the past two years for IRA tax credits back to the towns. So on this slide is one of the reasons we've been partnering with Bill. The line on the top is a building where we didn't get our IDS involved until after the building was already done. So as you can see, the EUI at the time was 45, with the goal being 25.

Through Bill's team, we were able to evaluate that system, identify pinpoints where we need to improve the services. So over the course of time, we were able to get it down to 25 EUI. The bottom line in green is where we got IDS involved early in the design, making sure that we partnered with all the various engineers that are involved in the project to start out at 25, so you don't have the issue through the operation turnover. As you can see on this example, you saved about $190,000.

It should be pointed out that these two schools, Ashland and Westwood, are similar to what square footage that we would anticipate for the town of Nome. All right, just trying to keep the construction costs low. Vertex has three of the lowest dollars per square foot costs in the state. As you can see from this slide, the three on the far left within the last 18 months have fallen below the line of the least expensive schools.

We work with the architects here in the town to maximize the square footage that we need for the town by being economically feasible to make sure it is. what the town needs. Maximizing MSP reimbursement. So there's a formula that the MSBA uses for dollars per square foot and there's certain excluded costs like turf fields, et cetera.

So we work with the town during the design to make sure that we can narrow that gap. So as you can see here, there's the last 10 schools through the MSBA process. The average spread was about 17.3%. Vertex's last projects were averaged 18.81%, a difference of 6.5%, additional reimbursement.

As you can see here, an example of Vertex project in the town of Millis, we had that gap, narrowed that gap to 4.4%, 4.48%.

Speaker 2 (02:06:08–02:08:29)

So what does this look like for the Cunningham Elementary School project? We took the three scenarios and using some of the MSBA space guidelines, which is how they judge the size of a school for different enrollments. We kind of game planned what potential schools would look like in those three scenarios. As you can see, I won't walk through all of it, but we tried to, looking at the costs that we've been seeing and what we think we can project, we came up with a total construction cost and a total project cost, assuming a 22% soft cost multiplier, that essentially when you apply that 6.5% that we've been very focused on doing internally for towns, narrowing that gap, amounts to significant savings.

And then time when you're going in front of the town for operational overrides and for other reasons, it's very important that we can have a good message around that savings. So that's an example of how that might work. This timeline is on one of the pages of the placemat. It's supported by the schedule that's behind it.

I'm not going to walk through it. I just want to point out, because what we've done with this is sort of mapped out how we would envision the communications with the community. Obviously, there are a lot of in-person communication and forums. Believe it or not, we think that still is a very important and critical way to get the message out to have people have the opportunity to come in and talk to you.

But we also started doing in the last few projects, we've worked with a videographer who puts together very informative video at each step of the way. So for those people that kind of enter the project late, most people and when they're asked to actually vote, they can go back and see pretty clearly in three minute videos, the project at each stage and how you came up with the decisions you came up with. And we find that very important. Obviously, this is supported by, you know, a social media campaign and other ways that Milton communicates as a community.

But we have found that that sort of integrated approach has been very successful for getting the message out. We have had, in our 17 years since Compass started, we have been, we have had one project, the town of Denham, that didn't pass its override out of 22 projects. That's it, thank you.

Speaker 9 (02:08:30–02:08:35)

I hope I, did I get it within 30 seconds?

Speaker 3 (02:08:37–02:08:41)

We said pretty much what we wanted.

Speaker 2 (02:09:07–02:11:22)

What do you view as your role in helping facilitate town officials' decisions on a timely basis? So we, I will tell you, we believe our critical, the primary role we have is making sure that the communication we use that you agree with is clear and concise and doesn't confuse people. I think especially where you're dealing with a project that is kind of a gateway to a district-wide implications, it's very important to deal with the anxiety people might have about that. Anything that doesn't replace a school in kind on the exact property is change and change is just for towns and for townspeople needs to be explained.

So I think our primary role is really communication. and working with you on what's the best way to communicate things in a clear way. I think secondarily, but we believe that if you deliver a good process, if the process is transparent, if the process is thorough, it sells itself to some extent. People don't pick up the process to get to some other reason for not supporting the project.

So we would want to work with you to make sure that the process is as transparent as possible to people so they see that you're doing it the right way. And then we have a bunch of graphics, which we can show you actually in our bullpen, that sort of show how we get through that process. If you look at this, this is an example, if you go back a little bit. you know, we sort of use this funnel as kind of a graphic idea of bringing things down and narrowing them into final, you know, final options that are preferred and then coming up with the solution that is most fiscally responsible and educationally appropriate.

And then we do use these kind of color-coded, we find that this one is fairly simplistic, but we use them depending on, we create those in conjunction with your take on what is the most important aspects. But again, in some ways it gives an ability to say, we evaluated everything and this is why we picked this option.

Speaker 12 (02:11:24–02:11:39)

Just to add on to that, another part of it is understanding the governance and decision-making, and making sure the right people are at the table, we got everyone involved, so that we're all messing together as a team, and just understand the approval process, and how we can work together to achieve the goal.

