Board: Milton School Building Committee
Date: 2024-08-26
Transcript
Auto-generated; may contain errors.
Speaker 1 (00:49–01:09)
Uh, so it's, you know, you know, now 7 0 5, we'll call the meeting of, uh, Milton school building committee to order on, uh, August 26, 2024. Uh, with a snake from the committee is, uh, you know, roll call attendance. Like I typically do, uh, Scott Tereshak, uh, Mark Lauren.
Speaker 2 (01:12–01:23)
Yeah. Uh, president. Thank you. Uh, Glenn Hoffman.
Yes. There we go.
Speaker 1 (01:24–01:30)
And Tim Lombard? I'm present. Yeah. Dr.
Selena Miranda?
Speaker 3 (01:31–01:36)
Present. And just so you know, I actually don't have video just because I'm not enabled.
Speaker 1 (01:36–02:00)
Okay. I'll do it again right now. I made you a co-host. You might want to try it again.
It should get you. You can use mine. There we go. And last is Mr.
John Kohane. Welcome, sir. Present. Thank you.
Yeah. And Carrie, you should, too. Perfect. Get her in.
We'll have full attendance.
Speaker 2 (02:05–02:08)
Let's make Carrie a co-host and get the video.
Speaker 1 (02:10–02:11)
There you go. Hey, Carrie.
Speaker 4 (02:12–02:13)
Hi, how are you?
Speaker 1 (02:13–03:13)
Just in time for attendance. Great job. All right, so item two on the agenda is citizen speak. So we reserve the first 15 minutes of our meetings for any citizen that would like to speak.
We ask that you raise your hand, state your name and address, and then please limit your comments to three minutes. So we have a couple attendees, so just see if anybody has something they want to say, and we'll just pause for a minute. All right, seeing none, all right, we're moving. Item three is the approval of our past minutes, which was Monday, August 12th, 2024.
So as always, Shanice, thank you for sending them around in our packets. So just open it up to see if anybody has any edits, comments, or anything like that in regards to the minutes from our last meeting.
Speaker 5 (03:22–03:48)
Seeing none, yeah. I just have a comment on item 3.01. And just, you know, it's maybe minutiae, but that I had asked you for the list to get to me, remember? You know, to get me a list, and I don't see that in there at all.
Speaker 1 (03:51–03:55)
James, is that something you can amend to the minutes?
Speaker 6 (03:56–04:06)
Yep. I can add that you were going to send an email to John with what you guys need. I'll add a line there in that meeting section.
Speaker 1 (04:07–04:11)
Yeah. Johnny, you're referring to your request to me for the expenditures?
Speaker 5 (04:13–04:23)
No. You were going to send me a list of what to go to the board for. Yeah, you did, you did, but it was just in that section.
Speaker 1 (04:24–04:43)
Okay. Okay. So yeah. Shamus, if you could just edit that.
So, so with, with that edit, uh, just seeing if there's any, any other comments that people have and if hearing, hearing no comments, we cannot make a motion to approve with that edit as long as, you know,
Speaker 7 (04:47–04:51)
I'll make a motion to approve the minutes with that edit.
Speaker 2 (04:51–04:51)
Is there a second?
Speaker 8 (04:55–04:55)
Second.
Speaker 1 (04:55–05:20)
I second. All right, any further discussion? Seeing none. All right, so roll call vote, because we're remote.
Scott Tereshak? Yes. Mark Loring? Yes.
John cocaine. Yes. Selena Miranda.
Speaker 3 (05:20–05:21)
Yes.
Speaker 1 (05:22–07:08)
Carrie early. Yes. Aqua bomb. Yes.
Yes, and Tim Lombard. Yes. All right. Great.
So, moving on for item for a new business for a, which is update. So, as most, you know, we sent along had contacted the district. I think it was last week in regards to. an update from them.
So what happens is we submitted our Statement of Interest, as everybody's aware, in the spring. We got an update from them that they want to come tour the schools. So it's basically like the filtering process with MSBA. We pass the first filter and now we're on to the next one.
