Board: Milton School Building Committee
Date: 2024-07-01
Transcript
Auto-generated; may contain errors.
Speaker 1 (00:53–02:10)
All right. Uh, welcome. Uh, tonight's, uh, July 1st, 2024, uh, the Milton school building committee. I'll call the meeting to order at 7 0 8 PM.
Uh, as they typically do just do a roll call vote of, uh, as they, as they see people on the checkerboard, um, um, Dr. Miranda. Thanks. Uh, Carrie Hurley here.
Uh, John Kohane. You're on mute, John, sorry. Yep, thank you. Scott Tereshak?
Present. Tim Lombard? I'm present. All right, Mark Loring?
Present. And Akbar Abang? Present. And, yep, a shot of work.
President, like I said, Glenn Hoffman's the only one that, he might be joining us in a little bit, he'll be calling in. Second thing on the agenda is citizen speak. We reserve the first 15 minutes of the meeting for any citizen that wants to speak. We ask that you raise your hand and just announce your name and address, and please limit your comments to three minutes.
So just give it a couple minutes and see if anybody raises their hand.
Speaker 2 (02:18–02:18)
I'm seeing none.
Speaker 1 (02:19–02:52)
All right, we'll move on. If somebody does pop their hand up, we'll come back. Item three on the agenda is approval of past meeting minutes from last week, Monday, June 24th, 2024. Those are all sent to everybody in your meeting packets from Seamus.
So just open it up, see if there's any questions or comments in regards to the meeting minutes. Hearing none, entertain a motion to approve.
Speaker 3 (02:52–02:55)
I'll make a motion to approve the meeting minutes from June 24th, 2024. Second.
Speaker 1 (02:58–03:04)
Second by Dr. Miranda. I assume no further discussion. So we'll go through a roll call vote.
Dr. Miranda?
Speaker 4 (03:06–03:07)
Yes.
Speaker 1 (03:07–03:54)
Carrie Hurley? Yes. John Cohane? Yes.
Scott Tereshek. Yes. Tim Lombard. Yes.
Thank you. Mark Loring. Yes. Akbar Aban.
Yes. and shuttle work. Yes. All right.
Uh, item four old business, uh, is a discussion update, uh, on, uh, the architectural work that's been going on specifically on the sustainability and the HVC design. Uh, so with us are our representatives from arrow street along with their sub consultant for mechanical electrical plumbing. Um, so, you know, uh, Shanali, I'll, I'll let you guys take it away.
Speaker 5 (03:55–05:18)
Thanks, I'm going to go ahead and share my screen. We have a number of slides to talk through today. Can everybody see the screen? OK, apologies, I can't make it a full presentation mode.
For some reason, my laptop doesn't let me move through the slides. But let me know if anybody needs to zoom in at any point. So for the agenda today, we're going to do a review of the sustainability systems that most of you were here for two weeks ago when Kate Brubisky, our Director of Sustainability, presented some options. She's going to review those with you today.
Then Dave Pereira from GGD is going to be reviewing some of the systems assumptions that are going to go into the narratives that we're sending to the cost estimator. Then the third item is going to be the review of the latest gross square footage calculations. The team's been meeting with the working group and we've made some adjustments and we'd like to review that with the school building committee this evening. And then lastly, The team, the AeroStreet team's been working on adjacency diagrams that we previewed with the working group earlier today that we'd like to present to the committee tonight.
So I'm going to get started.
Speaker 1 (05:18–05:30)
Sorry to interrupt. For me, the screen's hard to read. Do you mind if I share my screen? I can put it on full screen.
Yeah, that would be great. Yeah.
Speaker 5 (05:30–05:31)
Stop sharing.
Speaker 1 (05:31–05:31)
Yep.
Speaker 2 (05:43–05:43)
That better.
Speaker 5 (05:48–06:06)
Great, thank you. So the first agenda item will be Kate's going to speak to and then the second one will be Dave, and then number three and four will be Andrew and myself so we can move to page four. So, one more slide.
Speaker 6 (06:07–07:57)
So as you might recall from our meeting a couple of weeks ago, we were talking about different system options for the HVAC system, and I had showed basically the same chart, but there were some questions about sort of the total construction costs. So the items in blue are the same as basically previously, and then at the bottom, in addition to the potential incentive total, which is the right-hand gray box with the The outline on the left-hand side, I included a total construction cost for that option. On the left is ground source heat pump, on the right is eight air source heat pumps. I just wanted to update this based on some questions from last time about the difference between the ground source and air source heat pump from a construction cost standpoint.
You'll see on the right-hand side, For the air source heat pump, there is a number in there that says $15 million, and it says air source heat pump does not qualify. So I did add that in just so you can see the approximate cost of that system based on the size of the building. But it doesn't qualify for an incentive. So you'll see the estimated incentive is zero for that, just so you can see those together.
Because there was a question last time whether this was a $20 million more than the other. And it's not, it's incrementally more. And so I just wanted to update that slide from last time. So it was a little bit clearer as to, again, these are approximate costs just based on square footage.
