Board: Milton School Building Committee
Date: 2024-06-10
Transcript
Auto-generated; may contain errors.
Speaker 1 (00:44–00:47)
Perfect, so it's now 703.
Speaker 2 (00:49–00:56)
I'll call the Town of Millburn School Building Committee meeting to order June 10th, 2024.
Speaker 3 (00:57–01:08)
As you typically do, we'll do a roll call attendance. Almost perfect timing. Again, ACWA is willing to attend and say if we should hold a public hearing.
Speaker 2 (01:08–01:11)
Linda Hoffman? Here. Selena Miranda?
Speaker 4 (01:11–01:13)
Here.
Speaker 2 (01:13–01:43)
Scott Tereshek? Present. ACWA Vaughan? Present.
John Tohane? Present. Carrie Hurley? Present.
Sean O'Keefe? Present. Second thing on the agenda is CitizenSpeak. the first 15 minutes of the meeting.
For any citizen that wants to speak, we ask that you just raise your hand and state your name and address. Just looking, there's nobody in attendance.
Speaker 3 (01:44–01:52)
And just keep an eye on that. The queue, just for a minute, see if anybody has questions.
Speaker 2 (01:54–02:14)
Seeing none, all right. Third thing on the agenda is approval of past meeting minutes, Monday, June 3rd, 2024. So everybody got a copy of their meeting packet from Seamus from PMA. So just see if there's any questions or comments in regards to the previous meeting minutes.
Speaker 5 (02:17–02:22)
Good job. So just need a motion to approve it in a second.
Speaker 6 (02:23–02:24)
So moved.
Speaker 2 (02:25–02:34)
Second by Scott. We're all in attendance so that nobody removes. We're not hybrid, so all those in favor. Aye.
Speaker 7 (02:35–02:37)
Aye. Aye. Aye. Aye.
Aye. Aye.
Speaker 2 (02:37–02:39)
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye.
Speaker 8 (02:40–02:42)
Aye. Aye. Aye. Aye.
Aye.
Speaker 2 (02:42–03:33)
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye. Aye.
Aye. Aye. Aye Two things we want to talk about first is review some of the site diagrams. If you guys recall, last time we met, we went over some of the block diagrams for rooms and quantities and stuff like that.
We've started putting massing together for them and assembling them on the site. We will see some options. Then after we go through the site options and stuff like that, Kate, I can't pronounce your last name, I apologize. Okay, thank you.
We'll be talking about some sustainability options. It's going to pair into our pricing exercise too. So. With that, Shannon, I'll turn it over to you guys.
Speaker 6 (03:33–03:35)
Thanks. Um, so.
Speaker 5 (03:37–03:39)
Hold on a second.
Speaker 3 (03:39–03:44)
I'm just going to.
Speaker 9 (03:54–03:57)
We've seen that on the screen.
Speaker 6 (04:10–04:51)
So we're going to talk through four options. The team's been taking all the information from the past visioning workshops and getting clarity, as we discussed last week, on the square footages and putting down some ideas on the site. And we've also included where there are opportunities for entrance and drive planes. And you start to see how the building lays out on the site.
So we have four options. We'll have an aerial plan, an adjacency diagram, and a massing diagram for each option.
Speaker 5 (04:53–12:34)
Let me just stand up here. So this first slide is sort of an overall illustrated plan of the property in question, and then also we wanted to show its proximity to Welton High School, existing athletic fields, and other existing roads. And as well, we wanted to show the land conservation area that's to be preserved, along with a 50-foot buffer and then an additional 50-foot zoning buffer and this southern property line. And we're going to basically zoom in to this area that's a little bit lighter in color.
That's sort of the site. And the following diagrams are going to kind of take us through that. So just to orient everybody, here's that athletic field again. This is the proposed new valve road.
This is that shape that we were just looking at, but it's larger now. This is a little bit of Milton High School here, and it's parking lot. And so we've got four options that we're going to look at, each one sort of contemplating a different way that the building, the middle school, the PK, and parking for each of them might play out on the site. And we have just on the upper left some sort of key attributes for each scheme and a parking count that the scheme kind of generates.
And to just kind of walk you through this first one, the idea here is that we're concentrating the core academic programs in a sort of a bar element that's justified for the athletics field side of the property. And what that does is that allows us space off of Gail Road to propose the middle school parking along with a pretty decent sized bus lane and car drop off. separate parking for the Pre-K and a separate loop for pickup and drop off for the Pre-K. In this scheme, the middle school entrance is considered to be here on the north side of the building, this red arrow, and the Pre-K entrance on the south side shown by this red arrow.
Altogether, this is showing about 142 parking spaces. Through the visioning, the Pre-K had asked for 50 parking spaces. And we don't have an official count that we need for the middle school yet, but the count of what's existing at Pierce is 111. And so we're targeting around 100.
We think that those should be, hopefully we can do with a few, somewhat fewer than what's at Pierce now. all of this will be further developed, you know, as things move forward. You'll see that the sort of shared public, the gym, auditorium, cafeteria, those types of programs are going to be located in the middle of the site. And this scheme looks at having the 3K as a part of the building and located on the first two floors on the south side of your second building.
So this is sort of a diagram of looking at the first floor. You'll see that we've got the sort of academic students with middle school located in this area, the entry administration in a sort of vertical circulation zone, sort of at the knuckle in the heart of everything, the pre-K in its own sort of wing on the south side, and then the common and public programs located over on the other side of the admin. So this allows those Statements can be used after hours, on the weekends, in the evening, kind of separated from the academic elements. So this is a 3D view.
I want to be clear that this is not yet sort of a proposed design for the building. It's really just about giving you all a sense of, given the number of rooms that we're working with, kind of how many floors we think we're working with and what that might start to feel like about the kind of general bulk and mass of the building. It's not a design myth. But just to orient you then, we've got Valero here with the middle school parking, and then the blue bar is the upper middle school academic classrooms.
The purple is the pre-K tucked in on the first two levels on the south side, and the sort of light orange color are the shared spaces. And one of the things that this one contemplates with the pre-K is that it gets its own entrance. And even though it's a part of this building, the idea is that it would really be experienced as its own kind of realm and have its own play area adjacent to it and could sort of function independently as one experiences it from the middle screen. And then the next slide is going to be a view of the same scheme, but from a different, so here's Bavaro on the bottom of the image looking back that way.
And so you can kind of imagine, you know, from the road, the parking set up and then this sort of level being the entry point for the middle school and these shared spaces. In this version, this bar is four stories, and then these spaces here are three stories. Anyone have any questions about this one before we move on to the next? The size that this is representing?
This is representing, this is working with approximately 169,000 gross square feet, which we talked about the last meeting. and we are in parallel working through some looking at scheduling and things to see about if there's more efficiencies that can be realized in bringing the bulk of the building down so much. So option two is Similarly, placing parking along Vial Road. What it's doing is taking the middle school and putting the academic elements in a bar shape that's sort of overlooking towards Vial Road.
It places the pre-K as a two-story volume that is adjacent to the middle school, but not physically connected. We imagine there could be a covered walkway between the two, but it's still primarily a separate structure. Again, you can see the sort of separate loop for the pre-paid drop-off and parking. And the parking count of this scheme is about 151 spaces.
This is 56, that's 95. There are some things that can be reworked here to, I think, get it a little bit more efficient, but you get the general idea. It's a similar amount of parking.
Speaker 10 (12:36–12:37)
Same gross curriculum?
Speaker 5 (12:37–13:33)
Yes. All four schemes are using the same amount. So just to kind of look at a first floor decency, again, entry to the middle school on the north side here, points by administration and a sort of vertical circulation that goes with classrooms continuing off in this bar and then stacking up, which you'll see in a moment. the common public spaces coming up behind that and sort of, again, out climbing the middle of the site for the gym, auditorium, dining service, and then the pre-K of the two-story building.
Here, one of the things that's nice about this, as opposed to the prior one, is that there's direct access to outdoor space without having to cross a road. That's one of the advantages of having put the parking here to the left, as you can imagine, going out into the service.
Speaker 11 (13:34–13:47)
But quickly, yes. What is the distance between the property line with the neighbors to the middle school, the upper from here to here?
Speaker 5 (13:47–16:48)
Yeah. I think about three feet. So in this version, again, this is Valvo here. So we've got a four-story volume there, and it's kind of stepping down as it, with the masses as you move north to south.
So this is a four-story volume, three-story, that's the gym and cafeteria programs. That's a two-story volume. And then the pre-K is a two-story volume as well. Okay, looking at it, I work on the bottom.
So yeah, this is the property line I'm talking about. The third option contemplates combining the parking into one centralized area that has a sort of a side that services pre-K and a side that's for the middle school. And you imagine that there's a sort of a loop that splits off for the pick up and drop off for the pre-K. But this is a that you look at what we put the middle school building so over to the road and they don't.
This is sure that the single story up in the next one will be as in a similar issue that the story of the potential for them. And so this locates our middle school academics in a bar that's sort of adjacent to Gile Road. And it puts the public spaces in this quadrant next to Gile Road as well. And let's go to the next one.
Sorry, I forgot to mention, this is about 158 market spaces as shown here. But here you can see academic and academic. The entry in this case on the south side of the building, a vertical circulation space and admin, something that, with the common public spaces located here. Pre-K is, again, shared.
And this is sort of an example of places that's the furthest from the middle school. So you can kind of see there's sort of an L shape of the academic spaces and then the shared items that are on a more public location on Broadway. So this is a four-story, three-story, two-story, and a one-story.
Speaker 9 (16:56–16:57)
Let's go in the other direction.
Speaker 5 (17:08–20:10)
The fourth option looks at putting all, locating all of the middle school academics in sort of a bent bar that follows Guile Road and locates the shared program spaces sort of cradled by that and more in the middle of the site. This one shows Pre-K, the two-story volume on the south side with a lot of extra space that you could imagine the potential to, in the future, potentially expand to the right, either with Pre-K or some other program. This is the same consolidated parking scenario as we saw in the prior one. One thing that's worth pointing out with this approach is that because the land is at its lowest elevation along Vial Road as compared to up by the athletic field, a four-story building that's pushed to this site, the top of that building would actually be potentially lower than the top of the four-story building that we saw in the first scheme that was sort of here next to this.
So in terms of thinking about the mass on the site and whether what's visible and what's not, this is sort of somewhat downhill from the options that have the mass up here. But here again, it's a south main entry for the middle school with a vertical circulation front side administration with the academic wings and the common public area. Which again, you can imagine pretty easily being used after hours and separated from those. This version looks like it's sort of a stepping option where we've got a four, then a three, then a ten story volume.
There's another version of this where, you know, it sort of pulls in a little bit and it's more of a consistent four-story volume with less of a footprint on the site. These are two-story, this is two-story here. So here you can imagine that you're coming up Bell Road, that there's the most kind of building present in Berks that it kind of starts to step down and become less imposing as you move up. So that's the – those are the four schemes that I went through kind of quickly, but I think it's useful to kind of just look at it at that level and see you know, broad brushstroke these ideas about where the bulk of the building is, where the access and parking is, and where the pre-K is relative to the building.
You know, is it close? Is it actually within it? Is it fully separate? So happy to go back through any of these with any questions.
Speaker 8 (20:13–20:20)
We all have the same square feet. Yes.
Speaker 5 (20:20–20:36)
More or less. Yeah, they're all hovering around 150 parking spaces. Some of the versions are a little bit less, but this is very early days in laying out the parking. So we think that we're able to meet the parking needs in each of them.