They're going to be coming out to the schools. I believe it's the 17th, 17th, and then it was the team apologies. But so it's good news. So, for, for some of you that recall, I think it was in 2020, actually, we made it to the similar step, but their visitation to the school at the time was all basically through video conferencing.
So we had Dr written and. and Cunningham walking around with iPads basically showing what the spaces are. At least this time, they'll get an in-depth, in-person, you know, review of everything. So, essentially, with that thing and perfect timing, Mark, I was going to open it up and see if people have questions or comments in regards to that.
So, Mark, go for it.
Speaker 7 (07:09–07:14)
Sorry, just a quick clarification. What was the last year we got to this step of the process? Because I know they didn't come out this year.
Speaker 1 (07:15–07:29)
Yeah, I believe it was 2020. And the only reason I think it was 2020 was mainly due to the pandemic. We were kind of in the midst of the pandemic, which didn't allow them to come into the schools. So that's my timing.
I can confirm what that was from before.
Speaker 2 (07:36–07:50)
So it is September 17th at one o'clock. Is that something you would want us to be present for Sean?
Speaker 1 (07:50–08:33)
I'll find out. I don't know if the entire committee would need to be present because I think it may be a little overwhelming, but maybe, maybe a few of us to go with them to kind of see if they do have any additional questions for us. Thanks. And even further, if we needed to, I could find out if they could do a debrief even after that meeting, you know, if it's a day that we can all go and maybe just schedule one of our meetings, you know, at two o'clock, if they think it's going to take an hour at two o'clock and kind of have a debrief with them if possible.
So if that's something that you're interested in, let me know and I can look into it.
Speaker 2 (08:36–08:43)
Thank you. Any other questions?
Speaker 1 (08:49–10:15)
Seeing none. All right, moving on. So item 4B. for new business, which is our fall town meeting warrant article for funding article.
So I was looking through kind of what the schedule of the rhythm was last year for town meeting. And for the fall town meeting, which was held, I think it was in the first week of December, the warrant for that town meeting last year closed kind of middle, third of the way through, I think, the 22nd of September, they closed the warrant. So for us, it would be important, essentially at our next meeting, to be able to have a vote on these articles and get the language together, which I'm working on currently. So, you know, with that, what I wanted to do is have a meeting now that we can kind of dive into some of the questions that we may have or or comments or anything like that leading up to it, so that we were prepared in two weeks that we can actually take a vote on this and make our recommendations for it.
So with that, I'll just kind of open it up for any questions or comments that we can kind of just start diving into it. I see Mark smiling. I knew it was coming, so go for it, Mark.
Speaker 7 (10:15–10:43)
I'll try and watch my air time. To be clear, the initial article that we talked about last week was a funding article that would provide us enough funding for the designers specifically, maybe also the OPM a little bit, but we feel better about the OPM budget thus far that would get us through construction documents and fund us for the remainder of that portion.
Speaker 1 (10:43–11:06)
Yeah, I'll let Shanali talk a little bit about it, but what it would be would be full construction documents for the road realignment and then design development documents for the overall program for the school. So they wouldn't be full construction documents for the school, but it would definitely be a much more expanded, detailed set of documents that we would have with that funding.
Speaker 9 (11:06–12:54)
So Shanali, if you can kind of just… Yeah, so the DD, We gave a rough estimate to both the Shawns for the DD for the two buildings and for the CDs for the road construction so that we could do a preliminary site package to get the site work done prior to the building construction. And by doing that, there is a little bit of cost savings because you don't have to go through the same process With the GC for the buildings, as you do with the roads, and it can let Sean or Seamus or Sean's not here. I forgot.
She must speak to that. Yeah. So there is a different process, but it does give you some savings, but more importantly. the savings comes from the time, because you're able to start that site work prior to the building drawings being done, and that the escalation costs are severely decreased.
and the site is already then prepped and ready for the GC to get on site. I am currently getting fees from all of the consultants to finalize their DDD numbers and get all of their fee estimates all the way through CA. It's still going to take me a little while. It's actually a very Not hard, but it's like, it takes time, the process, because there's a little bit of back and forth.