These are not estimated costs, but these are just kind of comparing the two and potential incentives between the two systems. If any questions about that,
Speaker 1 (07:58–08:20)
Yeah, so just for clarity, Kate, so the upfront cost for a ground source heat pump is approximately $5 million more, but after rebates and everything else, it works out to about $3.5 million less than the other one? Correct. Yep, John?
Speaker 7 (08:23–08:25)
Does the ground source include the wells?
Speaker 6 (08:26–08:31)
Yes, this is with the well cost. It's the well field plus all of the HVAC system in the building.
Speaker 1 (08:31–08:46)
And just to be clear too, Kate, so this is like an estimated cost just on… Yeah, I say approximated cost because it's not even, you know, the estimator will be doing an estimated cost soon.
Speaker 6 (08:46–09:12)
So this is an approximate cost based on the square footage of the building and some initial assumptions. Okay. About, you know, number of wells and things like that. But this would be a total system cost for the ground source system and a total system cost for an air source pump.
So all of the indoor, outdoor equipment, all the distribution, supply all the way down to the registers and supply grills and things like that.
Speaker 1 (09:12–09:13)
All right, Mark.
Speaker 8 (09:16–09:36)
What's usually the timeline for receiving the incentives? How long does that pay back? And then also, have you been a part of any projects that you know, ultimately did not receive the expected incentives. And so kind of what, what would, what would lead to that risk of us, you know, not receiving the full $9 million incentives that you kind of lay out here.
Speaker 6 (09:37–12:18)
Yeah, I didn't put the slide in again with the timeline, but essentially for the federal incentive, which is the section 48, that's the top two lines, which is applicable to either solar or ground source heat pumps. Those are applied for after placed in service. So that means essentially after construction, after they are able to be turned on and used. So typically that's substantial completion or end of construction.
And then you would apply for that within typically a year, depending on exactly, it has to be within five months of the close of your fiscal year. It could also be on April 15th, like a tax year. So it kind of depends on which date you use, but it's essentially within five months of the next occurrence of one of those after the place in service. So that's the federal incentives and then the mass save incentives for path one and path two, you get a portion of that after the project is completed construction so they under construction you get the bulk of it then.
And then path one also has a verification 12 month verification. portion to it and so you get that after the building has been operating for 12 months and you show that you're hitting the energy target that is set by that program. So there's kind of two payments for that piece on the path one. I've not had a project in path one ever not get the incentive they're going after.
There is flexibility on the path one for that verification incentive. It doesn't start like day one that you move into the building. you can choose when you start that 12-month verification. Typically, it's after all the commissioning is done, which typically is not done that day one for occupancy, so you get time to decide when you start that date of 12 months.
Typically, we see projects started within 6-12 months after occupying the building. The federal incentives, as you're probably aware, are newer. They basically were created at the end of 2022. So there are some projects that are going after those incentives that were really essentially in construction or finishing design around that time, because again, it has to be placed in service before you can apply to get those.
But there are some projects that were in that calendar timeline between I guess, almost two years ago now. Maybe I will apply for those. And then they go to 2032. So right now, those federal incentives go up to 2032, and they're not guaranteed after 2032.
Speaker 9 (12:18–12:31)
Scott, you had your hand up, but it went down, so I didn't know if you still have a question. My question was about Path 1, but I can't answer that.
Speaker 1 (12:35–12:38)
Yeah. Any other questions? Yeah. Aqua.
Speaker 10 (12:41–12:47)
You mentioned something about the federal incentive. Is that part of this 9 million projection?
Speaker 6 (12:48–13:37)
Yes. So I don't, sorry, I can't, I'm not sharing, so I can't move my mouse, but you could highlight that it's the second blue line, blue row. That's the federal incentive there. Um, For ground source heat pumps, air source heat pumps are not incentivized.
So you'll see a zero on the right hand side. That's the federal incentive. There's also, I did put 700,000 in here for solar. So that would be if you installed the solar system, I estimated it to be equal to the energy use of the building.
So essentially a net zero building, that's what that number represents. So that's optional, like you wouldn't, you know, we haven't said that we're definitely doing solar on this building, but that gives you a sense of what the potential impact of incentive on solar would be.
Speaker 10 (13:39–13:46)
Just so I'm clear, the federal incentive is the $6.8 million, is that correct? Correct.
Speaker 6 (13:47–13:53)
And the 714 is also a federal incentive, but that's specifically to solar.
Speaker 10 (13:53–14:10)
Okay, so we're looking at more than seven million in federal incentives. Is there a possibility that, just playing it by ear, government changes and that incentive goes away, and a projection is on this incentive? Is that possible?
Speaker 6 (14:11–14:34)
I mean, these are passed by Congress, so Congress could always choose to pass a law to change the law, but it isn't something that could be easily changed by like a regulation or an executive office, administrative change. It would have to be a congressional law to change that. Right now, the law that was passed, these are until 2032. Thank you.
Speaker 7 (14:36–14:45)
Yeah, and John? Is net zero a condition for the MassFED rebate?