Speaker 3 (02:11:42–02:11:46)

Just because I didn't see much in your initial presentation.

Speaker 5 (02:11:46–02:11:59)

Can you talk about like your just initial professional thoughts as to kind of our three different sites that, you know, I think within the scope of the OPM proposal, they're kind of asking you all to look at and like what your just initial take or approach would be.

Speaker 2 (02:11:59–02:13:17)

I mean, I think that the, well, obviously we're pre-joining, but since you've asked me. The middle school has, to me, the clearest way of dealing with the broader issue around enrollment, and it does it in a way that doesn't create the change problem. It creates one change that I think is something to be considered of but can be handled, but it doesn't create issues where people are not used to, say, a 1,400-person elementary school, which creates some aspects of concern. and it's kind of nifty, it's kind of near the high school, it kind of works if that can work in a way that it's a natural graduation.

The one thing that we found, because NOAA did essentially the same thing, although they did it in one middle school, is to make sure to manage that idea of you know, those kids that are now in essentially a junior high are getting themselves transitioned into high school, but you're not dealing with having to worry about the fifth and sixth graders being so that I think is a big health event.

Speaker 11 (02:13:18–02:15:32)

on the normal process that we actually set up four meetings with the school committee and then address different topics. One is the way we are right now, and then education and what that would be, that's working with the district superintendent and the principal of the school. on how that change of adding the fifth grade would be. And then the third one was social emotional.

How would that be dynamic and behavior change? And then the last one was as a stair to just simply to have a chance to really revisit everything. And in Norway, in that situation, there was a five person school committee. And when we got the job, there was only two yes vote.

When they went to vote for the enrollment, it was unanimous, and they did not even have any doubt on that. So we were very successful to address the issue. And your elementary, the Cunningham site, that's probably going to be the most difficult construction because of the fact that you've already got a lot of kids there, it's a very tight site, most likely it's going to be a face construction that asks time and complexity and interruption to its speed. And so that's the initial feeling.

Tim and myself were the team that did the part until we get the votes through. Suzanne was the site manager, and Meredith was the person. You should tell them the story.

Speaker 6 (02:15:33–02:15:44)

We did the move from the five elementary schools, fifth grade classes, into the new building, as well as the old middle school into the new building. But I did the transition process for journals and stuff.

Speaker 13 (02:15:44–02:16:33)

Now, I know there's a lot of concern. I mean, I'm a parent as well. So a fifth grader wouldn't be a third grader. But what Norwood did is they had a grade per floor.

So the fifth grade is on the first floor, and the eighth grade is on the fourth floor. And so the fifth and sixth graders had their own cafeteria, and that's where they ate. And the seventh and eighth graders had a different cafeteria up on the third floor. So there wasn't a tremendous amount of overlay and mixing of the kids.

There was some, because there was one gym, there was one auditorium, that kind of thing. but I think it, like Chin said, when it came to the vote, they all were in favor of it, and I think people's worries were answered, and they had a lot of questions and things like that.

Speaker 11 (02:16:33–02:17:07)

So those details were in the very, very early stage that was already embedded in the presentation to the school committee, building up to the vote to make sure that, to basically say, if we vote down this road, These are the precautions that we will take, and we will make sure that we address them before they become a problem. So we do that, and we work with the committee. Obviously, each committee, each community have slightly different concerns.

Speaker 2 (02:17:07–02:17:42)

And I think Jim mentioned, on that project, we worked with school committee quite a bit, We came up with the idea of let's have like a theme for a month, deal with the social, emotional, deal with the facility impacts, deal with kind of in a way that could package nicely for the school committee, you know, where it gets a little more attention than maybe what the building committee is doing. That was something that, you know, that necessitated that kind of more engagement with the school committee than a typical project.

Speaker 11 (02:17:42–02:18:20)

changes potentially, you're going to have to also involve with the school committee quite a bit too, because school committee, they're the one who has to vote on the enrollment, because that's an educational decision. So school committee, that's dictated by MSBA regulation, but that's very intentional because you're the one who knows how to educate the kids. And then also that if we can provide a good solution that you understand, then you can also go tell your constituent that, hey, this is the right solution for the town.

Speaker 3 (02:18:21–02:18:24)

So we'll move on to the second question.

Speaker 2 (02:18:24–02:19:16)

So the second question is, can you provide an example of what an MSBA project you were working on was running over budget? What problem-solving approaches did you attempt to implement? And what was the conclusion? Also, what were the lessons learned?

I'm going to actually let Chin answer this, because Chin and I also worked on Westwood. And Westwood appropriated its money in 2021, I think, maybe, or something. Well, the inflation that happened, the 10% inflation, unheard of, happened after that. And we were in the middle of design.

And the town obviously didn't want to go back for more money. they did go back for a little bit more money, but we work really, and that was a design-bid-bill project, we didn't have the construction manager with us, so we worked, and Jim, maybe why don't you explain, because you did all the work.

