It's called the meeting to order the Town of Milton School Building Committee. It is 7.03 p.m. on June 9th. As typical, I'll just do a roll call for those in attendance and those online, the committee.

So with me is Gary Early. Here. Nathan Hutto, our newest member. Here.

Tim Lombard. Present. Glenn Hoffman. Here.

Tom McCarthy? Present. Scott Tereshak? Present.

And Sean O'Rourke. So with that, we'll get to item two, which is citizen speak. We reserve the first 15 minutes of the meeting for any citizen that would like to speak. We ask that you reserve your commentary to three minutes and please state your name and address.

So if you're here and would like to speak, please just raise your hand and I'll promote you. All right, seeing none, we'll move on to item three, which is approval of past minutes. Monday, May 12th. I didn't have those ready, so we're gonna table that and move that on.

Speaker 3 (02:10–02:15)

Are you taking minutes right now?

Speaker 4 (02:15–02:18)

I always do. Okay. I can take him.

Speaker 3 (02:18–02:26)

Is that is there someone assigned or how like how do you want to go? We used to have a rotation of assignments and then PMA took it over and now we're back to.

Speaker 2 (02:26–03:06)

So I was just curious how we're managing that right now. I was just going to do it. OK, yeah. I mean, the meetings right now are pretty light, if you want to call it that.

We're not as dense as we were before. So I've been kind of just on my own, just to put it that way. I already have the template set up and everything so I can populate it. All right, old business, update discussion MSBA module one.

So let me just share my screen to show you where we're at.

Speaker 1 (03:06–03:10)

All right, so to go to SNP.

Speaker 3 (03:18–03:20)

It allows me to mark it up easier.

Speaker 2 (03:20–06:08)

So currently, the ICC was, I shouldn't put Xs, I should put a checkbox. It's probably more appropriate. The ICC, which was the initial compliance certification, was submitted. That was due at the end of last month.

So select board school committee in town, I think town administrator signed that. The next kind of step that we have that's going to be due at the end of this month is the formation of the school building committee. So with us right now, we have our members. I think the one we're waiting on, it'll be decided tomorrow night, is the select board.

We'll make their final appointees for that. So Glenn, assuming you'll still get appointed, I think that John Cohen may be stepping down, I'm not sure. But then they need to have one select board member per the MSBA guidelines or rules. So my anticipation is one of the other select board members will be joining us.

Which one? I don't know. So. I don't know.

So I watched the last select board meeting and it was We've got two new select board members with Megan Haggerty and Vincent Daly. And with that, there's a lot of new assignments going on that other people were on. So this is kind of the last one I think they're working towards. So we'll see.

The other one that comes up, so the stuff that's shown here in white is work that MSBA has to do. So the educational profile up to 90 days. And then online enrollment projections up to 90 days. So the design, making sure I can see that.

There we go. That's better. Man, I sort of shot. The online enrollment projection is one that is work that the district needs to do.

And the main reason for me is that's going to line to kind of push school committee and the district, just to keep an eye on that, so it just doesn't fall off the radar. With that, I think there's some stuff on MSBA that talks about how they do their enrollment projections. Sorry. Let's see.

That's better. The education profile, let me just go back to that for one second, please.

Speaker 3 (06:16–06:26)

doing things covering my screen. I apologize about that.

Speaker 2 (06:26–08:07)

Sorry, I'm drawing a blank on that one. I think it's the educational profile that the district has to develop. And then the enrollment projection is provided by MSBA, I believe. Well, I have to talk to Nick about them.

I apologize. Um, but the key thing with this is, you know, the overall timeline of it is, you know, between June and July is we're going to have another. Um, kind of deadline coming up on that. So, as we're going through it, asking to just be aware, keep on the lookout for some of the meetings and stuff like that.

And then similarly, probably. As I should do, jump into the MSBA website and just look at some of the stuff that we have coming up between June and July that will be there. The one that's going to come up right after that, and Thomas is where we'll be working with you on it, is the maintenance documentation for that. And that's where the enrollment certification happens after that.