Speaker 6 (14:47–15:08)
It is not. So the Path 1 rebate, is the net zero or net zero ready pathway. And so that's just hitting an energy use intensity that we talked about last time of 25. But you don't have to do the solar piece of it.
You don't have to commit to even doing that. It's just you're hitting the energy side of the equation without necessarily doing the renewable side.
Speaker 1 (15:11–15:25)
Yeah, that's one of the things I was gonna ask too, Kate. So for the solar that's there, Could there be a potential to do a power purchase agreement, basically a third party lease for some of this? And I believe a couple of the schools we went to had that.
Speaker 6 (15:27–15:44)
This is just showing it as if you owned the system and were taking advantage of the incentive, but you could also purchase them in other ways, like a PPA. And so the incentive wouldn't be direct. It would be part of the negotiated cost of your PPA.
Speaker 1 (15:46–16:03)
And then similarly, you know, if we just didn't do renewables at this point as part of the project, it looks like it would just be on the estimated construction costs take off about $2.8 million or a net of about $2.1 million on that overall bottom line.
Speaker 6 (16:04–16:09)
Yep. You could just cross it out. It doesn't change the other numbers. None of the other numbers are contingent on that.
Speaker 1 (16:10–16:58)
Yep. So one of the things too, I'll just mention for all the members too, is like the exercise we're going through right now isn't to make, you know, quote unquote, hard decisions of exactly the path that we're going. Um, this is to plug in, uh, for the estimator, uh, for them to kind of develop their overall project estimate on here. If say come the fall, we decide that we don't want to do a ground source heat pump and we want to do an air source heat pump that's shown there.
We still have the opportunity to kind of go in that path early on in the design. But I think what we're looking to do now is try to figure out what our set budget's going to be. And then based on that budget, allow the estimator some direction on how to crunch the remainder of his numbers that he's working on.
Speaker 6 (16:58–17:49)
Yep. If you go to the next slide, this is just the summary chart that we looked at last time. We had talked about essentially three systems, the ground source heat pump. We talked about a variation of the ground source heat pump that didn't have full cooling.
And the consensus I was hearing last time was that that wasn't an option. So that would be the second one here. change the tire or cross it out, but that's the second one. We talked about that because of the not full cooling, that that really would come off the table.
And then the VRF, which is the air source heat pump system that was on the previous slide for the incentives. And we also talked about the heat pump, chiller, electric boiler as well. So this is just a review of those systems we talked about last time.
Speaker 1 (17:50–18:10)
So one other question I have too, Kate. So for the ground source heat pump that we're looking at, our last meeting, we decided on option two, which are two separate buildings for preschool and middle school. Will the ground source heat pump be providing conditioning for both buildings or would it just be for the middle school when we do something separate for the preschool?
Speaker 6 (18:10–18:31)
It'll be for both buildings. We actually have a slide on that. I think it's in three more slides. So we can hold that question till we get there, or we can jump to that now.
Um, because we did, we, um, we walked through, like, what would that look like for two separate buildings, how they would tie together? It wouldn't be two separate systems. Um.
Speaker 1 (18:32–18:35)
That's fine. It will get to it when it comes around.
Speaker 6 (18:35–20:18)
So, this is just again, the pros and cons high level that we talked about last time. You go to the next slide. We had also talked about this slide last time that was sort of showing you comparative sort of on the scale of best to good, best being the filled in circles, good being the dashed circles, how they compared to each other. And then if you go to the next slide, wanted to just show an example, because there were some specific questions just about how do we numerically start to compare some of those.
And so this is an example from a statistical cost assessment that we recently finished. So these are relevant numbers, but it's a different project. So it's not the same size project. So it's just for comparison purposes from one system to a next, not specific numbers to this building, because this building is a little bit different scale.
And so you'll kind of see that these numbers are relatively in line with the same thing that we talked about on the previous or the two previous slides. The incentives of the ground source is about 25% more expensive than the air source heat pump or the VRF system. So this just gives you a sense of how that played out on another recent estimating project. So you can see the energy cost, the annual maintenance costs, the capital costs, both with and without the incentive on those last four columns.
This gives you some numbers to compare as opposed to just comparing from the qualitative circles that we had.
Speaker 1 (20:19–20:33)
So, 1 of the question I have to Kate, so, like, you know, for us, this is, I think, for a lot of us are for a school building project that we're doing, you know, but for your guys portfolio, you know, what's what's the typical trend that you guys are seeing.
Speaker 6 (20:34–21:38)
I would say the majority of our public school projects are going for the ground source heat pump system. This is, you know. With the incentives, the additional incentives now, that's definitely more the case, but even before any of those incentives existed. So we're generally seeing people do the ground source heat pump.
Again, it's because it gets that energy use intensity, it's lower operational use. Um, you know, over time, it's more incentives up front, but then also over time, um, it is less expensive. Both on the maintenance side and the utility cost. Um, side of it, so you can see the, like this example, you can see the energy costs.
Dollar 26 versus the BRF dollar 41. And you can see the maintenance costs, um, 66 cents for 75 cents. Um, these are per square foot numbers. Um, so.