Speaker 11 (02:19:16–02:20:33)

So what happened was that the construction budget came in and was $4 million over. We planned out a number of scenarios on how we can move forward, and at the time that they have $2 million in cash in reserve fund, in the school committee from the settlement. And that was immediately put in, and with that $2 million, that was enough money to get us, and then we knew money out of the contingency, and so we reduced the contingency at that time. And subsequently, we were able to get $2 million of ARPA funding to supplement the money.

So therefore, we covered the $4 million. Afterwards, we were able to get $5.5 million of IRA money and MSBA increased their funding. So original vote was $69.5 million debt service, final debt service to the community. The final number is $60.2 million.

The taxpayers saved nine plus million dollars on it.

Speaker 2 (02:20:34–02:21:20)

And I think chin underestimates the work he did to make sure that because we were going to cost estimators. So we, we, he would work with the architect to set up. value engineering options that were acceptable. The earlier you get to value management, this happened around design development about 50% in, he was able to set that up ahead of time.

So we didn't lose time going back and revisiting things that the town had decided they were all sort of prepped, that we're looking at these three or four options with each iteration to make sure that these are acceptable to you before we start pricing them and go out public with them. So that was something that I think Jim did a really tremendous job working with just the architect of the process.

Speaker 4 (02:21:20–02:21:46)

Sorry, can I sneak one in? You talked about that project as an example where it wasn't the CM. 149, what's your, I mean, do you have a preference between the options? Or does it kind of depend?

Speaker 11 (02:21:46–02:23:00)

Personally, so the pluses and minuses are like, CM obviously, you know, what the CM, the advantages that you have upon, but usually that comes with a price. Design-built, you always get a better price. But that doesn't mean, and then the, Conventional wisdom is that you have a lot of trouble with this. You're fighting this contract day in and day out.

The reality is that if you have a good team with good sense of document and that you're willing to defend your document, it's not a problem. And I would encourage any one of you to call John Cummings, who sat through the whole process. That project, we were ahead of the problem, so we never had any real problem, but that also means that we have geothermal wells, and we make sure that we build in the specification, how to manage the wastewater, so that when the problem comes up, we already know how they're supposed to treat it, so it's not a problem, so you anticipate.

Speaker 2 (02:23:00–02:25:22)

You know, we did this timeline for another reason, and that's to show you the options you can have. So I was involved quite a bit in 2004 with the CM risk legislation. I've been working on it for like five years prior to that to get it drafted and consensus around it, and then also to get it passed through the legislature. very much a probe having the option to see them at risk.

But I do believe that it's morphed now where people are using it as a default option and they are paying a premium. I mean, there's no question the premium, you know, if you talk to any estimator, it's five to 10%. This timeline is set up so that some of the reason that moves people to see them at risk Depends on the size of the project. It obviously depends on whether it's an ad reno and phased occupied renovation, which you want that kind of pre-construction interaction.

But a lot of it is because the schedule has been pushed so much that in order to make a fall opening, you need to get early trade packages. You need to get design, you need to get construction started before the design's completed, which the only CM at risk allows you to do that. Otherwise, you know, design bid, build, you need to finish the design 100% and bid it. This schedule is set up that if by 2028, in the spring of 2028, if there is an approval of the project and moves forward, you would be able to bid this project in the summer or late summer of 2029 and be able to be ready for that fall opening without having to do early trade packages.

So that's why, that's kind of what this schedule intended to do is to give you the option to be able to have both of them at your fingertips. If you go with the new build option. If it's an ad reno, it can be a very different project. But if you go with the new build option, you should have the option because I'm not seeing right now the benefit to the town.

I know the benefit to us and I know the benefit to architects to have a CM. I'm not seeing the benefit to the town sometimes. for a clean bill, a clean site.

Speaker 12 (02:25:22–02:25:45)

Both options require complete documents, right? I think collectively as us as a team, we have a lot of years of experience, and not just knowing the project, knowing the systems, but incorporating lessons learned, questioning the architect, make sure that everything's included, so anticipating what a contract is going to add as a potential change, whether it be ceiling or historic design.

Speaker 2 (02:25:45–02:27:19)

Having done the schools before, when I was doing schools, seeing the risk was a very new thing. And obviously, as you know, they filed some bids was an issue. I mean, it was just, you were stuck with the whole bid. Have you seen this, have you seen it improve the quality of the contract that you're getting through the bid process as opposed to seeing the risk?

So now you can pre-qualify, which we couldn't do until 2004. So there was a whole level of, and we very rigorously, as part of the team plan execute, we very rigorously keep the prerogative to make sure we qualify all bad people. If one member of our team, meaning the architect or us, have had bad experience of the town, then we really look at whether or not we can find a way to get rid of that slot. Then you get supported at the Inspector General, the Attorney General's office with that.

So I definitely would say right now we see much better filed subs. I think where the problem can be, because we don't have that same pre-qualification process, is the non-filed subs, and they make up a significant, and they make up the early trades, the site work and concrete, people that can get momentum going on a project. So that's why we really spend, a strong effort in design and build with the general contractor pre-qualification to make sure that when we get a general contractor, they are qualified and have a record of buying good subs, the good early trade subs.