So all the consultants have been notified of waiting for numbers to come in, and then we'll do a little bit of back and forth to make sure that the scope is aligned all the way through CA. So that's what we're working on at the moment, as well as the SD package.
Speaker 1 (12:55–13:14)
And Carrie, just before I call on you too, just so for everybody's knowledge, I know most people know it, but more for the public too. documents, and then CA is construction administration. So after a bit is done, administering the construction to the completion, so.
Speaker 9 (13:14–14:17)
Yeah, and I would just like to also point out that DD, the design development phase, is a really critical phase because it's linking what we're conceptualizing in the schematic and making it substantially more real. We're talking to the consultants, getting a deeper understanding of the correct sizes of the structure, of how deep the ductwork is going to be, the locations, really understanding what the back of house spaces are going to be. For instance, as a small example, like the electrical closets, right? Like we need to understand precisely how big they are, what the footprint is, and how many panels.
And so DD starts to get into that level of detail, whereas construction documents do the actual construction details. But it's that really vital coordination that we need to understand so that the building will end up looking the way that you're expecting it to look. So it's, in my opinion, one of the most important phases that we need to really dig deep in.
Speaker 1 (14:20–14:23)
Carrie, you have your hand raised.
Speaker 4 (14:23–14:40)
Yes, I was just curious, with the news of the MSBA, how that might impact. Are we going to continue to do kind of the parallel paths process? I'm just curious.
Speaker 1 (14:40–15:33)
Now, again, great question. So it's one of the ones that kind of jumped out at me when that news came up. But my anticipation would be any funding that we would be allocated, we would wait to hear from MSBAs. MSBA's decision is basically be done, I think, December 12th or somewhere around that line.
So the articles that we've put forward would essentially some of that funding. It's basically at that point, we need to make a decision as a committee, you know, which way we want to go. And it'd be really nice to have both options available.
Speaker 4 (15:35–15:36)
Thank you.
Speaker 1 (15:37–15:38)
Yeah. Selena?
Speaker 8 (15:39–16:06)
Yeah, just quick question on sort of these three different, you know, steps. How far out would that take us in terms of that work? You know, just thinking about our discussion around when we would go before the town for a vote, and how much, how much, how much work would we still be able to do as we wait for the town vote vote.
Speaker 1 (16:08–16:14)
Yeah, so the three things you're talking about are the. trying to be exact.
Speaker 8 (16:15–16:18)
Yeah, the DD and the CD and the CA.
Speaker 1 (16:19–17:08)
Yeah, so the CA definitely wouldn't come until later. Until we get full funding and break ground, we wouldn't be into that. The plan would be for this next phase of funding that we're doing for the $4 million plus whatever OPM fees we have to do, roughly, that would get us to full construction documents for the road Documents for the building so that still be further detailing that need to happen. The timing of that I know she's working on a schedule of that to kind of see how that aligns.
when this is gonna go. So, I believe by our next meeting, Shanali, I don't think you have the schedule ready for- I have a draft.
Speaker 9 (17:09–18:24)
I think in our last conversation where we reviewed it, I needed to understand when those dates in the spring were gonna happen so that I could backtrack it. And as soon as I get the dates, I can shift everything. For instance, dd a full complete dd is four months but i don't know what my exact start and end date is i want to shift it so it aligns with um the town of milton's requirements for town meeting and all of the necessary pre-deadlines to get to there. So until I have those dates, it's gonna, I need to adjust it accordingly.
So as soon as I get the dates, the schedule's all ready to go. I need to plug in those dates and just shift the things. But like DD is, I have figured out it's a four-month process for us. And whether I start December 12th or January 1st, well, not January 1st, maybe January 3rd, and then like, or February 15th, it's still four months.
But for me to get you to the end date is when I need some of those dates. And then I can give you a more formal presentation on the schedule and how it plays out.