Speaker 6 (20:38–20:44)
In option three and four, how are we proposing to get the pre-K to the common facilities.
Speaker 5 (20:46–22:55)
So one of the things when we were doing the visioning was looking for synergies between pre-K and middle school, and the conclusion was that there's not a lot of obvious, like, yes, they have to be right there to use the gym. So the type of synergies that we talked about have been things like potentially the medical and nursing could be shared or at least kind of co-located with a the municipal side and the PK side. Potentially, there's some synergies with the administration that could be between them. But I think that, you know, feel free to jump in, but I think that the conclusion that we came to was that there wasn't like an obvious need for this to be directly adjacent.
One, you know, the lunch service will be prepared in middle school cafeterias. So that's one consideration about the lunch getting delivered. And so this is the furthest away. And is that a nuisance or not?
That's one of the reasons we looked at option two, where this was sort of close but not touching. Yeah, I think the interesting thing for me is, where is the parking in relation to the road and the building? This one is kind of interesting because it's in option three as well. You're essentially putting the parking behind.
So in some ways, the students looking out from the building are looking at the forest and fields beyond. It does have a little bit of operational. It really felt like that other approach. You could probably start to meld the two together.
And then the other versions are sort of coming in, and the parking is right there, option one and two. And that may be preferable, depending on how you see the sort of sense of that road. I had a few minutes extra to walk down there just this evening. It's, you know, a lovely forested space.
What can we turn that into?
Speaker 6 (22:56–23:49)
But then the other thing that came out of the workshops and last week's working group was whether or not the adjacency of the parking to Valero will support the athletics on the weekends with overflow parking. So I think, you know, they're each option has a different philosophical approach and I think what we're looking for today is for you to tell us this piece works and that piece works, or that one really doesn't work. And then we can take all the pieces and put them together in a way that we can summarize it and bring back refined options next week. I mean, if there's one option that you all love and get consensus, that would be fantastic, but we know it's a process.
But if everybody agrees that there's a preference for parking to be on Bell Road, we'd love to hear that. you know, as you're asking about preschool, like, do we need more of that feedback?
Speaker 5 (23:50–25:01)
I know it's early to tell, but do we know what the cost outset is for having it as a separate building as opposed to combined into one building? At the moment, we're sort of saying, what if it was cost neutral? And I think we have to kind of go back a little bit. How would you achieve that, though?
The question in my mind, at least, is the pre-K, a smaller building, maybe wood frame, maybe not wood frame, Certainly, you could have a lower floor-to-floor volume. Probably, depending on the building systems, they're getting more and more independent of each other. You know, the big central boiler is not part of the world. Heading forward in the electric, all-electric building, which we're sort of anticipating this will want to be.
So you may not have that. You may have some premium, but you may get some benefits. And so we're sort of at the moment, well, what if it's costing control? I say it because I think we need to sell it that way.
I think cost is going to be a big thing with this. As you know what all your projects are, right? In particular, Milton right now with the current political climate, I think we've got to be really conscious of being able to justify, all right, this is a separate bill and guess what? It costs the same and this is how.
Speaker 12 (25:01–25:16)
Yeah, you know, I was thinking the same thing. We already know there's opposition.
Speaker 5 (25:17–25:41)
We're already seeing it in social media. So I think we just want to make sure we have the answer ahead of time to the test. So when they say this is going to cost more, we can say, well, actually, no, it's not. It's going to cost the same.
And overall, the long haul is actually going to cost less because it's a more efficient system than we're putting in this building over here, which I'm sure you're already thinking of.
Speaker 13 (25:43–25:52)
Also, to the more than just perception, we should be trying to compare them. more economical approach.
Speaker 3 (25:54–26:07)
One of my things we looked at, the previous facilities director, Bill Ritchie, we looked at outside the high school doing modular construction to build some space out there.
Speaker 5 (26:08–26:16)
With a separate building like that, I don't know if you guys have experience with modular construction, be an option that we could look at for that?
Speaker 3 (26:16–26:22)
knowing that it's a smaller facility. That leads into a second question.
Speaker 5 (26:23–28:33)
So, two types of modulars. We have done pre-engineered buildings, which most people think of as Butler buildings, and fix those up in a way that supports a two-story building while saving money on the scale framing and the delivery. Actually, one of your projects you guys submitted on your proposal was a three-story building. Yeah, we could haul some up and show you that.
The other type is the wood boxes, like you see for construction. And those are coming in 60-foot lengths. And you can build them for a classroom and a hallway. And then you put two together, and then you build a whole classroom and a half classroom in each box.
And then you stack them up. We haven't seen the, well, the last time we looked at it was a while ago. We didn't see the economics of that playing out well. But it doesn't mean we couldn't look at it.
You would end up driving a bunch of boxes up, sticking them in place, and then putting a shell around it. And usually they come pretty finished up. The industry is pretty good for apartments. It's a little less developed for schools.
And then the other tricky part is making sure that you're not getting stuck behind somebody in the fabrication process. So you're sort of dealing with the builder, and as long as they can keep your schedule open, you're good. And if they get all behind because of their issues, then you become stuck. You can't bring out a different crew and start working.
So each has its little advantages. We could show you some examples of each, I think, but a finer point. I was certainly expecting we would do some cost, preliminary costing, because I agree with you guys both. You can't just say, oh, it's cost neutral and hope for the best.
But we also think operationally and for other reasons may drive the discussion more so than necessarily a little more or a little less. So the next one I hadn't shown, not less than this one.
Speaker 2 (28:34–29:14)
The question I have is, if you could do something that's modular or something like that, faster construction, do we split this in two? I don't want to do two projects funding-wise, but construction-wise, since you get the preschool operational first, quicker. You know what I mean? And it fades it that way.
So we've got to pre-school up. We can free up space sooner in schools while we build the bigger building. It might take longer time. So not that we have to answer that, but it's just when I see big buildings, it presents an opportunity that we may be able to do one much faster, get it open, get it going, address some of the needs we have right now while we're working on the bigger building.
Speaker 5 (29:14–29:26)
Sure. Yeah, no, I think the main question starting in my mind for that is, How do you separate the two? So you're leaving enough space for the contractor to be doing the big construction work. Sean will figure all that out.
Speaker 4 (29:27–29:28)
At least Sean got Sean.
Speaker 6 (29:29–29:37)
So would you have them deliver the food from the high school to the rehab building?
Speaker 3 (29:37–29:43)
So I'm looking at school committee members for preschool. Have they provided lunch?
Speaker 11 (29:43–29:50)
There are some. Most preschools I have worked with are full-day preschools.
Speaker 2 (29:50–29:54)
But most of the half-day ones, they bring their own lunch. They eat in their own space.
Speaker 11 (29:55–30:10)
I'm just saying the fast track one.
Speaker 6 (30:10–30:18)
I mean, I love that idea, but there's the operational piece to it.
Speaker 3 (30:18–30:28)
The other one, you guys also just talk about, like, we're talking overall square footage. Can you keep the breakdown between the middle school square footage and the preschool square footage, because we're talking in total?
Speaker 6 (30:29–30:49)
Yeah, so the middle school square footage is 141G, so we'll just say 142, right? And then the remaining of that 169 is preschool, so 28,000 square feet. And that's, both of those are gross square footages for the totals.
Speaker 5 (30:52–31:10)
Back up to a different question for a second. Just helps out with the merits of having a separate pre-K versus combining with the middle school. three of the four options show are separate, so it seems like you favor that, just like to understand the block.
Speaker 11 (31:12–31:28)
I can share from like whatever from Bernadette, which is a preference to having Separate having more separation between the kids, right? Being able to create their own school environment, right? As it were, solutions in both long areas for the little kids, right?
Speaker 5 (31:28–31:35)
And basically being able to create their own separate and small environments rather than being kind of just a core within.
Speaker 11 (31:35–33:10)
the primarily facilities and so just creating a little bit more separation. I heard at least once. Yeah, that would make more preferential while still having some connection. I think the other piece of my mind is I think about the the separate building and the space next to it, as it's shown here, is, you know, the idea of trying to future-proof this project.
I think this project future-proofs our elementary school really well by pulling out pre-K and mid-grade, and it helps Pierce really well by pulling out sixth grade out of Pierce, right? The one piece is the preschool, right? If preschool expands to full-day preschool in the future, the amount of space the building right now is not sufficient. And it's my understanding, at least, if you might correct me.
And so being able to ensure that we have the ability, the talent and desire to move to a full-day pre-K, as many places are, to be able to expand that programming fairly easily and as least disruptive as a manner as possible by just adding on to the side of kind of in the space that is already available for that that's me as I look at this is. very attractive to make sure that while that's not in the next 3-year plan or anything, we don't want to be back in this spot where essentially we built a pre-K, we've already grown outside of it, and now we've got to build a new pre-K building somewhere else.
Speaker 8 (33:10–33:18)
I was thinking that the same thing, that options 3 and 4 seem a lot more attractive from that perspective.
Speaker 5 (33:21–35:13)
Of course, I've got to contradict you guys right now. I like option 2. I like that you separate the parking. I don't like the shopping mall feeling of having all the parking central on the site.
And I think after listening to you, I like it as a separate building. However, I think I like the proximity of this building to the main building. Because I think there will be times, right? There's not going to be a gym in the pre-K building.
There'll be times they want to use the gym more. And I don't know if we'll actually be able to sell by the bridge idea, but I love that you're thinking that. Even if it's not an actual bridge, it'll be kind of a covered walkway. But even as a metaphor, just connecting the two schools, I like the idea of it.
And I see what you're saying about three and four, too. But those are very specific reasons I like this one. And I think functionally, with having Having coached several sports in this town, parking is always an issue outside of school activities. And I think it actually might help having them separate.
Because there are times when you've got a baseball tournament and a dance recital going on at the same time. So it might be nice to have them not always on top of each other. Just this evening, they're all stacked up on the roof. Yeah, exactly.
I mean, they're all very… Nothing going on. All four versions, I think, I'm impressed by all four versions. And I think the masking helps.
Big time. And I like that you're not thinking of this building as a box. I like that you're talking about the stepping. It seems like there's a lot of thought being put into the design already, even though we haven't really started to truly dig into the design.
But that's all. That's my two cents.
Speaker 8 (35:17–35:21)
In terms of blocks, which of these buildings did you expect?
Speaker 14 (35:28–35:41)
would the pre-K look more nice compared to middle school? Is that anything, or would they just be making money? Is the distance even enough?
Speaker 5 (35:41–35:56)
Are you thinking of the students, or are you thinking of the government? I'm thinking of the government. Yes, the government means to us. They'll be happy to be here, I assume.
Speaker 8 (35:57–36:03)
moving the noisy earthquake away from them as far as possible.
Speaker 5 (36:03–36:32)
There are students and those in there. Yeah, it was kind of interesting, the option three, I think, where in some ways we're trying to use the pre-K as a little bit of a buffer between the two. And if you think of the sort of back of the building facing them, you know, it's a little cleaner than, oh, we've got a big parking lot or a driveway or a parking area.
Speaker 6 (36:33–37:21)
But… I think also if you go to one of the plan options, there's a 100-foot buffer between the property line and the back side of the building. That's just the property line and the back side. I don't remember how far the houses are from the property line, but that's only going to be landscapes with trees and trees.
have a dense protective layer that we're not seeing on the plan. We haven't developed the landscape or what the tree layouts are, but we're anticipating that zone is going to be fairly dense with those trees and bushes. It's going to help mitigate any transference of sound. I think the houses themselves individually are, you know, much further south as well, but distance gives you additional protection.