Not only does it make, it's always sort of made sense from a long-term operational look at it, but now with the incentives, it also is less expensive from the first cost as well.
Speaker 1 (21:43–21:47)
Right. Any, any other questions from members?
Speaker 2 (21:52–22:19)
Right, not seeing any, so let me just stop sharing for a moment and just go back to the agenda. Sorry, just pull out the agenda and just jump after I stop sharing my screen.
Speaker 6 (22:19–22:42)
Um, so next we were going to go into Dave and he was going to, um, kind of talk through that. Like, what does this mean for 2 separate buildings? How do how do you, um, make sure that you're not. Increasing costs by having 2 separate and how does the systems work together?
So, I think if we kind of go through that. And then we can kind of circle because it obviously relates to what we just talked about with the systems.
Speaker 11 (22:49–22:54)
Right.
Speaker 12 (22:54–25:16)
So, for all intents and purposes, we're designing it as one building, the heat, the hot water and chill water plant will essentially be in the main building. and we'd run the piping between the two buildings, most likely in a trench, to service the pre-K wing. Now, the air system, obviously, will have separate rooftop units for ventilation. They'll be separated based on the building, so those will be separate, but that would be the case either way if it was a separate wing.
The communication system as well and the building management system, the entire building will be fed via fiber optics between the two buildings. It's very little conduit, very little piping between the two. It's essentially being priced as a single building at this point. There's no inefficiencies that we see at this point.
As we study different systems, maybe the VRF, may have another unit closer by, but there's no real inefficiencies with the two separate buildings that we see at this point. I think that's the main thing that we wanted to get across. If you go to the next slide from an electrical standpoint, Yeah, so we'll come in with a main service in the main building, and just sub feed that other building through a trenches, it'll be a, you know, pretty small service to get that to that pre K building. Same thing with the communications, it's just a, you know, fiber optics between the buildings so that the two buildings communicate with each other, you know, security system will be on the same network as the ATC system so There's no, you know, real inefficiencies like I said, you know, with this system as well we wouldn't be bringing in multiple services, unless for some reason one building wanted to be needed from another.
The other system would be the fire alarm system. You'd have one main firearm control panel where we put a transponder in the remote building. And we'd obviously have further discussions with the fire department to talk about what happens when one building goes off versus another. If they want to dump both buildings, if they don't want to dump one building, that's all done through programming.
So there's no additional infrastructure that you'd have to put in to make that happen.
Speaker 1 (25:21–25:29)
All right, any questions from members just in regards to some of the MEP stuff that was just discussed?
Speaker 2 (25:35–25:38)
All right, not seeing any.
Speaker 1 (25:38–26:12)
So I think what we're looking to have tonight is to provide, we've been trying to get there for the past couple of weeks, and I appreciate everybody jumping on, For the past couple of weeks to jump in these meetings, but I think what we're trying to do tonight is get some direction for the architects and the also designers. In regards to the systems that we're looking at. So, for me, I'm, I'm, I'm looking for from you guys for feedback on kind of which direction we want to go with this.
Speaker 9 (26:19–26:32)
Yeah, Scott. Personally, I like the ground source with the with the heating and the chilling both. Seems like the best option for the long term future.
Speaker 3 (26:34–26:35)
I have the exact same comment.
Speaker 11 (26:40–26:46)
Yeah, John.
Speaker 7 (26:46–26:48)
Me too, exact same comment.
Speaker 1 (26:52–26:53)
Dr. Miranda?
Speaker 4 (26:54–26:57)
I agree with that comment as well.
Speaker 1 (26:57–28:16)
All right, we get into a consensus. I see Mark smiling, so I think I already know how he's going. Yep. And, you know, I think, you know, I was skeptical of a ground source heat pump.
You know, when we did the interviews with the architects, I think Kate will remember I was a little, you know, all electric building, ground source heat pump and stuff like that. I was a little skeptical. the free money, as you put it, you know, for the federal tax incentives is staggering. You know what I mean?
I experienced, just on my own personal note, you know, I just leased a new car as a Tesla and, you know, free money down for the lease made it, you know, very palatable. So, you know, having this opportunity now to kind of do this here is nice. On one of the site walks that we did, I think it was the Acton building, Larry, that we went to, you were nice enough to take me into the mechanical room there. So you could actually see the system in working, talk to their maintenance folks that were there, and that's what kind of started to get me turning on it.
And then, Kate, your numbers tonight and everything there, I appreciate you diving in a little further. from the commentary we had last time, but yeah, for me, I'm fully in support of it. So, and Tim, I apologize, I didn't see your hand up.
Speaker 13 (28:16–29:05)
Oh yeah, that's okay. I put my hand up when you were talking there, Sean. So, no, I found all of that very compelling and I appreciated diving into some of the ancillary systems that, you know, were looked at and we're gonna experience no inefficiencies in kind of bridging those, over to the other building as kind of an umbilical. So that all sounds good.