Speaker 7 (18:28–19:16)
Mark, you're recognized. What's the timeline? Because I think the DDs for the road actually are probably, from a public perspective, less impactful than updated design, drawings, renderings of the physical building itself as we get out in front of voters. If we assume another December town meeting, and again, this is just to throw random numbers here and say, okay, that'll be wrapped up by December 15th, whatever that might be, it's probably a week earlier than that.
What is the timeline you all would anticipate for a DD set for the buildings, which are obviously more complicated? Is that also about four months? What is that?
Speaker 9 (19:17–19:45)
So I have the full CD site package occurring between the 50% and 75% DD of the building set. So it's a two and a half to three month schedule. I don't know if that's precisely answering your question, but the expectation is that the site package will be completed prior to the completion of the DD set, if that makes sense.
Speaker 1 (19:46–20:12)
Yeah, if I can jump into Mark, sorry, there's definitely going to be a synergy between the building design and the site package, you know, most likely that road is going to be full of utilities coming up to serve the building. So understanding what the, you know, anticipated sizes of some of that stuff is, that's where the package for the road is going to become important to, as we build that road to make sure we're putting the utilities in there to support the building.
Speaker 7 (20:14–21:11)
Yeah, totally hear that and understand that. I just think from a voter in perspective, I think right now our visualization of the road as is, is probably fine. I think we've made a lot of great progress too and probably have enough progress on the design too. But obviously a design development will get it refined even a little bit more.
And that's just my mind, like the sexier component where like, you know, you get some, actual renderings of what space will be and people feel that a little bit more of, oh, I could sense myself in this space versus obviously the site package being very important from a construction perspective, but again, from a public consumption perspective, maybe less so. Four months versus two and a half months or even three months, that extra month given the town vote is in end of April, seems important. That being actually really helpful and will align pretty well.
Speaker 1 (21:12–21:26)
Yeah, and I think at the end of kind of what we're working on right now, or at least in the coming months, Shanali, correct me if I'm wrong, but we're going to have some exterior views of the building a little more detailed than what we've seen so far.
Speaker 9 (21:26–22:13)
Yeah, we'll start to talk about materiality in the SD set. And we're still in the process of scheduling those working group meetings. As soon as we can get in front of the working group and talk to them and put to bed, so to speak, the plan and the adjacencies of all the spaces, then we can run with the materials. We're already developing pallets, but there's still in order in which we have to present things to make sure we get to the right place.
So while we've done all this materiality study, I can't move it forward until we get into those working group meetings. So hopefully next week, we will have a meeting on the calendar.
Speaker 1 (22:19–22:20)
of this product and stuff like that.
Speaker 9 (22:20–23:08)
You'll get some preliminary massing views in schematic, but those like really nice renderings, you're gonna see more in the DD phase and you're gonna see them more regularly and updated more regularly. SD, it's not gonna be, the fully rendered, you know, with people and trees and dogs and stuff, but in DD, you'll start to see some of that stuff. And certainly in CD, you'll start to see rendered views of specific spaces, you know, like the gym or the auditorium, like you'll start to get inside the building. During CDs, DD will still be outside for those renderings.
Speaker 1 (23:09–23:23)
Yeah, I think I think where Mark was going is those renderings won't come at the 12th hour, you know, at the end of April 1st time it's going to be coming, you know, as we're. be coming early and often as we're doing?
Speaker 9 (23:23–23:52)
Yeah. So like the design process that we've gone through with SD, we're going to present to you, we're going to present to the working groups, we're going to get comments back, we're going to incorporate them and come back. So this is the continuation of the same dialogue, but instead of looking at plans, we're going to be looking at 3D views. So absolutely, you're not going to get them at the end.
You're just going to get the final at the end, but you're going to have already been previewed. multiple times prior to that.
Speaker 2 (23:54–24:02)
Does that work, Mark? Cool. All right, Akwa, I'm sorry, you have your hand raised.
Speaker 10 (24:02–24:47)
Thank you for recognizing me. I'd like to understand a little bit of the process. Are we going to, can you hear me? Yeah, you're good.