Speaker 11 (37:22–37:56)
I think the other piece is just from a, the only other option would be the middle school buildings down there, but then from a massive force force building. hundred feet, which is much different than a four-story building that's 600 feet away. And so I think that it probably would be quieter to just have the back of a four-story building there and almost use that as the buffer, but you know, three school kids running around playing on that play structure. It's not going to be silent, but I think from a visual standpoint, that's going to, I think, would be way worse for the
Speaker 9 (37:57–37:59)
Construction noise too.
Speaker 7 (37:59–38:08)
If you build on that side, it's going to get loud.
Speaker 6 (38:09–38:11)
Do they complain about the noise from the games?
Speaker 5 (38:11–38:16)
There are people that do, but it's usually five games a year meeting, so it's pretty
Speaker 9 (38:17–38:19)
Five, four or five Friday night games.
Speaker 6 (38:19–38:50)
So it's really not to do that. It didn't come up during the conversations either. It really was more the concern than what it was. But I think also the way you have the playground there, it feels like it's still removed from or further from the residency.
And I think it's a good question. I think it depends on the time of day. So it's the play time for the little ones when they go out. But the good thing is that they don't all go out together at the same time.
So that would, I think that's the most important thing.
Speaker 12 (38:51–38:58)
And then it's release time. That's when we, that's all night. So morning time, the middle school kids come. I'm right there with the middle schoolers.
It's when I hear them.
Speaker 6 (38:59–39:01)
Right?
Speaker 5 (39:01–39:34)
So they would get more volume. You know, I think you're sort of interesting because there's cars and parking near and I think just how we screen that would be. In terms of building massing it's relatively small, but the building oriented to the north and south.
Speaker 12 (39:34–39:44)
What about traffic consideration? That's not being a massive parking lot versus two separate ones.
Speaker 5 (39:44–39:59)
That's an interesting question. There's a little more efficient. Sort of the parking along the road is sort of wrapping itself around the curve there. A little less efficient, although we may be able to just keep working on it and see where we come up on.
Speaker 3 (40:00–40:04)
The one thing to open up to is scheduling schedules.
Speaker 5 (40:06–40:12)
middle school schedule, half day, morning, half day, afternoon schedule.
Speaker 2 (40:12–40:21)
So as we start engaging with traffic consultants and stuff like that, that's all the inputs that they'll be pulling in.
Speaker 6 (40:21–40:30)
What about the environmental impact of having that big massive parking in the middle as opposed to breaking it up and having green space in between? Is there any thought about that?
Speaker 12 (40:33–41:07)
I mean, they're breaking it up, but it's still within my discretion. I don't know whether it's possible. It's expensive and concrete. So that is sort of creating some islands.
I let them out. I'm ready to do something about separating it. Maybe there's a little less road. I'm not quite sure.
You have to kind of look at the plan. I mean, ideally there would be, and I think you kind of showed that a little bit on the one with the centralized, you would have some green in that.
Speaker 10 (41:09–41:17)
So really, I mean, is that part of the environmental analysis that they make, that they make now porous materials that can
Speaker 11 (41:17–41:21)
Maintain force payments long term.
Speaker 12 (41:21–42:04)
Yeah, they start to look at the storm water. Like, that's the thing for footage. So, it's not why do we have this much over here and not over there? I think you kind of showing that there were planted islands.
in every row. And so, I think we would kind of do that regardless of where the seating is. So, I wouldn't say there's a real noticeable difference between the two. It might be different in terms of like, there's something mentioned with like, what are you looking out on?
You're obviously looking on parking from one side of the building, and all of them live in that green space on all of them.
Speaker 8 (42:05–42:05)
So,
Speaker 12 (42:06–42:23)
If you look at the shape of that parking, it's pretty efficient.
Speaker 5 (42:25–43:00)
But I appreciate your comment of, you know, does that start to feel like a job? And that's the difference. You know, for me, it was interesting to see the buildings start to fall down, rather than the students are looking down at the wetlands from one side of the building to the other side of the building. I don't know if you've ever seen that before.
I've actually seen, with the one-to-one with Guya Road, seen more traffic-wise. I don't know if it's as efficient as far as one of these spots you get. But traffic-wise, the way people typically drive around the high school, that would work really well. The option two, you're saying?
Yeah.
Speaker 8 (43:01–43:29)
So that's one way in, one way out, right?
Speaker 5 (43:29–44:50)
And I like having a parking closer to the field, which I think would be convenient for them. I don't have to park on the grass either anymore? I'm guessing people will. People park everywhere.
I would not charge people to park all over. Wherever they can fit their car, they'll put it. some interesting bargaining strategies. Keeping the pre-K away from the middle school drop-off too is sometimes helpful where the parents are going different directions and the classes are being separated and it's a little less chaotic on either end.
I know we're going to split the time. Yeah, but there's still going to be a little bit of overlap. It was interesting that they're actually operating that as a drop-off as opposed to some of the pre-Ks we work with, the parents. Caregivers stop, get out of the car, walk the child in, and get back in.
So it's more of a parking lot approach. And something like this, you could probably manage it both ways if there was some reason they decided to change operations. You could still have these parents or caregivers come in, park the car, walk the kid in, and come out again, or scoot through. Have them come out of the car.
Speaker 6 (44:51–44:58)
I also think having the smaller part of the building on the edge that's facing Home Inc. might be appealing as well.
Speaker 4 (44:58–44:58)
Yeah.
Speaker 6 (45:03–45:07)
Is it one story, two stories? I can't remember. It's the 3K here, two stories?
Speaker 4 (45:07–45:07)
Yeah.
Speaker 8 (45:15–45:16)
Yeah.
Speaker 6 (45:17–45:22)
Just feel the impact from the neighbors. No, it's not looking at it that way.
Speaker 5 (45:22–45:38)
The way it winds up right now, it's perfectly aligned with the middle school, but it doesn't really give you a great opportunity for expansion.
Speaker 14 (45:38–45:40)
We could fill up with that.
Speaker 5 (45:41–46:04)
A fair amount of space right now in front of the building. Probably too much. You need your point stop not aligning with the corner of the building, just shift it up. The other thing we're trying to chase down is whether we actually need this road going around the back of the building.
Speaker 6 (46:05–47:03)
Yeah, I did get a lot more information from Paul today. We haven't been able to analyze it and really integrate it, but there are dimensional requirements for how far the fire hose on the truck can go, so you can stop the truck on pavement and extend the fire hose a certain amount of distance. And based on that, there may be opportunities to trim back that row that goes along the field so that there's no paving back there. But we really need to get into a much deeper dimensional analysis to make sure it works.
Because when you do something like that, you need to make sure that the fire truck can either reverse back out or turn around. So there are other constraints that We're optimistic that we'll be able to cut some of that roadway cleaning out, but we just need to get to a deeper study to confirm that it happened. So we're taking the conservative view right now.
Speaker 5 (47:03–47:13)
In that situation, though, would you need to move the finger of no longer at the classroom when you could be there and instead use the auditorium or gym to be along that line?
Speaker 11 (47:14–47:28)
Because essentially, you're going to use the building as above a retaining wall, right? It means that you're really not going to have windows. You're going to have windows. I'm not holding all that stuff back.
Speaker 6 (47:28–47:35)
All right, I see what you're saying. I understand what you're saying. I think, did you want to take it?
Speaker 4 (47:35–47:39)
Like, I have different ideas than you.
Speaker 6 (47:40–48:14)
I think, you know, while a rotating wall is not definitive or not, but once we start looking at it sectionally, it might there might be a reason to have it anyway to give some outdoor, flattened outdoor space for middle school students or, you know, other opportunities for outdoor classrooms. Like, we haven't gotten to that level, so it would be nice to not have the expense of a retaining wall. But there may be other reasons, despite not having a road, to have it as well. I'm trying to keep my options open.
Speaker 11 (48:14–48:16)
Yeah, so not having the road actually
Speaker 6 (48:16–49:47)
Potentially, but you know, right now, one of the next levels to understand what kind of outdoor spaces we have and how does that benefit the middle school students. Like there's a prescribed amount of outdoor square footage for the pre-K for what happens within the school. So I think that's just the next level of investigation. So we do have a traffic consultant who's doing the current analysis of the existing traffic flows that will help feed into what will happen when We put a building on the site and how did that change things?
So he's writing that report and we should be getting that information soon. And then once we decide on one plan, one option. He'll look at that more deeply to understand how the existing traffic flow will change with the new building. And then, you know, we do have a link, but again, once you get to one option, we'll be engaging with all these people to look at these deeper dives.
Do you know what the gross square footage of Pierce is? 152,000 square feet plus.
Speaker 5 (49:48–50:11)
So when you look at the square footage, we'll be providing it here as we pull the sixth grade out of, as we pull a grade out of there. We'll have a school, right sides, for two grade levels there. And we're doing a similar school here.
Speaker 2 (50:11–50:16)
Similar size actually a little bit smaller when we measure everything and stuff like that.
Speaker 5 (50:16–51:35)
So that was one of the things we've been looking at, too, is as an apples to apples comparison of how big would this building be when we're meeting with the district and talking to teachers that may not understand how big it is from here, but we're trying to give them some visual metrics that they can kind of understand the space and stuff like that. Yeah, I've been out of the game a while, but I know when I was still going to school, we came up with some funky ways to do fire access roads. I know in Dover, we were able to put one in without having it paved, and you had to go back. Yeah, you need to be structured.
Yeah, but it gets expensive, right? It's pricey if you do that. It's tricky. It's tricky.
We'd much rather say, OK, this overhead had a lot of money. That's the thing is, a lot of these things are so non-heavy that the pump drops are full of water. But you're right. Functionally, it might make sense to just have it be a paved road.
Again, the biggest thing is the space that goes through there and whatever. I forgot, how wide do they have to be? Right now, we're showing 20 feet. 20 feet?
Is that so? Maybe we can probably skinny that down if it was a one way just fire.
Speaker 3 (51:35–51:35)
Right.
Speaker 5 (51:37–51:49)
The big one when I look at it is that bottom turn. It's a 90 degree angle. Well, he nailed it. Make it fire access only.
Which one?
Speaker 6 (51:49–51:54)
The 90 degree. Oh, that one.
Speaker 4 (51:54–51:54)
Yeah.
Speaker 2 (51:55–51:59)
Yeah. But I know we'll get there on that.
Speaker 5 (51:59–54:30)
I'm trying not to. I think people always find the shortest path, whether you create the path for them or not. So for that lower area of parking in the southwest, when people park there, they go up to the main field. you know, if that road's not there, they're going to create a path.
So, you know, maybe we think about if it's not there, maybe there's a stair that goes up and connects to the field and a way to get to the high school. Just some connectivity on that back side so we're not forcing people to try to walk around onto Guided Road. We talked about that on Scheme 1, whether, we talked about on Scheme 1, whether you could have a connection through the building or from the middle school out on to the upper level of the field. Well, yeah, they wouldn't have to go to the field.
If you could walk around, it could be a walking path outside, isn't it? They collect money, so you don't have to walk around to get to the football. for a football game anyway, or soccer, whatever. Just from a study I've seen, they prefer to have everyone coming in through the entrance that everybody uses right now.