Speaker 11 (02:27:19–02:28:24)

It's very important. Part of this is also, I cannot emphasize enough how important it is to have a good architectural team to produce a good set of bid documents. That's a legal document, okay? And then what we, at least I personally do, is helping them is that whenever I spot a problem, even in the schematic design phase, it's a slip, a note that say, hey, can you check against the code on this particular issue?

So that they have an extra, so what I ended up doing is that I ended up having an extra check in terms of whether it's building code or constructability or whatever else. And because I've done that before, I know that. And so that allows us to have a better set of documents. And then that makes Susan's job a hell of a lot easier, because she can point to, that's in the contract, you own this, and end the construction.

Speaker 2 (02:28:26–02:28:52)

So we have three questions left, about 10 minutes. Sorry. No, you'll find it. So question three is, what did you close out of the process to close the project quickly and avoid it dragging out?

Dragging out. Well, Meredith, why don't you talk about what you do, because a lot of the transition that we start a year before it's ready to transition, I think sets it up to close out properly.

Speaker 6 (02:28:53–02:29:25)

I use a survey that I give to the schools, the teachers, and anyone who's really using that space to kind of see what, anything that they think is wrong, furniture, construction, we start taking that information, putting it into what we use with IDS too, so we kind of get a big picture view of what is happening with the project. at the end once the contractor is out, and then we start going into our full closeout based on that survey and the information that the school gave us.

Speaker 11 (02:29:27–02:30:00)

Somebody else can tell me more on the closeout. And then also the other thing is, and Susan doesn't say it, but I know that you guys do it, is that the rigorous process of QAQC reduces that punch list. And that shorter punch list equal easier closeout at the end. And then having ideas on board, what that gives me is another, they will look into all the HVAC issues.

And I can tell you that I don't get calls on HVAC issues unless

Speaker 2 (02:30:01–02:30:19)

In fact, close-ups drag on because people are not happy. And I think what working with Bill's team has done is make people happy. They like being in the school. They're comfortable in the environment.

And I think that helps let us move much more quickly through that process.

Speaker 3 (02:30:21–02:30:22)

Questions, follow-up?

Speaker 2 (02:30:27–02:33:42)

All right, question four. young designer, general contractor can be strained. How do you work to maintain strong working relationships? Tell us about a project that were issues among the team.

How do you respond? Well, I'll give you an example. This was 10, 12 years ago. We did the Norfolk County Agricultural High School, which was 20 years ago.

building pieces and renovations. And that contractor was a bad contractor. That was one that should have, that's one that's no longer in business. We actually did not want to pre-qualify them, but the county did for a number of reasons.

And so then he ended up on the bid list, got the job. That was a very difficult project. They went out of business in the middle of it. We had to work with the surety to get the surety to finish it.

We started that process very early on because I spent nearly part of my career working as a surety attorney for the insurance company. So I know how you need to engage surety quickly, and we were able to work through and get a replacement contractor and finish the job. I think it was about six months beyond its original 30-month deadline, but considering where it was heading, that was pretty good. The challenge personality, so the CFO of the school would get livid sitting in these meetings, of course, with this contractor, because he's like the guest that never would leave, and he was a horrible person you have in your home.

And he would turn red and I would have to pull him aside and say, look, I know how hard this is, Rick, but if we don't, if we don't stay, keep our patience and stay through this, we're going to jeopardize, you know, where we want, what we really want. And I think the key to working, so, and even on projects that aren't that bad, you know, there's always going to be moments where we have issues. We have a very, very strong relationship with all our colleagues. We treat them all very well in terms of fairness, and they know where we're coming from.

We don't put them and make scapegoat them. We're in this together. We frankly know that if you're not happy with the project, you're not going to be looking and saying, well, it was the contractor or the architect. You're going to say everybody was bad.

So our goal is to make sure that everybody is is succeeding. So I have pretty strong principal relationships with most of these firms. So I'll speak with them and basically walk through where the problem is. And there have been some where we've had to replace people that have just clashed on the project because they're not, they don't, they're oil and water.

But I think mostly our goal is to not have that turn into something bigger. One of the sayings, little sayings we have, a lot of them, is sometimes it's the reaction, not the action that's caused. that's caused the problem. And so kind of stepping back and not letting that happen is important.

Speaker 13 (02:33:42–02:34:42)

And I think I'll just speak for a minute. Being on the site on a daily basis, I get to know everybody that's there. I'm very apparent. Everybody knows who I am.

And I look at it, I think construction has evolved over the 40 years that I've been around. And now people tend to talk with each other, communicate, and really try to work things out. Much more than they used to throw the vases and things like that back when I started. But I always tell the guys on the site when I go on to a new site, tell the GC office, listen, we're all swimming down the river together and I'm just going to help you swim down the river a little faster.

I'm not here to ruin their life and they're not going to ruin my life either. We all want the project to be done on time, on budget. and we want it to be done well. So that's what we all want.