So with that, the maintenance documentation, again, there's a separate portion of the MSBA site that's up there that basically gives all their explanations for what they're looking for, for everything over there. I haven't had a chance to dig into this. I'm not prepared to defend it.

Speaker 3 (08:07–08:23)

I don't know if they were ahead of themselves, but I did a survey with a gentleman that worked for a firm for the MSBA. We went to every school. And he talked about all the systems and everything. So I don't know if that's definitely in the head of the consultant.

Speaker 4 (08:23–08:23)

I don't know.

Speaker 3 (08:23–08:40)

I guess we'll find out. But the survey is done. The only thing we ended up having to do, which I thought was odd, because we did all the schools except for Cunningham. And then all of a sudden, we're like, yeah, we're going to Cunningham.

So we did that. So if you think.

Speaker 2 (08:40–10:46)

And if it's something else, we'll admit it. Yeah, the good thing, too, I got to talk with Nick a little bit about this, too, because with Nick working there, he knows kind of exactly what they're looking for for some of it. So we'll pull in some of that. But in regards to the overall status of where we're at with Module 1, does anybody have questions or anything like that?

All right. I'm just going to check, stop sharing for a minute, Just seeing if ACWA or anybody else had joined, because that's the problem with the Zoom is, if they get in there, I can't see if they're in there or not. All right. Back to, all right.

The other one that we have outside of item four, closing item 4A, going on to item 4B is the discussion vote for a BSC survey. So, Share my screen again. So as part of the land swap, when we did that back in 2023, town councils asked us for some of the parcels that were included in the land swap. They had historic documentation on there, but there wasn't a current boundary map or survey done.

So what they've asked us to do is re-engage with BSC engineering for them to essentially do boundary surveys on the part from two parcels. So the first parcel is the larger one where we use the centerpiece of this as part of the land squad. So it's basically a boundary survey of that entire one. And then the other one, the BSC one, it was 1938.

Speaker 3 (10:52–11:00)

I don't know if it's even on this.

Speaker 2 (11:02–12:15)

It's not on there, but essentially what it is, it's the other parcel that's up here that's made up of five separate parcels and one of them was a portion that was done as parks land and the remainder of it was for conservation. Essentially, this we received, survey, a proposal from BSC group that totaled $32,000. So we got this back in December of, or December 2023, this is more recent, sorry. Yeah, January of this year.

I've checked with BSC, the proposal is still current, so they didn't have to adjust it or anything because it's six months old. I'll open it up and see if anybody has any questions about this. This is just a boundary survey? Just a boundary survey.

I think one large parcel and the other one's broken up. This one is consisting of a couple of lots in there.

Speaker 3 (12:19–12:39)

Okay. And we can go and get other quotes.

Speaker 2 (12:40–12:51)

I just went to them because they did the other. Yeah. And if people find that we can get other quotes. I didn't know the cost, so that's why I didn't.

Speaker 3 (12:51–13:10)

Is there a requirement that we get through in town? I think we're going to be under a dollar. I think it's under $50,000. So it's not that good.

Yeah. Well, maybe the mass would show, like, hey, something like maybe $1,000 is a little high.

Speaker 2 (13:11–14:05)

That's been fine and great. No one's revealing them? I don't think so, but I think Town Council is just trying to wrap up all the formal paperwork for everything. It is a large lot.

It's six acres. One is six acres. The other, I think, was 12 because it's a portion. I'm trying to remember the one.

This one, the second lot that's here, I-38E. Let me look that one up. The six-acre one that we're looking at was basically this portion here, which was six acres. This one is,

Speaker 1 (14:15–14:16)

100 acres.

Speaker 3 (14:18–14:28)

So. I don't think it's like a cost per acre thing. I don't think that's the way that it's calculated. No, it's not.