The bathrooms are, it's controlled, so you don't have people wandering out into the woods from the other side, since everyone goes in that same way. We haven't explored too much the idea that the middle school kids are only walking to the high school or vice versa. That's probably something that we can look at at the various schemes. Yeah, if you look at it, unless you're cutting across the field, it's either way, it's about this, yeah, I don't think one way or the other safety on the distance from the circulation standpoint.
So we talked at one point about building an access road around the back corner of the field. So from the pre-K side in this scenario, it would be slightly closer, but you just have to see if that would be worth the expense and the effort to put a path around the other side of the field. The distance you're saving isn't all that much. You have that nice shrubbery that says Milton.
Speaker 11 (54:30–54:40)
I mean, at this point, if you like to disconnect in pre-K, this almost seems easy enough to do the top of the pre-K lane. Off lane, take it down.
Speaker 9 (54:40–54:44)
Well, there's middle school program above that.
Speaker 11 (54:44–54:50)
Yeah, that's right. You're right.
Speaker 8 (54:50–54:56)
Option two is the one that's disconnected.
Speaker 5 (54:56–55:02)
Yes. In the other building, the footprint is bigger because you're not stacked on top of each other.
Speaker 6 (55:03–55:07)
Oh, we can do that. We know with option two, it's not. We can do that.
Speaker 5 (55:10–56:06)
Yeah, the piece along Galloway is pretty simple. One thing we've got to figure out is where we can get buses stacked up as well as some amount of cars. We're not taking up too much space for all that activity. Other interesting That sounds like folks like this version.
Should we keep going with option one where it's at least part of the building? So we say we're going to tease those two out a little further. And we'll see if we can help to put some brackets around some pricing.
Speaker 12 (56:08–56:36)
And did I hear you say that you would try to look at option two? We'll see if we could. Thinking about the future and expansion. Okay.
I think as long as we're thinking about that. I think the important as we go to, chances are we would move to an all day eventually. And that would mean that we wouldn't fit there anymore.
Speaker 5 (56:37–56:40)
Yeah, we can look at a couple different ways to explain that.
Speaker 9 (56:42–56:44)
We could design it to go up, too.
Speaker 4 (56:44–56:48)
Yeah, we could design it to go up a bit. I know.
Speaker 5 (56:48–56:56)
It's not as easy as it sounds, but it's not cheap at all. Because you're going to design your steel, but still, you're going to design your steel now.
Speaker 11 (56:56–57:10)
It's just, it's very hard. You can't really operate the school building below it while you're building above it. It'd be difficult. The amount of sound, you know, and the amount of kids virtually doing it.
Speaker 5 (57:10–57:14)
And some in hospitals and stuff, and in school, it'd be very difficult.
Speaker 8 (57:14–57:18)
It's going to happen in the summer.
Speaker 11 (57:18–57:27)
There are.
Speaker 5 (57:27–57:52)
There are. and your first level, your first occupiable level.
Speaker 6 (57:53–57:57)
Oh, so it's a second floor. So it's a second floor.
Speaker 11 (57:58–58:01)
I'm just saying, like, I'm not proposing we ever do that.
Speaker 5 (58:01–58:11)
I'm just saying, to the extent one day they're looking for space to expand the pre-K, we gave a thought, and we provided space. They're still hiring, and it's worth it.
Speaker 9 (58:12–58:14)
I understand what you're saying. We don't think of this as a rectangle, too.
Speaker 5 (58:14–58:28)
This is expandable as is. Right. We don't have we don't have to make it a bowling alley. It's an expansion.
We could actually build off the edges, make it a U shape or an H shape. And that might actually be more interesting.
Speaker 9 (58:29–58:31)
Right. Yeah.
Speaker 5 (58:31–58:49)
You don't want to create a barrack, you know, when we expand it later. Didn't grab what I wanted. My shortcuts are not working.
Speaker 3 (58:50–58:57)
He's doing something like that.
Speaker 5 (58:57–59:00)
Yeah, no, the future expansions.
Speaker 3 (59:01–59:05)
I love Bluebeam. Bluebeam's the best invention ever.
Speaker 5 (59:05–59:11)
Yeah, yeah. That's the one I was thinking of.
Speaker 11 (59:11–59:18)
Yeah, that's a much more interesting expansion, I think.
Speaker 2 (59:20–59:32)
That actually mimics the early childhood education center that we looked at one time. It was the one that was there.
Speaker 4 (59:33–59:37)
So yeah, I think there's a lot of options there.
Speaker 11 (59:44–01:00:09)
Yeah, I just made my, I don't know if you can hear me or not, but I do worry about outdoor space a little bit. At this point, within any of them, we have outdoor space in the Pre-K, and I don't see any way to gain a significant amount of outdoor activity space for different institutions without utilizing it.
Speaker 7 (01:00:09–01:00:11)
Or a conference, yeah.
Speaker 11 (01:00:11–01:00:13)
They need to go up to the lower aisles.
Speaker 5 (01:00:15–01:00:23)
I don't think anyone's going to be using lower guile.
Speaker 9 (01:00:23–01:00:34)
It's in pretty rough shape. There's a lot of holes in it. It's just not safe right now.
Speaker 5 (01:00:34–01:00:40)
That's the one in the upper part.
Speaker 9 (01:00:41–01:00:43)
Yeah, down in the tail, lower guile.
Speaker 5 (01:00:44–01:01:00)
Hm. It's interesting, though, if you said, and who knows what improvements happen there, but would that be a space that you could put it for the middle school? Absolutely. In which case, people think about it.
Speaker 9 (01:01:00–01:01:06)
If the improvements go forward, it'll probably get used by the high school and the middle school, I would imagine.
Speaker 3 (01:01:06–01:01:17)
The current plan is to put a turf field up there. So there's been some controversy back and forth So it's up in the air right now.
Speaker 5 (01:01:17–01:02:05)
Sure. It's with the EP currency. OK. OK.
OK, so it sounds like folks like option two. We're going to keep option one going. So we're saying we're pursuing two of them. and we'll bring back some more.
Any other questions, comments before we move on?
Speaker 7 (01:02:05–01:02:10)
Thank you.
Speaker 12 (01:02:10–01:04:41)
We're going to talk about sort of very high level, but lots of little things. Please ask me questions in a word or abbreviation or something that you want to talk to me about. We're going to start here with kind of like, what are the basic requirements? What goes in RFS?
What are we responding to? Talk a little bit about what else you're interested in studying further. I kind of put some things here, but we're going to hear from you. So, basic requirements.
The project's going to meet the specialized energy code, so the stretch code plus the specialized energy code, and it's going to be LEED certified. what level of certification was specified in the RFL. So what I've kind of put under the study further is essentially talking about, is there an interest to go, based on the location of the site, the project would probably be, you know, there's not a lot of public transportation and things like that where you get a lot of points. And so the project is probably hovering right around Leeds Silver, just as basic design and the way we design.
Maybe I mean the industry, not just Aerospray. I would say it's probably silver is a very doable gold. I think you could easily get there even though you'd be changing the design or necessarily adding the process to do that. But if you wanted to talk about lead gold or something beyond that, I don't think the project would be able to get the lead platinum.
And again, it's just the location limits you from getting credits and points that just you can't get. once you change your whole city or your whole town, that's not going to be a big goal. It's something to talk about if you're interested in that. So really today I wanted to see is there things that you were thinking about in terms of sustainability that you wanted to explore, something that you're interested in that you might want to study further or aspire to, the other way to sort of think about that.
You know, I think that's a little bit more of a net zero ready building if you want to think about it that way. But it's not necessarily a net zero building. On the lead side, we could strive for something more if there's a particular desire to go beyond and explore.
Speaker 5 (01:04:42–01:05:17)
It would be an opportunity with a separate You could really do something. Maybe you could do it next year. It's a small building. You want to crush our budget.
It's something to think about. Yeah, if we had that as a separate building, I feel like we could do something special with that building. from a sustainability standpoint that might not be feasible on the larger school building, you know? I mean, it's gonna cost a lot of money, like she said.
You're not gonna get a platform if you can't. And even gold is probably a way to cost some money.
Speaker 2 (01:05:17–01:05:22)
Yeah, but if we can frame the conversation right now, it's around the certification. You know what I mean?
Speaker 5 (01:05:22–01:05:39)
Is that something you feel strongly about that you want to go after and obtain, or just use it as a guideline to go out there and set up another world certification similar to what you talked about before, you know, paying extra money just to get a platinum award. I've done that.
Speaker 11 (01:05:40–01:05:44)
I've done a lead silver building that didn't get certified just because we didn't track it.
Speaker 5 (01:05:44–01:06:10)
Well, even the certification itself, it's basically a checklist that you get points for doing certain things and maybe a certain amount of points for silver, next level is gold and platinum. So part of the question is, are you, this community and this committee, do they want that lead certification on the building or Do you want Arrow Street to guide you to efficient buildings, sustainable building, and not necessarily care so much about the LEED plaque that goes on the front of it?
Speaker 8 (01:06:10–01:06:17)
What's the pros and cons?
Speaker 12 (01:06:17–01:07:29)
The way that we think about this, if you want a LEED-certified building, we're basically giving you a building that you could go and pay the third party to certify, and that cost is going to be somewhere in between. It's probably going to be somewhere around $10,000. So it's relatively small amount compared to construction profit or cost. Because our process would be the same.
If you want it to be designed to lead, we would need to do the calculations and the modeling and we'd also have the contractor making sure that they're tracking and putting the right building materials and materials and they're going to support the air quality. So in terms of our process, there's a little bit of cost savings on what I would call sort of a soft top with like the design team and the contractor, but there's not a significant amount of cost there. If you wanted to say that it was designed, it would be because we take that seriously and we do the basically track that out, do the calculations, making sure that it could be the certification fee, but you don't have to do the certification fee.
Speaker 14 (01:07:29–01:07:30)
But once we get the certification
Speaker 12 (01:07:32–01:08:29)
Yeah, I mean, if you think about other schools, you know, every school that does go through the MSBA process, all of those schools are required to use silver, so there is some comparison, you know, there is that piece of if this is what other new schools are doing, that's something to potentially consider. I don't know whether staff and staff retention, if they're looking for that, or if that's something that they would look at. But that would be the only other thing to kind of think about what are other new schools doing in the city. And through that project, they do process around the city of Silver.
And I would say that we're not public charter school, we're not typically going after lead certification, but other public schools that are not on the MBA, I would say the majority of them, we do, are also following lead. We do do the certification.
Speaker 5 (01:08:30–01:08:40)
Where does the specialized code compare to LEED? Do you hit that code automatically, or is there a level of LEED, or is there still more that needs to be done to be certifiable?
Speaker 12 (01:08:40–01:09:01)
So, I mean, the energy code is just looking at the energy piece, which is a lot of points, and we need to not forget that the project would pretty much be LEED silver. just by reading the code, reading the other ventilation and indoor air quality statistics that are put in the state, and just sort of the basic services of what you're sending to us.
Speaker 5 (01:09:01–01:09:21)
Because I think the other communities don't have specialized, I think there's only like 45 or something in the state right now that have adopted the specialized code. So Milton is requiring, we're requiring ourselves to be better or more energy efficient than a lot of the other towns, where I think some of the other towns are going to go to the LEED because they don't have that specialized code. That is a minimum probably requirement.