So let's work together to make it happen.

Speaker 12 (02:34:42–02:35:10)

Exactly, making sure everyone's at the table, because it's so easy if it's just the owner and the architect, the same with the contractor. And then the other contractor, they blame the architect. I always make sure everyone, all decision makers are in the room. But like Tim said, you've got to make sure everyone has the personality to want to work together and get the things done.

Because negative attitudes don't fly. It's no such thing as everyone wants to hear good news, no one wants to hear bad news, but you want to be able to proactively deal with them in the bed. It's interesting.

Speaker 2 (02:35:31–02:37:41)

Well, I sort of started some of that. I think that, and I will say every community is different. Some communities don't have strong or even any local media. Some communities have local media that still is pretty robust and people respect.

So some communities are very big on Facebook sort of chat, you know, groups and things like that. One thing I think in terms of the biggest thing that I think every community is, is that the townspeople don't pay attention until it's getting close to make the decision. So it shouldn't surprise you that you'll have done all of this in open and you'll have done all your best to get all these forums. And then people will start to say, well, I never knew this was happening and I didn't understand this was going to be the situation.

you know, this is two months before the vote or something and you've spent a year. The biggest decision and the biggest outreach part of that process is the blue line where the preferred schematic report is issued because that's when you actually decide on the project you're going to go to the public with. And you don't go to the public for that vote for another six or eight months or whatever. So that decision is the one that I think the focus needs to be made on.

getting the message out, getting it out as much as possible, getting people an opportunity to comment on it while you're still making that decision. And we actually now have been using, I know it's old fashioned, I probably shouldn't say this at my age, but we use banners around town to tell people about an upcoming community forum because people are not reading the superintendent's message that goes out and tells them that there's a community forum. They're not reading wherever they're getting their news from. So we've gone to really just sort of putting up banners at various points in town that tell people there's a community forum and we want you to come and listen and ask us questions.

Speaker 11 (02:37:47–02:39:13)

We also established, currently I'm working on a project where also they have multiple enrollment options. Very early on we established how many public meetings that we have to have to get to the PSR. We set the date and then we actually send a mailer out to everybody in town. So what that does is that nobody can say to you that you have a total in every single meeting and every possibility to say upcoming whatever.

And then we started by, even before we have anything, the moment the architect was hired, we want to come and hear what you have concern about this project. It's not like, oh, here's our solution. No, we come to them to say, what are the things that you see as important issue to solve in this project? And then so that way, at a minimum, as elected official, you can say that we make every effort.

If somebody says that you never told me, that you can back it up with all the action you have taken, all the public meetings. Right now we have a list of about 50 public meetings that will be part of the process. And that's up there on the website in the presentation with the people.

Speaker 4 (02:39:17–02:39:31)

questions or follow-up? One or two. Who from the team is involved in sort of the community engagement strategy, or is it the whole team?

Speaker 2 (02:39:33–02:39:43)

It's very much the three of us during the feasibility phase, because we're most actively involved in the development. You want people that are going to be involved in that to know what's happening.

Speaker 12 (02:39:44–02:39:58)

And it's crafting the message, working with school building community and other stakeholders on what kind of information do you think we need to do and how should we present it? So we have our ideas. We want to make sure we come up with a collaborative approach to get the message out.

Speaker 2 (02:39:59–02:41:45)

So the strategic stuff in terms of, I think, is we would meet and talk with you about how do you see, what have you found to be the best way to get the message out in certain aspects of the project? going in front of school committees sometimes can be more, especially as we mentioned with these kinds of district-wide impacts can be important. And then I think one of the things that, you know, we also don't think the message ends at the vote. You know, like the message, it's important for us to leave a project in a way that you're proud of it.

like the town people are proud of it. And that's where Suzanne and Meredith, and particularly Suzanne because she's there day in and day out, crafts the message that goes out about, here's what's happening on the project this week. And here's how we want to engage the great learning opportunities of these projects. And it's something that we try to continue throughout the course of it.

Every project we have, Mark and I are working on the North Attleboro High School right now, which by the way is a very good website if you want to take a look at how they've structured and you can see those videos that I mentioned. We put out, there's a weekly construction update. We're just starting work, so it's in the very beginning, literally the last two weeks, but you'll see the work going scheduled for this week. What are the major impacts that are occurring in the neighborhood that you might, if there's like a, for instance, if there was a concrete pour and they were going to be going into late into the night.

We want people to know that in the neighborhoods. And so that communication starts in the very beginning of the project, but it doesn't end just because the project has been successful at the ballot. We want that to continue right through to the end.

Speaker 13 (02:41:45–02:43:20)

Yeah, I'm on Sitchwood Elementary School right now, and it's in a neighborhood. Literally half the kids walk to school like the parents walk. It's very adorable. But anyway, so we had a neighborhood like tour when we first started the foundations and whatnot and invited people to come, you know, four or five o'clock and just sort of got to see the footprint of the new school and got to meet me and get to see and just we answered a lot of their questions like are we taking trees down, are we going to replant things or you know, you're going to be working on weekends, what the noise is, and you know, all those kind of questions.