Speaker 2 (14:28–16:13)

But a larger lot is going to be more field survey work. So what happens is this large lot that's here encompasses portions of granite links. So granite links the lease line just for everybody and even the public that's watching. Granite's Links lease line, if you guys recall, kind of cut through here.

And all of this is owned by Granite Links. So it's not like the town had 100 acres there that we moved in. We moved a portion of it over here that abutted the six acres that we were putting in before. So really, what we need for the lands that we put into conservation was this portion here and a small portion of parks, and I think another piece here.

But because it's an overall reference to a parcel, they have to survey the entire boundary all the way around. So it's basically from the access road over to Lyman, up to the edge of Quincy, and then along the lines there. I believe so. I can coordinate it.

That's probably where some of the money comes into. Yeah, sorry, I thought it was just from what we had before, it was just this portion. And we had the dimensions of that from the lease line and the boundaries that we had as part of that lease. And this will basically be a survey in the entire process.

Speaker 1 (16:13–16:23)

Yeah, it makes sense.

Speaker 3 (16:23–16:37)

I think you'll find some of the other quotes you'll get from over the dives. They're a little slow right now. Would they be able to do something this large?

Speaker 2 (16:37–16:41)

They could, but they're slowest. When you say slow, you mean reaction?

Speaker 3 (16:41–16:52)

When you're saying slow, I didn't know.

Speaker 2 (16:54–18:54)

So this is basically what I shared with all of you, essentially by email and stuff like that. So in regards to the proposal or anything like that, if there are any questions, if not, I'll attempt have available payments? Yes, so what happens is we have funding that's left over from the money that's been allocated. So good question.

In town meeting I think two years ago in December we were provided I think it was $475,000 that are aware of the OPM, we've closed out PMA, and they came in well below what they were budgeted. So we have residual funds there. And then also from last time, Scott, that you looked at our finances even before we allocated that funding, we had enough money during that. So one of the things I'd like to do at our next meeting is come September, when we go to onboard and OPM and all that, we're gonna be, allocated through debt, 1.5 million that was passed at the winter town meeting.

And what I'd like to see is how much money's left over. If we have a bunch of free cash that's left over, you know. Which is what funded that initial draw. Correct.

And so I want to talk, once I confirm it with Amy Dexter, town administrator, I mean town finance director, if we could talk to her to find out, is there a way to kind of refund it to the town so they can utilize it for other things Because we'll have other source of funding, the $1.5 million. So we have a lot of action for us to take. You're not telling me that. No, because we don't know what it is.

But I know we have enough that we can cover this. And then essentially after this, we wouldn't have any additional items or expenses that I'd be anticipating.

Speaker 4 (19:00–19:05)

I'll make a motion to approve the BSE group proposal data, 1-28-25.

Speaker 2 (19:07–22:57)

Second. Second by Scott. All right. Any discussion?

Hearing none. Well, there's nobody online, so we're not hybrid. So we just do rather a roll call vote. All those in favor?

Aye. Unanimous. All right. Item 4.

C, discussion, so our overall project timeline. So as I mentioned previously is, stop sharing, as I mentioned previously, so our project timeline right now is we're working towards getting in over the summer, completing module one, starting module two, coming up at some point in the fall, you know, ideally September or something like that. So I want to get, we got to work with MSBA once we get the roster finalized, the next contact with them is find out when their next board meeting is so we can advance from module one to module two and kind of get that on our radar. But as I start kind of plotting things out, right, we onboard in fall 2025.

probably won't finish schematic design until end of 2026, which basically lines us up with, you know, a year for its schematic design, maybe even longer, puts us basically into 2027 before we do votes on some of this stuff, potentially. The other way is with MSBA's letter to us, we couldn't do any funding requests until July 2027. So what that means is we're trying to get clarification from them, but if we can't do the funding ask by fall, I call it May town meeting 2027, we'd have to kind of push it beyond that or come up with a special town meeting for that. So my concern is with the land swap, we have a reverter clause that kicks in May 2028.