Speaker 12 (01:09:21–01:09:49)
Yeah, the energy leadings are actually all in the stretch code. So that's actually giving us at least points, you know, that are related to energy. The specialized code is not. Giving you much more clearly and then if we're.
It's a, it's a school project, but we're going to be a, they actually get 3% additional reimbursement if they do a specialized. So, I think you'll see more.
Speaker 3 (01:09:50–01:10:01)
We need to frame it to a specialized purpose there. You know, there's the option that we can bring fossil fuel into the site, build out the building with fossil fuels.
Speaker 5 (01:10:01–01:10:18)
We just have to parallel the electric design, build it out, so if they want to go electric in the future, they can do that. However, once we spend all that infrastructure, they probably just don't want to go electric for everything, not double up. um, you know, piping and stuff like that for fossil fuels.
Speaker 3 (01:10:18–01:10:36)
So that's, that's the, the one thing I see, you know, what we're doing this discussion when we talk about specialized codes and stuff like that, you know, for the size of the building, we wanted to go with the fossil fuel base and heating, cooling systems, stuff like that.
Speaker 5 (01:10:37–01:10:51)
Um, and the electrical with it. So, you know, for that it's easier just to do the electrical bypass then. I think that's basically what you'll recommend too, is an all-electric building.
Speaker 12 (01:10:52–01:11:33)
And, you know, the lead piece here is not, you know, we're early in the process. We can kind of tease this out with the project. It's just good for us to know whether you're thinking of going, you know, beyond, are you definitely going to need And if so, are you thinking of going beyond? There's not a kind of cost difference between silver and gold, but it is something we'll want to vet out and make sure that's the most effective thing.
It's not your big cost, right? Because with HVAC systems, you're going to select that regardless of the certification. That's really driven by growth. So there is some cost there, but we would do that if we're interested in potentially understanding what that would be.
Speaker 5 (01:11:34–01:11:54)
typically would sort of lead projects that have been involved in. You know, you get the checklist to run down. There's definite yeses, there's definite noes. Like you were saying, certain things we're not going to qualify for.
And then for this committee, we basically look at the maybes and try to figure out which ones we move over each time.
Speaker 14 (01:11:54–01:12:04)
I'd be interested in seeing what it takes to get the goal. I mean, it might be As we go through the process, we might find it's almost nothing to get to that level.
Speaker 5 (01:12:05–01:12:51)
I'm not sure I'm convinced I would want to go for certification with LEED, per se. There are several buildings where we design to a certain level of LEED, but we don't go for the certification, so we don't add the layers of cost to them or the contractors. Well, doesn't mean you can't say we designed and built this to a legal level. You don't have to apply for the certification, but you can still advertise that it's what we designed it to and built it to.
Yeah, right. I think it's a good list of criteria that we, you know, it's giving you a healthier medical community. like to see how close we are to it. It might not be much to achieve it.
Speaker 11 (01:12:51–01:13:08)
Given the specialized code and I guess a point Sean made about essentially incentivizing all electric buildings and the state's 2050 net zero goal, what ideas are you setting in creation of a net zero building?
Speaker 5 (01:13:09–01:13:30)
Potentially control cost implications of net zero. curious on that last one too, like what else could we aspire to other than meteorites?
Speaker 4 (01:13:30–01:13:31)
There we go.
Speaker 5 (01:13:31–01:14:03)
I recently worked on a living building, a genomic building, which seems to be restored in the environment that it's built in, not just west of that environment, but east. less impactful, net zero, or if we're trying to generate some amount of energy to do a living building challenge, building, restoring any assets in the environment we need to build. So I think that that would be tremendously cost prohibitive.
Speaker 7 (01:14:03–01:14:11)
But it does, of course, which I've been talking about getting certification for.
Speaker 12 (01:14:15–01:15:57)
Yes, that is, that is something that would kind of fall on that fire to you go all the way to the challenge, it could be, you know, something in between. We've had projects that are really not only an energy, but water, sometimes that's driven by the location that they are in the stormwater system that they're tied into or the water supply system, sometimes it's just something that they're very interested in that isn't driven by that. And so that's another piece, you could go to that zero water, it could be a focus on your own, we're already getting, if we're talking about weed and just in general the way that Air Street designs their projects, health and wellness are big components to them. But if you were really wanting to go further with that, you could look at a well certification, which again is like me, but it's focused on health and wellness.
And so those would be some of those well health and wellness. There was something very specific that he said, we're really concerned about this particular piece. We really want to make sure that it's woven through the project, but that's what they aspire to be. could be.
It doesn't have to be a certification. It could just be, you know, like we really want to focus on water. So whether it's part of me or something else, you know, it might be. Kate, the one that we're- Not that you're not being aspirational about it, but it's really great for us to say that too, right?
These are really high standards to begin with, and so it's really like if there is something specific that you thought was important to your community that you did not have to feel like- not everyone has that sort of extra power in the field.
Speaker 5 (01:15:57–01:16:23)
I think the embodied carbon is something we're working on, and if you can get low carbon concrete or steel and things like that. And then, you know, the thing that's been in the back of my mind is if we have a small little pre-K, we can make it all wood-framed. And you'd be eliminating the steel. Yep.
Can you just talk about embodied carbon?
Speaker 12 (01:16:27–01:19:11)
So, there's operational carbon, which is what you would think of as your energy. So, the light, the heating, the cooling. There's outlets, everything that's plugged in like that is all the carbon that comes from that. That's what we call operational carbon.
And then the other bulk of carbon is what goes into basically manufacturing the materials, so making carpet, making drywall, making steel, and then all of the transportation of that to your site, the carbon emissions from that, and then constructing it, so the emissions that happen And on your construction site, and then over time, and so that's really a locked in date. Right? Like, you have this carbon footprint just like building your building. Um, and what's going to happen is we start to.
And we've already been doing this for decades. We do things like operational carbon. The amount of embodied carbon and its impact is quite significant and will actually be one of the largest sources of emissions in the country and in the world. So we really want to think about that because it's their day one, plus there's cyclical changes, right?
You have to replace carpet over time every time you do any kind of alteration or upgrade, there's an amount of that embodied carbon that's coming and being put back. Most of it is their day one. And so things like concrete and steel are the two materials that have the most emissions associated with them, with building materials. So what Larry was talking about was wood-framed material and that as a structural system is much lower in body carbon than concrete or steel, but we can also do a lot with one.
So we can replacing the material in the concrete when it's built to be lower in life for many components, you can be really efficient with steel. The body part is actually quite low cost because it just inherently is less expensive to be more efficient with your system because you don't need as much steel or concrete to obviously be fully secure and well built building. And so That is another thing that we would do as part of our process in terms of efficiency. But there's going to be a time where cost is potentially a thought within body carbon.
And so if you were really interested in body carbon, we could talk about that. And lots of things that were postdated or left in the models are going to be just top neutral, like with that low potential in the savings, but there will be some components that might cost more, and so that's where, unless you're really wanting to go further with the body carbon, you might say, okay, it's cost-prohibitive, we might do this, and maybe we can't go all the way.
Speaker 5 (01:19:12–01:19:25)
Is the premise of some of your current mappings based on concrete and steel construction, or is that still open to interpretation, like you were looking at a mass timber cross-laminated timber structure?
Speaker 11 (01:19:25–01:19:29)
Have we locked ourselves out of that?
Speaker 12 (01:19:29–01:19:44)
No, I mean, the mapping would support either one of those, but that would be an example for cost. Those systems do cost more. They save you time on construction and, you know, you could potentially save construction time cost.
Speaker 5 (01:19:44–01:19:54)
I'm not convinced that they necessarily cost more. They often do.
Speaker 12 (01:19:54–01:20:19)
We usually fight with the contractors because they're like, well, it costs this much more. And we're like, no, it really only costs this much more. Because it saves us some time. But if something like a small building, especially, you know, if we go with an option where the preschool is a separate building, that potentially doesn't cost money to actually do that, potentially out of, like, time frame and language.
Speaker 9 (01:20:19–01:20:25)
I was going to say, to my argument early on, and let's reverse it, we could actually probably let them keep her.
Speaker 5 (01:20:25–01:20:30)
That may be a net savings, depending on when we build that.
Speaker 15 (01:20:30–01:20:32)
No, I agree.
Speaker 5 (01:20:32–01:21:52)
I was just thinking steel. Yeah, no, but if you look at residential construction, the four-story wood framing that's happening everywhere, it's a little hard to do with the fire protection requirements that the assembly uses in the school. So we haven't seen that come over and be used for wood framing. So you typically are doing CLP, cross-laminated timber, which is more like big pieces wood and you know as much as I'd love to chase it out today and see what the costs are so far we haven't seen anything.
I would love to go through that. We're doing a project in Belltown right now where we have cross laminated and they're 14 inches thick by 65 feet long and we have a light gauge A metal frame at either end of the metal structure. We're doing layers of that on 5 stories. I think that would be the hardest.
That's the only concrete building we want. Yeah, let's look at it. I think, you know, to me the question is, you know, how much drywall can you get rid of if you have all this wood? You know, those kind of things.
Is it giving you a nice, resonant space? You know, so far we haven't seen, but I'm happy to chase it around a little bit.
Speaker 12 (01:21:52–01:25:12)
I hope that the price on that will come down. It just wasn't quite where you'd get all the projections offered. I think we haven't seen that. So we'll move on.
This is an overview of some of the tasks that happened during feasibility and schematic design. On the left-hand side are some general tasks. On the right-hand side are related to HVAC and net zero. That's something we're looking at.
We've already been doing some of these things through revisioning. This right now is sort of like our introductory workshop. We're talking through these things at the end of these ability. We want to know what the project requirements are.
Basically, what are we. You know, then designing to further as the project design. And then on the HVAC side, it's really about understanding the HVAC systems that are potential systems and selecting a preferred option that is not necessarily the option, but a preferred option for pricing at this stage. It's not said, so that is, we will do in internet design, we'll start doing more, we'll start doing energy modeling around multiple systems, we'll do life cycle cost assessment for those systems, and then at the end of the internet design, the final system would be selected.
In pink, you'll see some things that we actually just talked about that are optional. They aren't necessarily a standard we're doing in every project in the right now, not in the base B for this project, but we talked a little bit about net zero. There is a potential that we could do what is a very detailed net zero life cycle cost assessment. It is not necessary in order to do a net zero project.
Oftentimes, the standard LCCA that we do Um, which looks at utilities, um, cost differences, operations and maintenance cost differences, and then over time the different systems. That is usually enough to be able to feel like we select that system. Um, the net zero, you know, detailed assessment would go much further into a cash flow analysis over, you know, a 30-year process, um, and look mostly at savings that you get from the net zero as opposed to net zero ready, which is, uh, solar savings that you're doing on-site. solar.
That is not typically necessary to be able to make the decision for a net zero building. And then with that, we kind of talked about embodied carbon and life cycle assessment. We wouldn't typically do the life cycle assessment during this phase unless that was something we were really interested in doing. But for me, we would be doing one of those in a later phase.
It just wouldn't be doing it as typically as we're doing it now. And then a water LPCA, again, which is collecting rainwater and reusing it on sites. And for some projects, it goes beyond that. And it's about collecting gray water and black water and treating that site.
And so we do use these sometimes when we have the very specific requests from the districts that we're working in. Typically, it's because there's a very specific site condition where they look at this.
Speaker 3 (01:25:12–01:25:28)
Just one other thing, so for the life cycle cost analysis, the detail that she was talking about is The town of Lexington did a very detailed one.