So we try to have community involvement as far as I always feel like if people know what's going on, then they're not as, don't get as mad or it's, you know, whatever. They're like, oh yeah, they said they were going to do this talking board and they're doing it. It's like, yeah, you said we were, now we are. So, and like that, I go out in front of the school every day, because our gate is close to the school entrance, and when the kids are coming to school, just to make sure that, you know, the trucks aren't allowed in anyway, they know that.

But I just stay out there in case somebody shows up, and someone usually does, and I'm like, go away. Go away, you're not going in right now, there's too many little people around. Some of the parents have gotten an emoji from what fits the school.

Speaker 6 (02:43:20–02:43:32)

You also go into classrooms to talk to the kids sometimes, especially what we're doing right behind them with the loud noise and hearing glasses. Yeah.

Speaker 12 (02:43:32–02:43:51)

Yeah, in North Alboro they actually had like a career day in the middle school and us together with the architect and the contractor gave presentations to the kids in the school so they really understood it. Granted there were some other areas that were a little bit more interesting, but certain kids paid attention to it and they liked to see what the school was going to look like and how it gets done. Yeah.

Speaker 13 (02:43:52–02:44:13)

We did it in Norwood too. We went in there once in the fall and once in the spring. and talked about all our different roles. We had like a carpenter come with us and just trying to expose the kids to different job possibilities and tell them what was going on and everything.

So, we're totally game for any of that. Whatever folks vote.

Speaker 3 (02:44:23–02:44:43)

Thank you very much.

Speaker 2 (02:44:43–02:45:16)

Would you like us to hand out a copy of that presentation? Oh, my goodness gracious.

Speaker 9 (02:45:17–02:45:24)

Sure. Call Rhesus.

Speaker 2 (02:45:56–02:48:40)

the pros and cons of each that they heard. So I'll just start with you. Yeah, you want me to talk about all three of them all at once? Yeah, I mean, just high levels.

I mean, you know how you scored all three of them, right? Yeah. So based on your work, so what would you do? All right, well, I'll try not to be totally comprehensive.

I'll just give a couple of thoughts. I thought, so just in terms of, you know, my view of like experience and experience, I thought just on paper, PMA brought a significant amount of experience doing this kind of projects. And in their answers to our questions, I felt that that implementation experience showed, specificity of their answers, direct examples. I felt like I learned the most from their presentation about how this project worked.

I thought that kind of tapered off over the presentations. I think they're in Vertex. I was just a little worried about, they have a lot of municipal projects, obviously here in Milton. They're probably the leanest on school building projects out of the three that we saw.

And, you know, that makes me a little nervous. Now we'll stop there, just give space for folks to talk. Sure. I agree.

I think PMA answered a lot of the questions. They seemed real confident. Sean Burke, the guy in charge, he was well-answered, confident. I liked all their responses.

I thought Left Fields was great with the community and how they get the message out. And they did seem really, really school-oriented, all about the schools. Vertec, I liked them, too. I agree that they have a lot of projects going.

So I would have leaned to SPN.

Speaker 3 (02:48:45–02:48:50)

Yeah, I thought Vertex and PMA were pretty good.

Speaker 2 (02:48:50–02:50:07)

I thought they were head and shoulders above left field just from their presentation, their polish, how confident I felt about the team. experience, just not the company name as a whole, but the individuals who are going to drive the project or what really matter and how comfortable do they make doing this? How much do they seem like they have an understanding of the project? Obviously, they feel really good about PMA's understanding of the project based on how much time they've already put in.

I think they also talked about three different options. One thing I was trying to put Vertex on was to see if they'd even thought about Laboree. I know that's kind of a later addition. didn't mention it at all, so that was a question.

But overall, I thought Vertex's team, especially their senior project manager, the people who are going to be on site the most, made me feel really good about their level of competence and other similar complex projects. So I think either would be a really good option, just because of the teams, but I'd probably give the edge to PMA. I'd say it's much closer than I was expecting, because again, I think he may have just had so much positive experience and like running room on kind of understanding the project. I thought really highly of Brutex's presentation and take on it.

Speaker 4 (02:50:12–02:52:26)

Peter? You know, very similar. With respect to PMA, I was really impressed with their materials coming into the presentations. I, you know, including some of their team and their educational liaison that they advertised, I thought they spoke well.

And this isn't necessarily my world, but spoke well about their sort of their databases. And, you know, I guess I thought they were strong on community engagement, and you can sort of feel that from their presentation, like their personalities and view on trying to attract residents to come out during the process. but they were. So they were, it might have been, it was awfully close for me between they and Vertex, even though I appreciated, really appreciate all three strong presentations.

With respect to Vertex, I thought their materials had a really sort of a personal feel to it, tailored to Milton. You know, I appreciate their town, their fire station experience. I also was impressed by their MSBA track record of 21 out of 22 pass rate. And the Norwood Upper Middle project that they worked on seemed pretty on par, although I haven't dug into that deeply, but just how they described it.