The one concern I do have, Sean, is like early on, we had talked about the need to upsize emergency backup generation. I know that's kind of like an area of expertise of yours. So I'd love to get your thoughts on that and maybe in conjunction with the designers. But I mean, this was all very compelling.
I'm very much in support of moving forward with the ground source. I just would appreciate your thoughts on that.
Speaker 1 (29:06–29:09)
I'll jump in right after Aqua talks too.
Speaker 10 (29:11–29:57)
Like everyone else, I like the ground source. My only concern is the, this is based on a federal feedback and I'm concerned that if we don't get the money, Is there a chance that we don't get the money? I don't really understand the process, especially since ours would not be completed until seven years from now. Will that money, free money still be available to us at that point or five years from now?
So looking at it from that point of view, I have some concerns, but I see the benefits. I think we're really putting our eggs on this federal money here.
Speaker 1 (29:58–30:24)
Just just a clarification to you as Aqua. So, you know, for us, you know, my hope is we're still on track for a twenty twenty seven opening. So that's you know, that's the project schedule we've been trying to hold for all this. So, you know, if we were to hold that, you know, that tax incentive would still be there.
You know, I think you said twenty thirty two it expires. Is that correct?
Speaker 6 (30:25–30:30)
Yeah. So the current regulation is through 2032. Yep.
Speaker 1 (30:30–32:07)
So that, that would be, you know, essentially an additional five-year window for, you know, the built-in schedule that we have now. So, you know, I mean, if, if for some reason, you know, we got accepted to MSBA and then went into their program, I think we'd be out of the seven year timeline for there. Um, but you know, our current timeline is to have the school built and operational by 2027. Thank you, Sean.
Yep. So yeah, Tim, in regards to like the electrical backup and stuff like that, yeah, that doesn't deal with the ground source heat pump or anything like that. It just deals with the all electric building and basically having a slightly larger emergency generator there to basically make sure that the heating of the building is still There in the winter, in case you have a loss of power or something like that, whereas if you had a gas service that provided you heating, we can dive into that further. But I think the small upcharge for a generator, because I dove into this a little bit when When we adopted the opt-in code, I talked with Alex Hasha, that's the chair of Sustainable Milton.
And when we went in front of the Warren Committee, I actually laid out some of the pros and cons for it. And to upsize from an 800-amp switchboard to a 1,200-amp, or if it's, there's probably fat already built into the infrastructure that's there that can accommodate it. So to upsize the generator isn't that much.
Speaker 12 (32:07–33:10)
Sean, I can actually speak to that if you don't mind. So essentially the service is going to be sized for an all electric building no matter what. Even if you were to have a gas service, if you're opting code, if you want to meet that 3% from MSBA, we have to size that service anyway. So you're not saving anything there.
You do save on the, like you said, the generator is going to be larger to pick up those, the heat pumps. And we actually, We don't put the entire heat pump system on, we've actually used BMS controls to put maybe three sections, modules of the heat pump on that can maintain that freeze protection level. So we're pretty good at downsizing that generator to a reasonable level with the electric buildings. And when we do study those systems against each other, air source to geothermal to VRF, and if we did study a non-all-electric, we would actually take that generator size into account.
So as we move forward into that process, you're going to see those numbers, and that's going to be built into the estimate.
Speaker 1 (33:12–33:13)
Excellent. Thanks.
Speaker 6 (33:13–33:37)
Yeah, because, you know, right now, what we're talking about is budget, setting a budget, but then we'll be doing the full bicycle cost analysis later, like that example chart we showed. And in there, if there's any costs associated with electrical upgrades, those all are part of that bicycle cost assessment. It's not like 100% just the HVAC side. It will have any electrical impact if there is any between the different options.
Speaker 1 (33:40–34:09)
All right. Jim, that answer your question? Right. Perfect.
Yep. So, so Kate, Shanali, I think, you know, basically heard essentially, you know, outside of Glenn Hoffman, you know, essentially unanimous in the direction, I think we want to go with this. So, you know, I think, I think for, for that end of the agenda, we're good. If you guys have anything else.
Speaker 5 (34:10–34:24)
Thank you. This will help us move forward. Dave will be able to continue with the narratives and be able to get more precise information into the cost estimate. So this was really helpful.
Thank you.
Speaker 1 (34:26–37:37)
Okay. All right, so on to item five, which is new business, and 5A is a land swap update. So as everyone knows, at our last meeting last week, there was some progress done from the Executive Office of Energy and Environmental Affairs. They submitted a letter back to Senator Timilty finding that the resource value of the replacement land was equal or greater than the land we were trading out.
So essentially, the land swap was a good thing. Since then, the Senate has moved on that. They've engrossed the bill. And there were some minor edits due to some typos that we ran into with town council and the Senate council had a couple revisions too that made a reference.
So we just, it all got cleaned up and I appreciate Senator Timothy's help on that. It's now a new bill mainly for the edits they made and it's bill S2840. Um, and that 1 is now moved out of the Senate and is over at the house and it's into a committee now. So, we've been, I've been in touch with, um, representative Driscoll represent and represent fluke.