Speaker 5 (01:25:28–01:25:55)
There's a presentation online if you guys want to see it, kind of dive into it. Get a view, kind of, if we ask for it, what to expect on there. What they found is the operating cost of the building over a 30-year period was much, much less. And for them, when they were looking at the overall project, they understood the upfront cost to do some of this, but then weighed in the overall 30-year cost of operating the building.
So I'll forward that around there, but it's
Speaker 2 (01:25:55–01:26:00)
a little boring, but as you can get into it a little bit.
Speaker 3 (01:26:00–01:26:21)
I mean, you guys run up those guys, so I'm sure it'll be exciting for you guys. But it's good to kind of see where some of these things that are here, you're talking about them, they sound really expensive. We're actually making it so it's much more efficient. So over the course of the building and stuff, it'll be less.
Speaker 12 (01:26:21–01:28:45)
That assessment used to be more useful than GAAP. I'm going to talk about this in the next slide here. When we were looking at GAAP systems and when GAAP systems were the cheapest system where that is not the case anymore. And so we don't see as much benefit within that zero like separate cost assessment because you see most of that in just doing the standard LCCA.
And then we could talk about what the savings are from CME without having to get into the detailed assessment. So we're going to show some examples. I don't have an example today of what the dead zero assessment looks like, but it's similar to what Lexington did as well. But I do have an example of what the standard LCPA is.
So I want to talk about energy code just a little bit. The energy code, as we talked about earlier, there's a scratch code component, and there's a couple of pathways I'll talk about in a second. And then there's the specialized code, which is a solution. I always think of that as a little cap on top.
Most of the energy efficiency and reducing your energy happens in the scratch code. And then the specialized code is just really preparing you for electrification or heating all electric cables. So on the stretch code side, there's two paths for schools. Essentially, there's a passage of certification, and it's likely for a third party that the certification is given a certification fee, which is your document, and you get a certification.
And the state of Massachusetts, when they created the 2023 stretch code, created a path that is essentially parallel to that, but didn't require you to go to the third party and pay for that certification. They tried to, as best they could, make a parallel to similar tasks, which has an energy modeling component plus the cryptos components to it. But they're trying to get at the same thing, essentially, what we call path-assessed principles, path-assessed design principles, which is about focusing on the envelope and having a really thermally improved envelope, an airtight envelope that reduces the load so you don't have to heat the pool as much because the envelope is a great envelope. And then having dedicated ventilation so you get all that great air quality but having that be a controlled system where you're also using energy recovery or recovering energy heat recovery in your ventilation as an efficiency process.
Speaker 8 (01:28:45–01:28:45)
So
Speaker 12 (01:28:46–01:39:29)
These are both trying to get to that. Our recommendation is to do the Teddy model for this project, unless you say we really want to do a pass-the-pelvis certification, because they are getting essentially to the same buildings. They might look slightly different, and I don't mean visually slightly different. This one might have a half-inch left insulation in that, because the way that they're modeling You know, not exactly the same, it's a different software, so we can't give you exactly the same results, but essentially it's giving you the same performance of the building.
And we'll talk about that actually in just a minute. So, in terms of, you know, the design side and then the construction side between the 2. It was the same all of a sudden, right? Is your building and the same system.
It's the 1. it's going to be the same system that the other pathway would say. works with that and has the same envelope, essentially, and has the same windows. And pink are really the only two differences.
It's new, so we've only got a few models. We talked to our colleagues both on the energy modeling side and architecture side to see, like, what projects are you doing? Because, again, we have all been doing this for years. We don't have a lot of examples.
We are seeing that sometimes the PEDI process might require a little bit more installation in certain areas. It's not a given, we can't say that's a definite. I think this particular project, when I look at the mapping and different mappings and where the program spaces are, I don't think there's anything that's necessarily going to trigger that to be true. And then on the process side, I kind of mentioned this before, the certification fees.
And the certification fees are not only for that certification, but on the construction side, we do think there that there's additional testing and verification that happens during construction. So there are some things that, you know, even the TEDICAP will have to do with air leakage testing, MEP commissioning. We might also be doing on-load commissioning through the LEED process. We talked about that a little bit above and beyond that.
So there's fees that are associated with stock costs. We have to hire third-party bearers who are similar to the commissioning agent where they're hired directly by the owner and they're going out there as a part of the project working in terms of observing and inspecting what's happening and providing information back to the commission if there is anything that is deficient in the statement. For a project of this size, we anticipate that cost for passable certification, including all those soft costs that we just talked about, plus the fee that you pay to the third party for the certification to be around $200,000 to $250,000. So that is why we are recommending the penny pack right now in terms of that cost of that certification.
That way, we're recommending to do both the teddy pack with fresh. And then the specialized code, there are 3 pathways. I'll start with the 1 here. Shawn mentioned that earlier, but.
You technically could have a mixed fuel building, meaning you have natural gas in the building. For reasons in terms of cost, both construction cost and operational cost, we'll talk about later why that is not necessarily the system you would want to do. But if for some reason you said you wind up gas in the building, you are held to more heat on the HVAC for heating the hot water. And then you need to install solar to the extent possible, meaning if you have a roof that's not blocked by buildings and trees, then you actually could generate the renewables you require to put the renewables on.
And you have to have a full electrification design. So that means that your service or electric service is designed day one to support a fully electrified building. You have to pre-wire the full building. You have to design all of the space inside the building.
You're on the roof. You have to basically do design and plan that show exactly where all of those things would happen in the future. This typically doesn't make sense for a school project. On the very top, there's your energy path, and that is providing renewable energy, solar, PV on your building that can supply 100% of the energy of the project.
It is possible on this site, but it wouldn't be possible to do it all in the booth. So you'd be talking about large canopies over the majority, if not all of the parking area. Based on the square footage and, you know, the free store or the four-story massing, and then two stories on the preschool, you know, you probably could get it all on site, but it would be a little bit difficult. And so we, again, would recommend all electric paths, because that's where you're probably going to end up anyway, because we are all fiercely committed to being all electric.
And you could certainly add TV on site, While the code calls this the zero energy pathway, the industry also recognizes that zero energy buildings are not on-site. It's either a combination of on-site or completely off-site, especially if you wanted to put it on-site. So a net zero building, you would still be able to be a net zero building, even if you didn't put it on-site. In terms of what the industry recognizes as a net zero building.
Organizations and databases that very clearly define net zero as not being 100% on-site, but for the energy folks specifically, they consider 100% on-site as what they're coming to. So, we're going to talk high level about different systems. And again, the reason I'm talking about only electrified systems here is because. Some of these systems are the exact same price or even less than a gas system, especially when you start to account for the electrification ready component that would be required if you had possibly a specialized curve.
And then, in terms of the operational side of these, especially if you didn't pair it with photovoltaics or subatomic photovoltaics, we're really using that to reduce your operational cost. And so there are generally four types of systems that would be appropriate for a school. The first one being a ground source heat pump system, which is a geothermal well field. So it's a closed-loop well that goes through the ground and basically uses the heat transfer of the ground in its heating and cooling system.
The second one is sort of a version of that, that is a ground source, and we're not going to get too much in the details today, but you can kind of consider it the same. They're both ground source. The second one would not be full cooling in your space, because it would be geosignifications and not capable of full cooling. And that's really the main difference between those.
And then the third option is a BRF system, or the Reservoirs for Drink Flow system. And then the fourth system is an air-to-water heat pump chiller heating plant. The reason I have this little flash through it here is we don't recommend that system. And we'll kind of talk about the pros and cons in the next slide, and you'll see why.
We don't recommend that, although it is a system that we're listening about whether it's work or getting a good position for engineering schooling. Options 1 and 2, the ground source systems, are the most efficient systems. They are definitely able to get to net zero. And the way that we define net zero, and again, that's an industry, we are not heirs to these, net zero is defined as basically having an energy use intensity, or an EUI of 25.
So that's a benchmark of how much energy we use per square foot in a building. And so 25 is, or below, is considered zero. And the ground source heating systems would definitely be 25 or less. The VRF is maybe net zero, because it doesn't always get to that 25, even with a great, efficient envelope.
The VRF is just not quite as efficient as the ground source system. And so sometimes when you run the energy model, it is really depending on mapping and site, but not in a way that we can easily design and map the building to the chemical lab over a genetic suite. I just want to point one other thing out. So the first two here and number four have displacement ventilation, and we'll talk about what that means in a second.
And number three has overhead ventilation. So this place, we'll talk about overhead first. So this space has overhead ventilation, pretty typical to see it in those buildings you go to where you have the air coming out up high, and it's basically at a higher velocity to get down to where you're all sitting, because this is where the actual breathing zone, and so that's creating a mixed air system, and that's the diagram on the left. And so the building will have good air quality just in the nature of new systems in terms of ventilation rates, how much air changes over In the space, the filtration that happens on the equipment side.
And so there will be good air quality in the space, regardless of which option. Displacement has the ability to be a little bit better in terms of air quality, just because displacement is liberating the air lower. So typically it's a. The wall towards the bottom of the wall, and it's coming out where we're all sitting in the breathing zone.
That's where the air is coming out. And so just by the nature of that, instead of mixing the space in order to get the comfort, it's able to deliver it down low where we need it, and then it's exhausted up top. So it's not mixing all of the air. I found that I don't have to explain it too much now that we've gone through a pandemic, people are pretty like savvy to like why mixing the air might not be quite as good quality as delivering all the pressure as we take the stale air out.
Speaker 3 (01:39:32–01:39:50)
Yeah, and that's why I say more improved indoor air quality, you can probably read that in the back, because they're both good indoor air quality.
Speaker 12 (01:39:50–01:41:29)
there is a slight improvement that you can see through the placement. And then the other two pieces are the acoustics, because we're not trying to get it. And this is obviously a very tall room, but even a regular, you know, typical height room, you have to supply a much higher velocity to get down and create that mixing. where on the displacement you don't have to.
So less velocity means you don't feel as much of a draft. You don't feel like, oh, I'm sitting underneath the duct and I can feel the heating or the cooling coming down on me. You essentially don't really notice it coming in. It's also quieter because it's not at all, it's not blowing out at the same velocity as what you would be in your normal suit.
There is a lot more comfort from that and acoustics. We have people who go into some of the schools that we design and have a displacement and they leave it on. And so sometimes we get questions from staff, is it preventative? Is it so quiet?
Is it on? Is it getting fresh air? And so yeah, you would notice if it wasn't on because you also wouldn't be getting the heating or cooling or things like that. So those are the two big things.
You will get good air quality. You will get slightly better air quality with a displacement, but they could get in with normal pump or other. the two biggest communities. And you'll notice that we talked about option three, that VRF can't move through the displacement, and so that is just a good way to that system, and we'll talk about that a little bit in a second.
The way that it's delivering to the state just can't be through displacement, where options one and two can do displacement, they can also do it.
Speaker 11 (01:41:30–01:41:54)
You can see now the ability to cool though, because the dehumidification system, in my experience, cannot cool to the extent that a more traditional HVAC or VRS system can. and like, yeah, I know in the first one, the chillers, whatever. Can you just talk about kind of between those three, like, what is the actual cooling effect within the spaces?