Okay. At what time do we take this to the voters? Are we going to keep, it sounds like this DD and CAs and all the others are going to be some heavy financial lift. At what time are we taking it to the voters?
Should we not have financial commitments to deliver on this before we start spending more money and we're not sure whether we're going to move forward or not? Maybe I'm not just understanding the process. Help me
Speaker 1 (24:48–26:20)
Yeah, great question. So the intent right now for the articles that we're looking at is to have a funding article for, you know, to take us through that next phase of development that we're talking about for design. And, you know, part of that, you know, there were questions that came up, you know, as we were going through this previous exercise to get it onto the ballot. Um, they were raised that we essentially need additional funding to to address those and the.
The type of comments that were there, you know, necessity, you know, getting to that level of detail. So that's part of the reason we're going through this. So the anticipation of the hope is that we would have. A ballot questions in the spring next year to, you know.
Date and time to be determined, but, you know, with that, you know, what we're trying to do is expand the design a little bit further to be able to address some of the questions that came up this last time and address them. So that way, when it does go up again, That's what we're trying to do now. Obviously, this $4.5 million only takes us to a certain point in that design. We'd still need additional funding after that as part of the overall project to take it to full completion all the way through.
I hope if that didn't answer your question, feel free to follow up with any follow-ups that I might have missed or anything.
Speaker 10 (26:23–26:31)
It gives me a better understanding. I'll have further questions later. Yeah, no problem. Thank you.
Speaker 2 (26:31–26:33)
All right, Carrie.
Speaker 4 (26:33–26:40)
I'm just curious on this phase. I know we're talking about SD, which is site design, correct?
Speaker 1 (26:40–26:44)
Schematic design.
Speaker 4 (26:44–27:03)
Yeah. And we were talking about the road and utilities and infrastructure. I'm just curious, is it at this point that we are prepping the site for any sort of HVAC plans that we have down the road or is this, is that a different? time.
Speaker 1 (27:04–27:39)
Yeah, so you're talking the geothermal wells. So yeah, most likely what would happen is outside of the design of the road, the remaining land that was there, mainly the parking lots and stuff like that, the understanding is that's where most of the geothermal wells would be going, at least that's what we've heard from consultants. So as part of that design, there's no anticipation under the road to have the geothermal wells so they wouldn't have to be designed early on as part of this early site package, if that's kind of where your question was going.
Speaker 4 (27:39–27:42)
Yeah, I think that's it. Thank you.
Speaker 11 (27:42–28:27)
Yeah. Scott. Thanks, Sean. Just a couple of things while I was looking up while we're talking here.
Mark's earlier question about the last MSBA process. It was an application from 2020, but everything was delayed that year, so they didn't actually visit the school until January of 2021. But the application was in 2020 for a date for the spring town meeting. We usually don't find out for quite a while yet.
Right? But it's the 1st week of May. Typically, should we just make an assumption and say, go with May 1st on that. And then work the schedule from there.
So we have something to look at.
Speaker 1 (28:27–28:55)
Well, it's, it's 2 things, so the town meetings, typically the 1st, I think it's the 1st week in May for the annual town meetings. We know that the unknown that I think she's trying to work into her schedule right now is the town wide ballot. So, you know, that right now, there's no schedule for that. And that's 1 of the things we're requesting.
So that way, we can understand what that data is and. You know, push it into timeline, so we can kind of.
Speaker 11 (29:00–29:03)
Do we know if that happens before or after town meeting?
Speaker 1 (29:04–30:49)
It can be either. So what happens is, you know, to kind of go back to the process for the overall project for funding, to do a debt exclusion, you have to do two things. You have to have an article at town meeting that passes by a two-thirds majority for the overall funding of the entire project. And then you also need a town-wide ballot that it's only a 50% or 51% margin that would have to pass by, the order of which typically the way you would do it is you do the that the town meeting has approved, and then you do the ballot question following that, and that ballot question following it would then have, you know, as we showed, it doesn't have a number value on there, it just allows you to exclude yourself from the limits of Prop 2.5.