So once we start hitting anything with a 2027 deadline, we're going to be pushing up against that 2028 reverter clause very quickly. So, you know, I think it's something that us as a committee need to just be aware of, of like, you know, three more years from now isn't really that far away. It sounds like a far away way, but like, if we know the pace of, That's going to come really quick and we're locked into certain chunks of time by MSBA that's stretching us out a little bit, which wasn't anticipated when we did the land swaps. For everyone here, I don't know if everybody else is in deep as I am with thinking of some of the stuff and keeping track of it there.

That's something that I want to share with everybody here that we kind of need to start thinking about, you know, as we're moving forward of a, you know, how can we move faster and maybe get MSPA to move that fall 2020, I mean, July 2027 deadline back so we can hopefully do something in May 2027 for funding. And if it doesn't pass, it gives us some time to catch up. But if we can't, that basically means we would have two town meetings one in the winter of 2027 and one in the spring of 2028 that we could do for funding. And those type back-to-back would be really tight.

So that's my take on the timeline. So we'll open it up and see if anybody has questions. Tim?

Speaker 3 (22:57–23:07)

Is the 12-month SD timeframe prescribed by MSBA, or is that just what you've conservatively scheduled?

Speaker 2 (23:08–23:12)

conservatively scheduled. Yeah, just no one helped.

Speaker 3 (23:12–23:32)

I'm thinking back to when we were not on the MSBA track and we exceeded that schedule in a non-MSBA track. And I know that this all is kind of, although we have solid conceptual designs, it is back to the drawing board. But I was just wondering if that's prescribed.

Speaker 2 (23:32–24:28)

Yeah, there's no prescribed 12 months schematic design. I think we had to ask them to move faster than we could, but I just don't know if MSBA as a state agency would give on some of that. And part of it that we're going to find out about too is like, as we know, trying to schedule stuff at the town and the lineup at town meeting, all the committees that have to go before and stuff like that before it goes live. MSBA is probably going to be very similar where they're going to want to flush things out before it goes to their board.

So my anticipation is nothing that we do is ever going to move as fast as what we were moving the previous years. The other part is like starting over, anybody who worked with an architect before, they're not going to want to take what another architect did and say, yeah, we'll expand that. You know what I mean? We'll have to see how the architect procurement process plays out if we

Speaker 3 (24:30–24:37)

do end up with a successful proposal from the same group, there could be some timeline advantages there, but that's not necessarily what will happen.

Speaker 2 (24:37–24:51)

Yeah, we can't bank on that. That's my main, like if Arrow Street came on, we could resurrect what we did before. Even if they do, there's going to be major changes to that.

Speaker 3 (24:53–24:53)

So.

Speaker 2 (24:54–25:18)

Yeah, your point is 100% right. So the size of the classrooms, if you recall, we made the classrooms a little bit smaller.

Speaker 3 (25:19–25:25)

Oh, yeah, but that would be bigger, which changes the whole thing. Yeah, you use the mask.

Speaker 4 (25:26–25:27)

Correct.

Speaker 3 (25:35–25:53)

Is there another MSBA approval required within the first year, whether it's something similar to funding? Well, the funding runs in module one again.

Speaker 2 (25:53–28:37)

Yeah. So we got the invite from board of directors. We closed out the initials, compliance certification. We're forming the school building committee, like I said, once the select board provides their appointee, we'll be good on that.

The educational profile and the online enrollment projections, we'll have those done by July. The maintenance documentation, they give us 180 days from May. My goal was to try to get ahead of that now, so that's not to burden you or anything like that. We're here to help.

Whatever you just point us in the direction, we can help with a lot of that stuff. The local authorization of funding is the other one, and that's where we pass it. the town meeting in January. So when we got allocated the $1.5 million, that checked that box.

And that was the big reason I was pushing that one. That's the hardest one to get. So if we got that out first thing, then it clears everything else and just kind of moves forward a lot quicker. Yeah, so once we get that, this is the last step to get out of it.