Speaker 12 (01:41:54–01:48:07)
Yeah, so options one, three, and four can do just dehumidification, or they can, which would be at that point of the 78 degrees, or they can do full conditioning with full cooling, which would be at that point of 75 degrees. So they have the option to go down to that, For option two, it can only do dehumidification, it can't go to full cooling. And the way that it works with the ground sort, in option one, it basically does transfer with the ground coming in and goes into a heat pump chiller that creates either chilled water or hot water. And then that is running to your air handling units, that's running to your radiant cooling and your spaces where option two is only doing sort of the heating side of that.
And then on the cooling side, it basically removes chilled water from your building. And so because you don't have that chilled water, you can't get to that full cooling level. So you can do the dehumidification. We would do dehumidification in everything because dehumidification is, humidity is actually a lot of the component of feeling, being empty, and things like that.
And I'm going to run through these quickly because we don't necessarily, we can always go back. This is just an overview, but this is not option 1. You can see that there's essentially indoor units that are transferring with the ground well. You still have rooftop units that are your air handling units.
And in the classroom, you have this basement. And you have radiant. And so radiant is heating and cooling at the perimeter. And that's just radiant heating and cooling, just like it sounds, where the displacement is providing your ventilation air, but it's not necessarily doing all of your heating and cooling.
This is why this is the most efficient, because it decouples so that you get your heating and cooling the way that you need it to be. And you don't overventilate the space to get the heating and cooling, because the heating and cooling Sorry, the ventilation is not also what's giving your your feeling. So you can basically control those two things separately. Option two, again, is very similar.
We have indoor equipment that's connected to your ground loop, and the classroom would look similar in this placement, but it wouldn't have radiant cooling. It would only have radiant heating. So in the cooling season, you're basically relying on that ventilation to do the most cooling you can, which is the dehumidification system. So that's really the main difference between them.
And then BRF system, all of the equipment is on the roof. You have similar to the other two options where you're going to have a large air handler on the roof, but you also have small outdoor units that are contributing to heating and cooling that are basically stand coils in the in the ceiling of the classroom. So we talked about acoustics from the overhead versus displacement, and just the nature of overhead, it is louder because of the velocity. And specifically, too, if you're doing overhead for the VRS, that's a little bit louder as well, because there is moving mechanical motors and all those things going on in the ceiling.
Whereas if you did an overhead with, say, a ground floor system, that overhead would be a little bit noisier because you're, you know, having air coming down in high velocity, but the actual grill, if you will, looks fluffy. There's no moving parts, there's no mechanical movement up there. But with a VRF, you have, essentially, mechanical movement in the ceiling now. And then option 4 basically has air conditioners on the roof, heat pump, heating chillers on the roof, with backup electric boilers.
So pros and cons. Ground source heating and cooling, it's the most efficient system. It's the lowest operational cost in terms of both the utility cost, because you're saving energy and not paying for the energy, but it's also the lowest operational cost in terms of operations and maintenance of the equipment. It's the lowest birth cost factor incentive, which I'll talk about incentives next.
It can be achieved with full cooling. The ground source, keep off hot water, number two, most efficient, lowest operational cost, and it's lowest risk cost. It's very similar to option one, it's really just the cooling is different. The VRF, the pro would be that you don't need sites for the well field, because you don't put any wells in, it's all contained in the building and the roof, and it is the lowest risk cost, so for instances, but not at this point.
And so on the con side, you know, typically the ground source, it's, you know, do we have space, can we put the well field in? We do have space on this particular site, so we can put a well field in, and then the cooling side, And then on the VRF, it's more rooftop equipment, it's also more indoor equipment, has more maintenance. Again, it's most of those, you have a lot more rooftop equipment, plus if you imagine that side camera shows in every ceiling, you have all these equipment components that need filters and motors, and there's a lot more equipment and maintenance. It may not get to that zero.
And then number four, the air-to-water heat pump, you know, it is the least efficient option. It's the highest utility cost. It's definitely not going to hit net zero, and it's not going to have the amount of incentives that you would get with any of the other systems. So it actually typically has the highest risk and cost factor.
Speaker 5 (01:48:08–01:48:15)
So when you say not net zero, is that, I assume that's just the end of what you've seen with me, not getting low enough? Yeah. That's the problem.
Speaker 11 (01:48:17–01:48:20)
A couple of questions. Sorry.
Speaker 5 (01:48:21–01:48:30)
Don't provide me that there's there. There wouldn't be filters within each of the users within the wall.
Speaker 12 (01:48:30–01:48:42)
So the placement is just, it's a growth, right? You're passing air through it. And it's really passive. There's nothing active in there.
Speaker 11 (01:48:43–01:48:50)
And how big is the well?
Speaker 12 (01:48:54–01:49:19)
For this building, the well field would probably be somewhere around maybe like 80 wells, maybe a little bit more depending on how deep they were. there's space on a 20-foot grid. So we, there's definitely, you would essentially, if you thought about it as the amount of parking you have right now, imagine wells being built off that.
Speaker 14 (01:49:19–01:49:21)
Or under the building.
Speaker 12 (01:49:21–01:50:15)
We typically don't put wells under the building, especially in new construction. Not that there are necessarily things that you need to go back in the ground for. It usually is more of a construction sequencing. So to be able to do the well field while you're also doing you know, foundations and things for the buildings, that's typically, we put them under buildings when they're existing buildings, because often times, that's where they're going to be.
But in new construction, we typically will use football fields. Yeah, and so, that's why I say parking, because typically, you're not expanding necessarily on parking, meaning, I know we talked about the columns before, like you, You can put columns down in the parking, but if you're going to put a whole new building on the parking, then you'd have to think about that if that was the case.
Speaker 11 (01:50:15–01:50:22)
So, given the amount of parking on the site, is that really a con for this particular project than the areas that are wealthy?
Speaker 12 (01:50:23–01:50:31)
No, this is a generic site, so it's not specific. So, for this particular project, there is enough site area.
Speaker 5 (01:50:31–01:50:45)
But you're right, this is a logistical challenge to get the wealth built in, because you start running out of space pretty quickly. If you're trying to build a building next to a place where you're installing wealth builds, that's something, a challenge we will have to overcome. And no matter what scenario we do, anything with wealth.
Speaker 12 (01:50:46–01:51:04)
And oftentimes, we do start them a little bit earlier, depending on where the wealth fields are. But sometimes we do that. We start that before you want to do the whole site work just to get those in, because it takes time.
Speaker 11 (01:51:04–01:51:08)
With doing that, does that system mean essentially you have no RTUs? Like there's nothing on the roof?
Speaker 12 (01:51:08–01:51:29)
No, you still have RTUs. These are just supplying the heat. So the well field is just going to the heat pump chillers. And then from there, you have hot water and chilled water going to your RTUs.
So it's basically just using the ground source as a heat sink, as opposed to the air and a VRF, which is essentially an air-cooled heat pump.
Speaker 11 (01:51:29–01:51:33)
OK. I guess I was going to say, it's more rooftop equipment than the VRF.
Speaker 12 (01:51:34–01:51:47)
Yeah, it's not the air handler, it's all of the outdoor units for the VRF. So the VRF also has basically the outdoor units for all of those.
Speaker 5 (01:51:47–01:51:53)
I was thinking it's important we can take you guys on a tour of some of the things we started to see.
Speaker 12 (01:51:53–01:57:15)
That's interesting. And I'm not going to go through this whole thing, but this essentially is what the life cycle cost assessment will look like, but with numbers on it. So right now, this is just showing comparative, where the full circles are better performing in the metric, and then the open circles are less performing. None of them are underperforming, which is all just relative to the statistics we see here.
But in the LPCA, we'll essentially fill in not the qualitative components like indoor air quality, but the comfort and acoustic. But the energy costs and operations and maintenance costs, the capital insurance investment, investment after incentives, and then the number of years in the payback. So that part of the chart will be filled in. And I just want to touch on incentives today.
Briefly, there are federal incentives, there are state incentives. The federal incentives are basically tax credits, which now municipalities can get that through a direct payment. A state library map save, which you're probably all familiar with. And there's two paths.
One is a path where your project is net zero ready, or 25 or less UI. And the top two is if you're not able to hit that 25 or less in the top two. Just quickly, federal program, as I mentioned, direct pay, which essentially is a check after the building is built and placed in service, what you would apply for. Essentially, you're applying for the pre-filing registration after construction, and then you're filing essentially a tax return, and you get correct payment after that.
So it's similar to that state where It's after construction and after the building is built. It's going for that. It was like a reimbursement in that way. The federal incentives are really targeted towards technology.
The technology that would potentially be in the school building would be solar or ground source heat pump, which we just talked about, or EV charging. EV charging is not applicable to this site because we're not in the census tract that allows that. So the bottom here you can see Solar and ground source are the 2 potential technologies that you might have in a building that you could get federal incentive money for. And you would get between 30 and 40% on the solar side, and that's just based on how much of the content could be domestically produced, which is much more difficult today right now for solar.
A lot of it is not produced in the country. And on the ground source side, It's much more easy to get domestic content, and so you'd be looking at 40%. That's 40% of the whole cost of that system. So it's not just the ground wells, it's all of the HVAC equipment that is fed through the majority of HVAC systems.
If you're going to use taxes and bonds for this project, those rates are reduced in the objection for those taxes and bonds. So, a 30% would really be more than half, and a 40% would really be 34%. So this is just an example using a building under 69,000 square feet with estimated amount of heating capacity and number of well fields and the cost for that. We obviously haven't been computing for the project yet, but this just gives you on the left hand side a ground source heat pump and on the right hand side an air source heat pump, which is the VRS system.
You can see at the top that they both have solar. We're just assuming that they all have solar, the same amount of solar. The ground source obviously has ground source, so you can go out with the federal incentive for that. We wouldn't be able to do that if we didn't have ground source.
in the VRF system. And then Path 1 is the not safe path. You get a lot more incentive for that pathway than is eligible for the Path 2. And again, that's at 25 EUI.
And typically, the VRF can't get to that, so it would be Path 2. You can see the difference between the 1.8 and the 340. I just showed an example where there's EV charging, there is an incentive for that. It's obviously not the bulk of the incentive.
So you can just see the difference between a ground source and the air source. And earlier when we were talking about the ground source as being your vote of self-option, you factor in the incentive, and that's because they are extremely heavily incentivized to do the ground source with them because they are the most efficient system. So this is sort of teeing up the conversation as we go through this, to know what system is your baseline system for pricing.
Speaker 3 (01:57:15–01:57:26)
We actually lost, right? Or is this just an education for what's coming next month?
Speaker 5 (01:57:26–01:57:41)
Well, part of it right now is, you know, we're looking to get into pricing at some point soon so that we can, you know, come to some observations. Yeah, sorry. I was trying to share the room, but they're running low.
Speaker 2 (01:57:41–01:57:51)
Yeah, so one of the questions I have is, I know these construction costs are just estimated. They're not construction costs for this project.
Speaker 12 (01:57:51–01:57:58)
I mean, they're reasonable construction costs. It's a different project, but it's calculated.
Speaker 3 (01:58:01–01:58:14)
So if I just add up what we have for construction costs and the ground source heat pump, we're at $23 million. for the total, whatever's listed there, for the total construction costs, right?
Speaker 5 (01:58:14–01:58:20)
And then if we look at construction costs in the other one, we're roughly at $3 million.
Speaker 12 (01:58:20–01:58:32)
Is that correct? But that's not correct because there's no HVAC system on the second one because it doesn't transfer. Yeah, I'm just asking for clarification. So that $1 million might be that $2 million for that airport.
Speaker 2 (01:58:33–01:58:38)
Yep. Okay, that's kind of it. That's what I was going to say.