And, you know, they're, they're working at pushing this through. So, you know, it's, it's. it's moving so out of the uh letter that senator timothy provided us or the step-by-step process uh with 15 steps we're now on step 12. uh step 15 is signature by the governor so you know we're almost there so it's good so um i'll open up to see if anybody has any questions or anything like that and i'll do my best to answer from you know what i know seeing none all right Um, so move on to, uh, item, uh, 5 B, which is discussion update space utilization and space adjacency.
So, um. In addition to these meetings we're having every week with us as a school building committee, the architects are meeting with the district consistently now for probably the past four months, a couple of times a week, working through the stuff that they're presenting to us as a committee. There's a lot of background work that's going on during the days while we're not meeting. Essentially, that's why we hired consultants to do that work.
So, we appreciate it. We appreciate the funding we got to do it. So, what you're going to see now is kind of an outcome of some of that work that's been done. So, as you guys know, we started the visioning sessions that the architects work with the district leadership team.
they put everything out there that they wanted. And we had this nice, big, enormous building. And we've been working, working, working over the past, probably like four weeks, four or five weeks to really scale this back, to get it to the right size school that we need there. So it's like a balance of, you know, trying not to make it too expensive and also make it work educationally.
So I think they found that balance. And with that, Chanel, do you want me to keep presenting, Chanel?
Speaker 5 (37:37–43:34)
Yeah, that would be great. We're going to have to do a little bit of zoom in. I'm just going to warn everybody these slides are really text heavy. So, essentially, what we did in the first slide that you're going to see is we track the timeline of the reductions and some of the caveats that were made to understand how we got to those numbers.
So that very first column where it says initial study, this came from the presentation that a previous architect did, and they came up with a rough 115 to 120,000 gross square footage. I did not, we did not get an explicit program from them. So there's some assumptions that we made on how they got to that number. But our understanding is that it does not reflect the 14 structure.
It does not include the auditorium, world languages, and any of those additional exploratories. If you look at the next column over, which is the MSBA, that is just for the middle school and doesn't include the preschool, and that's 112,000 square feet. And your initial study was 115,000. So there's some ways of breaking down the square footage that something was not included that the town of Milton really needs.
So the MSBA, again, doesn't include the auditorium, the world languages. It does not include the pre-K and it does not reflect four teams. So that's how they were able to land at that 112,000 gross square footage. So then this is when Arrow Street enters, right?
And we did these visioning sessions with the educational planner. And we met with the teachers and we met, you know, with some of you on the school building committee to talk about what are you thinking about for the middle school? What do you see? What do you need?
What's operating at a deficit in the current middle school that you need to see in the new middle school? And that's how we came to the 202,000 gross square footage. And that included the auditorium, the six world languages, the exploratories, increased teacher support, planning spaces. And a lot of those spaces, again, were not reflected in the MSBA gross square footage tally.
There were extra classrooms in the preschool. I think they had asked for nine. So there was, That was what we were working with to understand what you needed or what the faculty, the teachers felt that they needed to operate a peak school. So then we had to get realistic about what does that mean?
How do we make this work budget-wise? How do we give you the best middle school, but also be pragmatic? And this is our, that next column that Sean is pointing to is our first revision. We right size the spaces.
We looked at the size of the classrooms. We looked at the size of the offices. We looked at the size of the auditorium and we became really efficient with those sizes. And so we were able to take out some square footage there.
We decreased, I think we had four STEM steam rooms. We decreased one of those classrooms. We removed a health classroom and a drama classroom. And that came about because we got help from The educational planner, Sean Burke, also did quite a bit of work here along with Bill Fish, the middle school principal, to find utilization so we could find the rooms that could do double duty.
And that really helped us bring down that square footage from the 202 to the 168. So highlighted in red is where we stand now. And we made more cuts, so to speak, to get to that 152. This version is three and a half teams per grade.
So a total of seven teams, where in the previous version, it was eight teams, four teams for the seventh grade and four teams for the eighth grade. In this version, there are three teams for the seventh, three teams for the eighth, and there'll be one flexed team. So if you have a spike in the enrollment, that extra seventh team can flip side to side what your enrollment numbers are. We also reduced from six world languages to four world languages and I think we did another And the last big thing that helped reduce the size is we increased the lunch cycle from two cycles to three.
So when you increase the lunch cycles, it actually reduces the footprint of the cafeteria because you have less students in the room at a time. So that was a substantial savings of 1,500 square feet. The other thing that we did in the preschool from the 27,000 to the roughly 25,000 is we right-sized the back of house. janitors, storage, we had extra square footage in there because we were duplicating services from the middle school.
And this is when we started to really look at the program. And we were able to cut out some of those extra spaces, like there isn't a giant storage room in in the preschool, that will be all stored in the middle school. So we were able to combine those spaces and find some additional efficiencies. And that's how we landed to this 152.
And that's where we landed as of last Friday.