So, you know, the timing of We were talking with John at our last meeting for items that we'll need to progress the project and stuff like that. For what we're doing now, for this article or the funding articles we're talking about, would be to fund for the design and get us that way to do it. You could even put the full… I would assume you can even put the full funding now for the entire project and see kind of where that goes.
And if it passed town meeting, then you would only need the town-wide ballot sometime in the spring. And then, you know, we would be fine with that too.
Speaker 2 (30:52–30:59)
Great. Thank you, Sean. No problem. Yeah, Mark, you can trace.
Speaker 7 (31:00–33:42)
Yeah, you kind of jumped or Took it right out of my mind, Sean. As I was thinking about these timelines and as they line up, right, one of the concerns is the timeline between this town-wide vote and the town meeting vote and making sure that town members are clear about what the final number is and what they're going to be voting on and having enough time to communicate that well. And the fact that the town-wide ballot doesn't have a number on it, the town, you know, the warrant vote article that the town meeting vote for does. all those pieces.
And I know, you know, we obviously disappointingly missed the opportunity to get a town line down in the fall, but if I'm understanding it correct, I think to the point you're just making, like, there's nothing actually that at this point would stop us two from going to the town meeting to ask for the $173 million allocation warrant at this winter town meeting, which then if it passed, Then we have that number in the books firm for, you know, a special town meeting in February and the April town meeting, you know, whatever it might be. And again, I think that at that point, it again falls back. My understanding would be to the select board as to identify when they're putting this on the ballot. But at least the town meeting part is out of the way, right?
It is done, it is accomplished. And it's not this tight kind of turnaround between we have, you know, special town meeting two weeks before the town wide vote or something like that. And people feel, feel like it is rushed or poorly communicated in terms of what that number is. So I guess my question would be like, is there a way in which we could do kind of two Warren articles?
One is full funding for the project as approved by town meeting, which to Aqua's point kind of gets us some confirmation as to like, you know, how at least that representative group of the town are feeling about our project, and gives us some data point to move forward. And then the second would be, if that doesn't pass, let's say, then it's, okay, what about just funding to continue design? Because we'd assume if it doesn't pass, folks, again, similar to, I guess, maybe what the select board, some members have said of like wanting more information, that would be almost like the plan B. So you kind of have those two options presented in front of town meeting to get their opinion on.
And again, the best case scenario related to the school is we go ahead and get the town meeting approval kind of checked off with one of two steps.
Speaker 1 (33:45–35:37)
Yeah, I mean, so technically for warrant articles, we can recommend talking to Scott and said, yeah, you can do it at the fall town meeting, check that box, have that, you know, thing on the to-do list that we have for the project kind of crossed off if town meeting approved it. And then essentially, yeah, it would just be, you know, working towards that townwide ballot. I think the only thing we'd want to do similar to, you know, what Kerry had referenced earlier too, is if we're doing You know, if we got into MS, say we got full funding at some town meeting before the MSBA decision, I would probably want to have some type of language in there that at that point, do we go on our own at 173 million with no MSBA financing back to us, or do we pivot, move into MSBA, get a longer timeline, but get some type of reimbursement? And I know theoretically, we've talked about that at least over the past four years, as we've kind of been going through this timeline and looking at everything, but it'd be a unique one.
Like we were talking about in theory, but having impracticality of, you know, for us to kind of look at, but yeah, long-winded answer is basically, I think if we did something like that, we'd want to have some ability on there to not move forward with anything until we hear back from MSBA, if that makes sense.
Speaker 7 (35:39–36:08)
Yeah, so like some type of reverter clause and saying if we get, and again, I'm as hopeful as anybody else that we get an MSBA, but I think it's still a big if, we're not that many steps further. We've been scorned before. But some reverted cause to then essentially you're saying like force us to go back if we got an MSBA, we'd want to go back to the town essentially to have the town vote on whether or what.