Speaker 4 (01:58:38–01:58:39)
Yeah, you have to make sure.
Speaker 2 (01:58:39–01:58:45)
Yeah, because if you're looking at it, just adding up the columns, you know, way different on there and stuff like that.
Speaker 5 (01:58:46–01:58:51)
Under the air source decompensates NA, but there are costs for that system.
Speaker 12 (01:58:51–01:58:54)
It's not a fixable thing.
Speaker 5 (01:58:55–01:59:00)
Gotcha. So there are additional construction costs to kind of bring them together.
Speaker 12 (01:59:00–01:59:11)
Right. Yeah. This is not really to show construction costs of each system. It's just to show the incentive for that system.
And obviously, the construction cost of that is there if you can.
Speaker 2 (01:59:12–01:59:22)
Correct. So the overall construction costs, when you start adding them up between the two systems, somewhat similar, but the incentives that we can get are more
Speaker 5 (01:59:23–01:59:32)
The free money you get from the government is more there for a ground source.
Speaker 12 (01:59:33–01:59:46)
Say the difference between a ground source and a VRS system is 1% without any incentive, 0.25% for any incentive. The air source for the VRS system is probably 2% to 3% more.
Speaker 5 (01:59:47–01:59:59)
What's the downside of option 1 versus option 2? You get an option 1 device, greater cooling, and so more costly, right?
Speaker 12 (02:00:00–02:00:51)
Yeah, you have to think about, you know, bridge finance in that, because these are all representative of capacity, right? We have the plan for building a front builder. a risk to do that or a process to do that is you have to, if it's a whole bunch of stuff, and you're going to get, you know, handling that later, that is something you have to factor in. It's not something you're relying on a lot of consensus, but you don't get it until a year after the building is done.
Potentially a year and a half, maybe two years. when you fall in the cycle essentially for the federal funds. So that's one thing you have to consider a little bit.
Speaker 11 (02:00:51–02:00:59)
That's the difference though between the VRS and the ground sources. My question was more on the two different ground sources, the chiller versus the non-chiller.
Speaker 5 (02:01:00–02:01:09)
I mean, it seems like it's obvious to go to the one that's rising temperatures and things like that, like provide us the ability to chill.
Speaker 11 (02:01:09–02:01:27)
That was some feedback we got from one of the buildings. We just said, where are they going to be for the building? And it's only been engaged in a number of ways. And so that's one thing that we regretted about the construction.
So I just don't know the difference between that or not going to.
Speaker 12 (02:01:27–02:02:28)
So we actually, most of our project programs are option one. We're working on a project right now where they wanted to look at option two and we were like, okay, and we're looking at the end of the year to figure out like, does it make sense? They just didn't want to apply. It's common to build in places where people didn't want shore water.
So then we were like, OK, well, are you going to really keep saving? And so LifeSafe was talking about this big issue that there wasn't savings construction-wise from doing that. It was very negligible to do. And then, of course, they don't get full growing, but that was just a preference.
So that's why it's on here. But it's not typically the thing that we would propose. I mean, I don't know if we're looking for it, but if that is the particular point that's on your presentation, it's very compelling to me to go with option one.
Speaker 8 (02:02:29–02:02:43)
Just for sort of the estimated incentive and also just the fact that the temperature changes that we're seeing, we do need to have a building that can chill.
Speaker 5 (02:02:44–02:02:57)
Is there any issue with the… I'm going to take a minute to answer this, but obviously VRF is a much more tested system, right? It's been around longer, is that fair to say, than Ground?
Speaker 12 (02:02:58–02:04:28)
No, Ground has been around longer than VRF. Even if you look at VRF, it's been around longer than you have in the system. Ground has been around longer than VRF. VRF is still You know, been around for a long time.
Um, there are, we talked about some of the main challenges, um, the maintenance costs is, you know, maybe a little bit more premium, if I'm being hard to it. Um, the other thing with the BRF is that refrigerants do change over time. Those systems also don't have as long a shelf life, you know, back to maybe 10 years, maybe 15, 20 years. Um, and so, There is sometimes a risk factor in that.
We know right now that this is an interaction between things. And then maybe kind of in a couple of years, we'll be into a new refrigerant. But that could also change over time, too. And so there is some risk that we might have to replace refrigerant lines in buildings where the refrigerant changes.
Because some of the refrigerants don't work the same way. So that is, it's on a renewal risk that we know in five years we're going to change that. We don't know what that's going to do, but it is a bit of a risk.
Speaker 5 (02:04:31–02:04:39)
One of the questions I had for Larry, we walked the Acton-Marxboro project and they haven't gotten to the C-Pump there.
Speaker 3 (02:04:40–02:04:58)
We've got to see everything. As you talk about replacements and stuff like that, I'm wondering, For all the wells in the parking lot and stuff like that, is there a lifespan on those? And if so, at some point, how do you replace those if you need to?
Speaker 12 (02:04:58–02:05:31)
So the wells should last for 100 years, at least, so we don't integrate anything in the well field. So that's the vertical well. In the horizontal well. You have to know that they're there, right?
Because you don't want them to be sticking a whole bit of stuff into your home. And those are, you know, store the 5G under the dome. So those would be relatively big and useful. The equipment side is really for the, the location side is all on the same side of the dome.
You can see on here, it's like that section of the city. There's the service regulation office.
Speaker 5 (02:05:31–02:05:34)
There's some pumps that have been in place.
Speaker 10 (02:05:35–02:05:37)
Do you know what located in the field, right?
Speaker 12 (02:05:37–02:06:01)
Right, so the pumps are inside a mechanical. There's not, the main pumps are not hanging wet layers of branches. There's a vault that kind of selects a lot of the well fields. It's called a vault, which is a bunch of them.
And then, you know, you can see the building. There is some equipment in there that might need maintenance. It's not like routine maintenance.
Speaker 5 (02:06:01–02:06:13)
Yeah, my question is more, thank you for answering, it's more like 20 feet on the center wells that are going to be spread out over the entire parking lot. So, you know, just 20 years from now, we don't have to dig up the entire parking lot.
Speaker 12 (02:06:14–02:06:32)
Yeah, and you know, it is an older technology, they, in terms of the VRF. These are not open well. 30 years ago, these would be open well, but there are issues with them in that not these are closed well.
Speaker 14 (02:06:33–02:06:37)
They have to be commissioned.
Speaker 5 (02:06:40–02:07:00)
Yeah, just one follow-up. I know we're planning on doing borings at some point soon. Will that information help influence whether this is a good site for a ground-source heat pump, or is it just, you know, any geological strata as we go down and get dissolved?
Speaker 12 (02:07:00–02:07:44)
You can put them in anything. Rock is actually better. It's something to be counterintuitive. In terms of what would impact it, we don't necessarily know that from the boring, but if we're definitely looking at ground source, then in somatic design, we would suggest having the geotextile.
Geothermal consultants do a depth assessment, and it would be referring to both. Because then you can anticipate, you know, based on forings and other things that are known that you hadn't helped in high ground water, you could say, okay, we think there's gonna be more dewatering.
Speaker 5 (02:07:44–02:07:58)
There'll be some dewatering. So, let's see, in Acton, we were in the fissure in the rock where the water was moving, and so that was coming up, and there was a lot of dewatering. We just put two test wells in Quincy, and it went into the bay, and they were dry.
Speaker 12 (02:07:59–02:08:06)
There's a lot of seawater.
Speaker 5 (02:08:06–02:08:32)
We mentioned Lowell Field earlier. That's the drainage plant in high school, and there's a lot of groundwater there. Other parts of the site may be fine, right? But when they put the first pipe in, it's really the issue of when they're pulling it.
They put a pipe down, and that thing just keeps opening up. They might get lost on the site. Really surprising. We'll find out.
We'll be outside of our realm of possibility to know.
Speaker 2 (02:08:35–02:08:47)
And then the other one I had too is, you know, we talked about solar portable tanks. Is there any opportunities? Is there anything about solar hot water or anything like that that you guys typically do? Or is that just like an abandoned one?
Speaker 12 (02:08:47–02:09:11)
It wouldn't make much sense here if you don't have a high water level. We've done it in the past. You can come over and use it if there was a pool. Even though it's outdoors, as long as you're able to extend, you don't really have to get in the water to get rid of it.
And so they made sense there. But there wouldn't be, even with a pool, it's imperative to have enough water.
Speaker 5 (02:09:11–02:09:17)
Thank you. And just for clarity, we're not putting a pool in. We just want to make sure.
Speaker 7 (02:09:17–02:09:25)
Can you compare efficiencies, better efficiencies with the ground source? Do you have a steadier temperature?
Speaker 12 (02:09:26–02:09:37)
That's what makes that system the most efficient, because the ground temperature is always the steady state, whereas the air temperature can be, you know, minus five to a hundred, and so you can save money.
Speaker 7 (02:09:38–02:09:46)
And that's going to be a challenge for us too when it gets real cold outside.
Speaker 12 (02:09:46–02:09:52)
We're not going to have enough heat in the air.
Speaker 5 (02:09:59–02:10:13)
So one last thing on displacement ventilation, if you guys are flying out of the new terminal B over at Massport, the big red building, it is 100% displacement ventilation. It's a really cool interior.
Speaker 2 (02:10:13–02:10:25)
You'll see big column interiors that are there, and it's basically that's where all the fresh air comes in. And similar to your photo that was in there, I was involved heavily on the initial concepts of that.
Speaker 3 (02:10:26–02:10:31)
And because it's such a big atrium space, it just lent itself for displacement ventilation very well.
Speaker 5 (02:10:31–02:10:59)
So to the point, if you're traveling through there, you'll see it. Very nice. Yeah, because otherwise we're trying to throw the air from right above. Yeah, it just became totally inefficient.
And I can go on for hours on that one, you know, different thermal constraints on the chilled water and hot water lines. Any other questions? Sorry, went off on a tangent.
Speaker 9 (02:11:03–02:11:07)
All right.
Speaker 3 (02:11:07–02:11:22)
All right, that closes out item four, which is old business. Item five, which is new business. I think we just covered all our new business, so we'll adjust those for next time. Item 6 is future meeting dates.
Speaker 5 (02:11:22–02:11:25)
I think our next meeting is next week.
Speaker 2 (02:11:25–02:11:53)
As you can see, we're starting to make progress faster and faster. I appreciate everybody showing up tonight. It's good to have a full And just for the people that weren't here last week, John, the newest member of the select board, there was a few members that weren't here last week, so just introducing them.
Speaker 3 (02:11:54–02:11:57)
I apologize, John, I should have done that.
Speaker 4 (02:11:57–02:12:02)
That's okay. Don't worry.
Speaker 11 (02:12:02–02:12:06)
What was that one?
Speaker 13 (02:12:07–02:12:11)
I like munchkins, I can bring them.
Speaker 5 (02:12:14–02:12:38)
So yeah, just for everybody, if everybody's good for next week, we'll just hold that. Any further questions on anything? You know, I think that I think you should have an e-mail, but I probably sent it an hour before this meeting, probably 545. It should be in the inbox.
Speaker 3 (02:12:38–02:12:51)
Yeah. Next thing, item seven adjournment. Make a motion to adjourn.
Speaker 2 (02:12:51–02:12:58)
We're all in person, so all those in favor, say aye. Aye. We are adjourned.
Speaker 1 (02:12:58–02:13:02)
Thank you very much.