Speaker 14 (43:34–44:18)
I'd like to just add one point to what Shonali was explaining, which is that when we noted reduces to four world languages, that's not a reduction in the actual number of languages that are offered educationally. This was talking about how many dedicated classrooms needed to be planned for in the building. And through digging into the utilization and understanding how the schedule of the building could function and reviewing that with everyone, it seemed like it could work with four classrooms. It's not that there's only four world language classes being offered.
It's that it's just four classrooms.
Speaker 1 (44:23–44:43)
One other thing I just want to mention too, Shanali, the reduction from the visioning down to the other two in regards to the preschool, I think, and correct me if I'm wrong, during visioning, the preschool was envisioned to be full day preschool, and that's why it was around 33,000 square feet.
Speaker 5 (44:44–44:49)
Correct, correct. That was a big impact from that 33 to the 27.
Speaker 1 (44:50–44:57)
Yeah. And then, you know, for special ed spaces, we've done our best to hold everything that was requested for the most part.
Speaker 5 (44:58–45:28)
Yeah, I don't believe that we've removed any special ed spaces. We did right-size a couple of the spaces. We had them as full-size classrooms. And then after talking to Bernadette and some of the other teachers, we realized that that was too large.
They didn't need it. That was just a miscalculation. So we were able to reduce them from a full-size classroom to a half-size classroom. And I think that happened to two or three special ed spaces.
Speaker 1 (45:29–45:30)
Any questions from members?
Speaker 10 (45:40–45:58)
Yeah, Aqua. What is your biggest concerns? This is to the architect moving from the 168 to the 152. Do you have any concerns that you want to share with the committee?
Speaker 5 (46:01–46:06)
in terms of the cuts or the right sizing of the spaces?
Speaker 10 (46:06–46:15)
The right sizing of the spaces. Do you believe it will affect the delivery of services as initially intended at the 168.8?
Speaker 5 (46:16–47:24)
I don't think so, but I think it really depends on the principal and the teachers and the way that they're utilizing the spaces. I don't think as the architects that we're able to to predict that because we're not with the students every day, but based on what we're hearing from the teachers, we're not seeing an increased percentage in the utilization. And Sean Burke may be able to speak to this a little bit more clearly because he dove straight into the numbers. But there's a percentage of utilization where you look at the classrooms, you see how many times it's occupied throughout the day based on their enrollment numbers.
And Sean worked with Mike and Bill Fish and found that those enrollment numbers or rather, excuse me, those utilization numbers were pretty consistent with standard practices. I don't know if that fully answered your question.
Speaker 10 (47:25–47:28)
Sean, can you add some thoughts to that?
Speaker 1 (47:28–48:51)
Yeah, sure, Aqua. So the one thing to keep in mind is, you know, we weren't working in a bubble. You know, this has been vetted throughout the district with the superintendent principals, you know, and the principals in relation to the teachers to, you know, The, you know, the, as we're saying the visioning, you know, the middle column that you see here was, you know, we put all the teachers in a room and said, you know, we're going to build this new school, what do you want in it, and opened up, you know, the door to everything. And then, as we started doing that, that opens up, you know, if someone's asked you to design your perfect house, you would want everything, you want a pool, you want this, you want this.
And then, you know, as you start realizing what the cost of these things would be, you know, that's where we start, you know, let's bring it back a little bit, but we still want to make it so that the building that we're building will work educationally. So for me, I think the only concern I would have is, you know, going from three, eight teams or four teams per grade to four and three. I think that's one of my things, but, Talking with Bill Fish right now, the way they're operating the existing middle schools on a similar program. So he's making it work there with similar size classes or class grades that we're seeing.
So he's pretty confident he can make it work in the school too.
Speaker 10 (48:53–49:06)
Thank you, Sean. I just hope that we're not that this building would be sufficient for Milton for the next 20 or so years, that we don't make it just a little too small, that we have to really do this process again.
Speaker 1 (49:07–49:17)
Yeah, and that's that's something I want to talk about too is, you know, as we start expanding or jumping into the, the, the spaces that are here too. So, right.
Speaker 15 (49:19–49:52)
Sorry, just to just to put things in reality, the current Pierce building, which holds 3 grades, 6th and 8th is 150,000 square feet. So, this new building will hold only 7th and 8th at 127,000 square feet. So a little bit smaller than the existing Pierce, but if it eases some concerns, just to say that it is a, for the amount of students and the amount of grades that are in there, it is larger per grade than they are currently in. So it's hoping to ease some of that overcrowding that they're seeing in the current Pierce by providing additional space.
Speaker 2 (49:58–49:59)
All right, John, thank you.
Speaker 7 (50:03–50:32)
My question is similar is we went into this with the population looking for eight teams. How much are we sacrificing going to seven? And the other question too I had was I went through the Cunningham with Mark and one of the biggest questions was the lunch cycles and how much of a sacrifice is it going to three lunch cycles?
Speaker 1 (50:36–50:42)
Yeah, so Shanali, do you mind talking about the three lunch cycles?
Speaker 5 (50:43–52:14)
Sure. So we did, again, I just want to reiterate as what Sean said earlier, this was all, all of these suggestions came from the working group. Like we're implementing these changes, but these are the ones that they're putting forward. So basically what happens with the three lunch cycles is typically for the two grades, you'd have all the seventh graders go for lunch, and then you'd have all the eighth graders go for lunch, and that's your two lunch cycles.