This is a little bit on the softer skills side, but I thought, their team treated each other really respectfully during the presentation, it jumped out at me. So, you know, it's really close for me between those, might have been a point difference in scoring, but really strong.

Speaker 2 (02:52:29–02:53:54)

Let's see. So I tried to look at, I kind of broke it down to individual How good are they at managing the design? How good are they at managing the construction? I kind of looked at the individuals for that and how good they might be in those work streams.

And then I kind of looked at the team overall, how they would work together. And then I just kind of looked at their overall experience and tried to pull that out of the interviews. I gave PMA the highest score. I had them rank the highest from the pre-qual coming in.

They pretty much maintained that level. There's a high level of comfortability with them based on our previous experience with them. We know exactly what we're getting. and what to expect and our experiences up to now have been really good.

So I ranked them the highest for those reasons. I had the other two coming into tonight basically dead even with each other but based on the interviews I felt much better with Vertex. People have expressed reasons why, just the way the team interacted with each other, their experiences, they just gave a good feeling that they would be good to work with.

Speaker 14 (02:53:55–02:54:05)

I definitely came away with Vertex as the leader, which I didn't expect to be the case. I thought that Chinlin was fantastic.

Speaker 10 (02:54:05–02:54:59)

He knocked my socks off. He knows his stuff. He knows every single position. He could probably do every single job.

And I just think that that's really important. And I also agree with you, the way that they treated each other was something that I guess that's the soft stuff that I wanted to see. So I got my wish. I mean, PMA, we know what we're getting.

They're terrific. They always do a great presentation. They obviously have a vested interest in Milton, having two people from Milton. So that's also a nice thing to have.

And I did like Love Field as well. I think they have a good approach for community. So thank you to the team that brought us these three candidates. They're really hard to pick from, but if you were to put me on the hot seat, I would say Vertex is my number one by far.

Speaker 2 (02:55:03–03:01:28)

All right, I'm gonna touch on all three a little bit. It's funny, actually, if you would carry on. I really like Chin Lee, but the whole time he was talking, I was thinking, I want him for my architect, not OPM. I really mean that.

I think he presented very well as an architect, but that's not what we're hiring. What we're hiring is being OPM, which is a very different role. But I do, they all threw it very close. The scoring was all very close.

I also came out with, PMA on top, but I'll stop the other two first. Like I said, Vertex I think presented well too. They know their stuff. They've obviously got a good reputation in town.

I do worry about the number of municipal projects that they're doing in town. There can be conflicts there, which does worry me a little bit. I also like their answer on question number two. They didn't shy away from the fact that you know, outstanding circumstances led to increased project costs, and no one else mentioned that, and I was kind of impressed that they mentioned that.

Left Field, I thought, also presented well. I think, other than the community outreach that's already been talked about, the thing that really impressed me about them was their HVAC, their OEP expert, which From a OPM standpoint, you can't really estimate, it's huge. I mean, the most expensive change orders are always coming from mechanical systems, and it's really good to have someone that's on board like that. It's actually something I'd actually, moving on to PMA, I'd like to, one of the things I think they're definitely behind a field on, and I'd like to push them on that, like, ooh, two medium loans for you guys, and I'll make sure it's someone good.

But obviously, Sean really presents well. And it's easy to say that, you know, they knew the project, so they knew how to talk about it. But having been through this process with them before, they did the same thing before. They just really do their research.

It's not boilerplate. It's very project-specific what they talk about, which I love, because that's what I want to hear. And that's, I mean, if they didn't make it, that was part of the problem. Almost every one of them.

I'm not really seeing much of anything specific to what our design problem is. And I like that, the other thing I'll mention is that I like the little diagram that they did to break down the program. That was really, really helpful. I'd like to see a little bit more of that from PD&E as well.

But like I said, I had PD&E on top, but it was not by much. I think it was by a couple of ones, maybe. I'll also point out, me and Scott, we did no collaboration. Surveys before were pretty much right on.

I think this time, too, we were pretty close. Thank you. Sean, could I ask Glenn a follow-up question? Vertex was the only company who didn't ask about the change orders, and I was just wondering, I think it was more, I was going to, I think it was more time and scope and less questioning, but, and I also, I think I have a pretty good idea of that changeover approach because of the work they've done in town.

So we kind of know how they deal with that, which I think is, you know, that's a good system. I think the fire stations have all been pretty much on time, on budget, right? As far as I know. because of the opening up of the design round as well.

Yeah, thank you. Tim? Yeah, I was also really happy with the group and co last round and didn't necessarily agree with, so I was on the subcommittee. I was very close to these three, I think I had two with the other one being in fourth place in a very close race there.

So I was thrilled with the group we bombed up with. And I like how you said the specificity of PMA, because that's really what I, and I know they have the built-in advantage of having worked on this in the past, but they did the same thing in the last time, and they did not have that benefit at that time. And, you know, Sean's able to speak. his other team members who are right on the same page with him.