Speaker 1 (36:09–38:06)
No, I don't think it'd be that it's probably something I want to reach out to town council Just so we have it, but I don't think it would be a reverter of, like, we're forgoing all that funding. I think for us, it becomes a decision point. Of, you know, we have the ability to have full funding, or we have the ability to go with and then. I think it falls on this committee's charge to kind of make that decision.
Obviously, it would be there's a lot of input we need from a lot of people. So I don't anticipate that. Like I said, my hopes of anticipation with MSBA is low, not just based on, you know, our history with them and everything. But if we did get it, it would be another thing on this project, kind of just another curveball we get thrown over the past couple of years.
So we'll see. But, you know, for that, so, you know, essentially, as Mark talked about, two articles. One for the design that would just take us through design development to go for a future funding article, funding warrant article, and funding townwide ballot. And then a separate one that would just be for the whole 173 million, similar to what we were planning on doing for So I just want to open that up to everybody.
And Mark, you've had your hand raised a couple of times, so I'm just going to jump on to Kerry first. She'd be good to do it.
Speaker 4 (38:07–38:40)
I keep raising my hand, too. I think that it's a brilliant idea to get that two Warren articles out there, one with the bigger number and then one with the more palatable number. I just I think the more we can get that number out into the public for them to view it and, you know, mull it over. Um, I think it, it would be wise, in my opinion, that's, I'm kind of in Mark's camp on this one.
Speaker 11 (38:42–38:53)
I think my only concern would be that it's still the select board's prerogative whether or not to allow a town vote on this at some point, right?
Speaker 1 (38:54–38:55)
Yeah, correct.
Speaker 11 (38:56–39:17)
So yeah, so my only thought related to that before you jump in was just maybe trying to resolve some of the questions they may have between now and December. December would be beneficial. So maybe the sooner we get the questions, the sooner we can answer them and prepare for a December article.
Speaker 1 (39:19–40:55)
Yeah, the part of the, some of the questions, for example, in regards to like the energy model and stuff like that, we definitely couldn't get that by December, just by the amount of work that has to go in by the consultants to do that. The intent would be is like whatever funding, whether it was be, you know, the 4 million that we're talking about or the full project funding, we wouldn't get any of that And then whenever that townwide ballot would occur, it would still be kind of the same start date to work towards that townwide ballot. It's just more of the town meeting member vote or the town. Yeah, sorry, and I'm thinking of, you know, I'm just trying to think of some of the hurdles, you know, and that's honestly why I wanted to have this meeting today.
We're still going to talk about this in two weeks, too. So, you know, there's no vote schedule for tonight. But, you know, for me, just knowing the rhythm of last year's town meeting, it's, you know, That answer your question Scott previously?
Speaker 11 (40:55–41:11)
I think so. I think. Like I said, the main thing I just want to make sure as we. We consider what the select board had brought up as part of putting that together and put some time in to answer some of their questions.
I think that will just help with the whole process.
Speaker 2 (41:15–41:18)
Yeah, John, you're recognized.
Speaker 5 (41:18–41:35)
I'm, I'm. I'm wondering if we hear about questions from the select board and I'm wondering what those are. Are you talking about the last select board meeting, the questions that came up?
Speaker 1 (41:36–42:20)
It's one of the to-do things I sent on the email. questions that came up from the select board during the last presentation that I was doing, or at least leading up to the vote. Kind of what we've been requesting is, For example, the get you to vote no, right? We're trying to change the no votes to a yes.
And there were concerns that people had when they voted no. So what we need is, you know, that entire list of what the questions and concerns are so that we can get the consultants working on it to get you the answers so that you can understand it. That's all.
Speaker 5 (42:21–42:29)
I just, I thought a lot of the questions weren't really directed to this committee, but more to the schools themselves.
Speaker 1 (42:32–44:36)
Either way, whatever the questions are that are causing a no vote, we need to resolve those. what that entire list of questions and answers that you guys on the select board are seeking. And then as we know what those questions are, we can answer them. You know what I mean?