So we need to work with the USDA to get on their directors, let them review all the submitted documentation we give. And then they, you know, we graduate in module two. Okay. So that was just funding for module one that needed to be approved, essentially not funding beyond that.

Yeah, it's just funding. So it's funding that funds module three. So let me just go back. Is that the feasibility?

Yeah, that's the feasibility. So there we go. Eligibility period is where we are right now with module one. forming the project team was Module 2, feasibility is Module 3.

Okay. And then after, yeah, so that's, like I said, this forming the team is what I'd like to try to get to in the fall, get everybody on boarded, try to get everybody on boarded by December. You know, if we can, again, align with that, this is going to be a lot of work, back and forth with MSBA to, you know, find out when their board meetings are, try to push them so we can get on their board meetings. Or designer selection committee is actually the one for the architects.

The OPM will do our own interviews like before, pick our OPM. And then the designer selection committee for MSBA, we'll have to figure out when those happen. I think they're mostly, but it's just a matter of getting on that agenda.

Speaker 3 (28:39–28:46)

And the overall funding for a town meeting is the one that's needed to prevent reversion of the learning spot.

Speaker 2 (28:46–30:29)

Yes. Yes. So the initial funding we got for the schematic design isn't funding that would hit that reverter clause. So the language that's in there for construction funding.

Yeah. So that, um, Yeah, that's just one, again, as we're going through this whole thing. When we originally did the land swap and agreed to the reverter clause at five years, the intent was we never thought we'd get into MSBA, because obviously MSBA is a longer timeline. And if we knew we were getting into MSBA, we probably would have made it longer to align with MSBA.

So it's a kind of a new little wrinkle when I'm looking at the overall timelines. Again, we just need to be aware of of, you know, the deadlines we have to hit are kind of going to be important. But, you know, going, if we, when we weren't going with MSBA, you know, the timeline worked, because, you know, as you recall, last summer, yeah, it was last summer at this point, you know, we got our, we came up with our cost estimate, we're looking for funding, we wanted to get on in the fall for the vote for the debt exclusion, if we got that, We weren't worried that there were verticals, even if it failed in the fall, it still gave us time to recoup. Now, with everything kind of coming at some point in 2027, possibly, maybe end of 2027, that's where that, you know, May 2028 comes around really quick.

So, we can discuss that more, just keep an eye on it as we're going forward with everything. Any other questions?

Speaker 1 (30:30–30:35)

Comments? Nothing? Okay.

Speaker 2 (30:35–31:46)

The item five, which is new business. So the school building committee roster. So for those online or you guys here too, so Nathan Hutto from school committee has been appointed. He's replaced Selena Miranda.

Um, the, uh, you know, Dr. Miranda was, you know, she was great. She was on this for two to three years, I think, or something like that. So, you know, I appreciate all her help, you know, over that time.

Um, look forward to working with you, Nathan. She'll be fine. And so you, a daughter is in class with my daughter. She's in class.

So, yeah. Yeah. So it's like a, mirror image of our daughter's class. That'd be interesting.

But yeah, and then tomorrow night, like I said, the select board will make their appointment. So we'll see what comes out of that. It'll be good. Glenn, hope you're still with us.

I'm a politician.

Speaker 1 (31:46–31:50)

I'm part of the process.

Speaker 2 (31:51–31:53)

Yeah, so any questions on that?

Speaker 3 (31:53–32:05)

And there's no further action for us existing members to take beyond the email correspondence we've had over the past couple of weeks confirming that we are interested in saying that there's not, do we have to be at least sworn in by Susan Gallin?

Speaker 2 (32:05–36:42)

I don't think so. I'll find out about that. But yeah, that's actually a good point too. So for you guys that are, so myself, Scott, Tim, Karen, we're all appointed by town moderator.