Left Field came in. I mean, they were whiz-bang with their community engagement. Their graphics package was really good. Their presentation was highly scripted, unlike PMA, who was just like, we are here to talk about any aspect of this that you were here to talk about.

I was very impressed. But I had a great time listening to them learn from Vertex also. and happy with the way it worked out for them. Yeah, I'll just kind of close up mine.

So, similar to what you said, Brian, I'm a project manager, owner's project manager. So, part of me is that you just look at the metrics, it works. So, for a project management experience, Tim Dorman with Vertex, one year prior to that he worked in 95. He has no educational experience.

He has other projects and student project management experience, but for a project where both of them are out in the United States. Sean Burke, with PMA, has 21 years experience with that project, including schools. And then Chin Lin, to your point in the left field, it didn't seem to be a script that you were technically reading from during the presentation.

Speaker 10 (03:01:28–03:01:35)

I think that's because the guy who was supposed to lead the charge and couldn't be here wasn't here. I think they had to talk to a little bit.

Speaker 2 (03:01:35–03:05:28)

And that gets more difficult, because we're hiring a product manager, Tim, we're not hiring the owner who wasn't here. So for me, Sean Burton was the PM. He talked to the majority of the family and offered a validation, So yeah, I mean, similar to me, coming into tonight and just reviewing everything, Vertex and PMA, it was, I was very torn between the two of them. I wanted to see kind of really the advantage.

I wasn't with left field just, just due to the experience on paper I had in the party, like behind me while we were starting. So yeah, I mean, for me, it was a very So kind of with the discussions we're just having and stuff like that, I know everybody's already scored and stuff like that. Is there anything you need to be said that makes you want to change how you write? I don't want to change.

I want to make one more point with Sean. Communication with this project is going to be so key. We're going to have community issues, let's be honest. I want to talk about, there's going to be some opposition.

I just think Sean is so equipped to speak to our community and do it well, and as a member of our community, which shouldn't matter, I think, on this project. Yeah, I think it just makes sense, tuned into what's happening. That's my last point. Sorry.

No, no, no. Sorry, I didn't mean to cut off the I just want to echo, kudos to whoever whittled them down to these three. This was difficult, it was really good. You did that.

Thank you. All right, so there's a drum roll. No, it ties up with the conversation. I'll just note that Kerry, Pete, and Mark had It's time.

No, June 17th, I think. So that must be it. We need a vote? Yeah, so we need a formal vote to bring them to PMA.

To rank them in that order, PMA, Vertex, Lafayette, and to authorize the negotiations. I'll make that motion. Second. Any discussion?

Speaker 3 (03:05:29–03:05:35)

Hearing none, all in person, so we can just say aye. All those in favor? Aye.

Speaker 2 (03:05:35–03:06:40)

All those opposed? Hearing none, that before the July date. I guess it would just be Chinale. That would be the only other parallel path.

Yes, so one of the other things is somebody made a weird school committee last week. Yeah. Sorry if it's boring. Yeah, no, it's fine.

School committee last week. We're there, so there is essentially the contract that we voted on in our last meeting to have Shenali from DLR Architecture Group perform kind of a schematic design of feasibility for what that will look like there.

Speaker 3 (03:06:40–03:06:42)

We have that.

Speaker 2 (03:06:42–03:07:01)

At our next meeting, we will have to vote separately for the cost assessment of structural engineering as part of that. this month, just to kind of execute that. So for folks, know that Mondays are a typical meeting time.

Speaker 3 (03:07:01–03:07:09)

I'm meeting Mondays this month for the next couple of weeks. I'm traveling on June 29. Me too.

Speaker 2 (03:07:14–03:07:42)

I'm in Fox, Scotland. So how about this, let's aim for two weeks, 20 seconds. If I am traveling, I can probably call that. Appreciate it as well.

That's fine.

Speaker 10 (03:07:43–03:07:53)

And if you didn't know about it, Nathan did a very nice, concise wrap up of Laburai. That is my favorite thing that comes up. Thank you for doing that.

Speaker 4 (03:07:53–03:08:13)

It's truly helpful. So what would we be talking about on the 22nd for that project? It might be nice, for example, to hear some kind of, or is it premature to hear anything about what's happening on the architect front?

Speaker 2 (03:08:39–03:08:59)

Yeah, sure. Maybe in person, maybe remote. But I think that would be just kind of in line with the rapid timeline we're under and collaborate to get the architects up and going now that we've got a program, have them check in with us to see if there's anything they need from us to move forward or anything like that.

Speaker 4 (03:09:03–03:09:22)

It's such a short timeline, and the more opportunity, everyone's just kind of checking on each other a little bit, just to kind of make sure everyone's thinking about it right, in terms of what everyone's doing. So it'd be great just to hear that from that team.

Speaker 3 (03:09:24–03:09:44)

That'd be great. Any other agenda items that you think we want to discuss? Make a motion to adjourn. Second.

All those in favor?

Speaker 1 (03:09:45–03:09:49)

Aye. Very good. Thank you very much. Thanks, Sean.