My concern is always, you know, we hear a list of questions, we come back, we answer all the questions, and then there's another list of questions. And what we're trying to do is just get to a consolidated list of questions, concerns, present them to this committee, And if it's not us, it's the school committee or anybody else. And we can dive in and just, you know, the example I used, I was hearing is, you know, the cost of energy for the entire building. You know, what's the annual cost of energy that the building is going to use?
We can get there, but it takes a lot of design. As we mentioned at the last meeting, you know, as a HRS rater, John, you know, the thermal envelope of the building ties into that overall energy model. So we're not there with the schematic design. We can start making assumptions as we move into design development and start building an energy model based on the building and get those numbers.
you know, we need to know them. And school committee too. I know one was, there was before for operating for teachers and salaries and stuff like that. And I know Peter had put something together, you know, in preparation of the last meeting prior to the vote, that we had that.
So like, that's just an example of, you know, you guys have questions and that's totally fine. But, you know, we can get you the answers, but our goal at the end of this is to get everybody to a yes vote. overcrowding, everybody doesn't have to jump on Zoom calls anymore on Monday nights. You know what I mean?
And that's all we're trying to do.
Speaker 5 (44:37–44:38)
And I will work on that.
Speaker 1 (44:39–44:40)
OK, thank you.
Speaker 11 (44:42–44:57)
And Scott, you said you had a hand up and just didn't know. Yeah, no, you answered the question. I was just going to clarify what I meant before, but you nailed it. Thanks.
Yeah, no problem.
Speaker 1 (44:59–47:07)
So what I can do, like I said, I can talk with town council and see what the draft languages would be. I'm assuming, if any of you guys are looking for something similar, I would assume, look at what the debt exclusion vote was for the fire stations. I think it's probably the most recent one, just for kind of what the language would look like or something like that. And, you know, I can have that ready, essentially, for our next meeting, obviously distributed to everybody on the committee ahead of time, so you can kind of see what the language is within there.
But my goal is, you know, at our next meeting, which I believe is the 9th, the Monday after Labor Day, is to, you know, dive into this a little bit more. would be doing this is we would be drafting warrant articles and submitting them for recommendation, I believe, to the select board is the process by which we did them before. And then essentially the select board decides what goes on the warrant and what doesn't. I think that's correct.
If anybody knows differently, and nobody's correcting, so I guess that's a good thing. So any other questions or comments in regards to warrant articles or funding or anything like that? All right, hearing none. Old business, I think is just a placeholder, item five, that Shamus had on there.
As far as me, I don't really have anything for old business, so we're in good shape. And our last agenda item for the night is future meeting dates, which was Monday, September 9th. So just a reminder for everybody that we'll meet again on that night and kind of expand this discussion a little bit further. So with that, I'll entertain a motion to adjourn.
Speaker 2 (47:12–47:14)
So moved. Moved. All right.
Speaker 1 (47:14–47:26)
And so we'll do a roll call vote. I was trying to second, I was late. Okay, gotcha, appreciate it. All right, so yeah, roll call vote.
Scott Tereshak?
Speaker 2 (47:28–47:28)
Yes.
Speaker 1 (47:29–47:30)
Mark Loring?
Speaker 2 (47:30–47:30)
Yes.
Speaker 1 (47:32–47:33)
John Cohane?
Speaker 2 (47:34–47:34)
Yes.
Speaker 1 (47:35–47:39)
Carrie Hurley? Yes. Selena Miranda?
Speaker 3 (47:40–47:40)
Yes.
Speaker 2 (47:41–47:42)
Ankur Wadhwa?
Speaker 1 (47:43–47:48)
Yes. Glenn Hoffman? Yes. Tim Lombard?
Speaker 2 (47:49–47:49)
Yes.
Speaker 1 (47:50–47:57)
And I've realized I forgot to call myself for every roll call vote, so Shamus, if you'll give me a yes for all of them, please. I will. All right.
Speaker 2 (47:57–47:59)
Thank you all. Have a good night. See you in a couple of weeks.