Typically each year, the previous moderator, Mr. Hiss, would email me just saying, hey, just try to see if everybody wants to stay on, because sometimes they receive applications. Everybody wanted to stay on a couple of years ago. Cool.

And I just rechecked with everybody. Everybody confirmed they're all up for staying again. I just, I haven't relayed that to our new moderator, moderator Dylan. So I'll send that to her and just hopefully, yeah, again, because she could, I don't know if it's going to be able to get a confirmation from her.

I don't know if it's going to be able to get a confirmation from her. I don't know if it's going to be able to get a confirmation from her. I don't know if it's going to be able to get a confirmation from her. I don't know if it's going to be able to get a confirmation from her.

I don't know if it's going to be able to get a confirmation from her. For the most part, yeah, all five. So the five of us are appointed by the town moderator. You and Mark Loring are appointed by school committee.

And Glenn and previously John Cohane were appointed by select board. So like I said, select board will make theirs. The other non-voting roles I think are all have been filled. I got to check with Nick on that.

But I basically want to get that final roster because this All of us at the table will expand once it's finally published to MSBA. So essentially what happens is the nine of us, the five appointed by the moderator, two by school committee, two by select board are all the voting members, and then the other members there, for example, Tom is a non-voting member. But there are certain rules under MSBA's guidelines for boxes that we have to check. So that's why we expanded the committee.

Any other questions? All right. The other one that I had on here is kind of what we've already talked about, new business discussion about, and that's school building committee town budget. I meant to get the numbers for what we were talking about there to find out truly how much we have left over in our bank calendar allocated to us.

minus the ESC funding. So I'll keep that for our next meeting. But, you know, just touching on that or recapping what I said before is there was money that was allocated to us essentially through free cash that we have available to utilize. But once we have the additional funding of 1.5 million, we won't need all of it.

I still think we should keep some mainly because if something is, so the reason I say that too is, I'm not sharing my screen. So the reason I think we should, once I figure out those numbers are all forwarded to everybody, so we're aware of it going into the next meeting. But I think, as you can see with everything comes up on this, things come up at different times that we need funding for. The 1.5 million, because of amendments made at town meeting, we're only allowed to utilize that 1.5 billion for MSBA study.

So if something comes up that's outside of that kind of delineating scope that's there. we need some type of funding mechanism to cover that if it comes up. So what that dollar value is, I don't know. But we can discuss that or plan to discuss at our next meeting, potentially vote on it to say we want to send back this much money to the town that will free them up to utilize it for different things in the town, which I think would be a great thing as a taxpayer.

So any questions? hearing none. The next one, future meeting dates. So about three weeks out is the rhythm that we're trying to keep.

So that will put us at June 30th. So if you guys could just kind of pencil that in. And like I said, the last meeting works good because it lines us up right before July 4th. So we can get a meeting and kind of be on track for that.

Then hit our next one after that. a couple weeks later on the 21st of July.

Speaker 1 (36:53–36:59)

Sound good for that meeting?

Speaker 3 (36:59–37:03)

Cool. All right.

Speaker 2 (37:04–37:24)

That's fine. I mean, that's That's what I've said to, you know, for people that are, you know, potentially going to be on here and stuff like that. You know, we're hybrid for everything. So the people have to be remote.

It's easy enough. Glenn, you've taken a couple of calls in your car. Absolutely.

Speaker 3 (37:24–37:31)

I took a call on a field one time. That's right. Yeah. I was at a baseball game with the practice.

I was hooking.

Speaker 2 (37:32–38:04)

The remote's good. Um, yeah, specifically over the summer. I mean, with some of the stuff that we're going to have, you know, just with the way the deadlines are going to line up with some of this stuff, um, it would be good. I'm going to be traveling a lot too.

So yeah, it's definitely a good option. All right. Item seven. Motion to adjourn.

See if anyone makes one. I'll make a motion to adjourn. All right. And we're all together.

So all those in favor. Aye.

Speaker 1 (38:05–38:06)

All right, thank you very much.