But in this scenario, you'll have two thirds of the seventh grade go for one lunch, And then you'd have a mixed lunch where some of the seventh grade would mix with some of the eighth grade in a lunch cycle. And then your third cycle would be all eighth graders. Bill Fish, I think, you know, said he could make it happen operationally that there's currently three lunch cycles at Pierce and he knows how to organize that. But that does, substantially decrease the size of the cafeteria.
And again, it goes back to, what are the values of the school? What's the educational programming? Is there a preference for the two lunch cycles? Do you want all the seventh graders to eat lunch together?
Because that's a different philosophy for the way you wanna run the school. And as the architects, we can only speak to what that means for the space, but not for what Milton's vision is for the middle school.
Speaker 1 (52:15–54:07)
So one other thing I'll jump into too, John. So with Collicott Cunningham, the total population that's in those schools is a lot larger and they all share that one cafeteria that's there. So there's more of a rhythm of them going in. That's what's made that window for lunch for them expand so much.
And that was part of the reasoning where thoughts were, a couple of years ago, we were looking at alternative options you know, adding on to schools and building them out and making them bigger with classrooms of the existing facilities. The cafeteria became the pinch point for all that stuff. So if we expanded schools and put a bunch of classrooms on there, it would screw up the lunches there. For this one, we're only talking about two grade levels that are there and a smaller population.
So the rotation of them in there, we didn't think would be a problem. The other one that you mentioned as far as going from eight to seven teams, when we looked at this too, The teams that we had there, if we go back, I think it's four meetings ago, where we had the bubbles of the teams and the classrooms that are associated with them, the world language classrooms that are there are additional classrooms that are off there that, when we look at MSBA, weren't accounted for in there, and that's, I think, why you see some differentiality there. um you know of about 16,000 square feet extra that we have in there so you know as we were going through this um you know we felt and along with the district um that you know reducing that one team down and have still keeping those world language classes there allowed us some flexibility that would allow them to adjust i yeah i just wanted to be careful that
Speaker 7 (54:08–54:29)
you know, coming from residential, I know the same thing. The first visioning was in a perfect world, this is what we'd like to get. And now we're at a reality world. But in some cases, and even in the residential, when you get to the reality world, you want to make sure it's still what you originally wanted.
Speaker 1 (54:30–55:43)
Yeah, and that's exactly why we've been working with the district the entire time. So, you know, if it was myself, Shanali, and the other Sean locked in a room, I would, you know, I'd be a little concerned about it. But, I mean, we have been, honestly, probably the past Two months, you know, the visioning sessions occurred, you know, February, probably up till April, you know, with some site visits to two middle schools and two preschools in there. And then using all that there, we've been working over the past couple months.
using that visioning to define, you know, what they want for spaces, and then have them try to understand, you know, part of it is asking teachers to understand the difference between a 1200 square foot classroom and 1000 square foot classroom, you know, I mean, they, they don't, and that's kind of this last exercise we've got to we've really tried to hone in on ways to really skin this down to the what we think is the most appropriate uh square footage there while still maintaining you know educationally something that's going to work okay um dr miranda
Speaker 4 (55:46–57:18)
Yeah, no, I was gonna express actually a similar concern to Aqua and John that I would hate for us to, well, I mean, the three lunch cycle does worry me a bit in terms of how much more room do we have should the population increase in the future, right? So that's one thing. Are we creating enough of a buffer? for potential growth and also making sure that from a student experience that we're not having them have lunch at an insanely early time.
That happens already at Cunningham. And I can tell you that it doesn't do well for the kids. I've heard many stories of kids just not eating because they're not hungry so early. And so that is a concern of like, are we thinking enough about the future and not just the present?
And I think it's hard to, you know, when I think about Principal Fish and others who are right now that the answer that you've got is exactly it. We're going to make it work because that's what they've been doing. right, that they can make it work. And so that for me, it also concerns me a bit, because it's the reality they have right now.
So if that's the lens they're using, I understand why we want to get to a size that will reduce our costs. But I do want us to think from a future perspective as well.
Speaker 8 (57:22–58:26)
All right, Mark. Uh, hi. Sorry, my, uh, can't start my video because I got kicked off. My kids interrupted my intro.
Um, so I, I hear those concerns. Um, I think that's all fair. I think, you know, at the end of the day, we needed to cut square footage, in my opinion, because I think the building was just too big. And as we think about how residents are going to respond to this, and right, and how we get to a place where we can Um, get support across our community for this in order to get any space, because ultimately residents vote this down.
We get zero square footage of additional space. Um, then I think we need to make sure we're going to them with a plan that says, you know, justice of like, Hey, we have been mindful of costs. The primary driver of cost of square footage, and we've gone through multiple iterations of trying to cut that cost to put this in line with MSBA. I would ask, I think I remember, Charlie, that the auditorium was at 30,000 square feet?
Speaker 5 (58:27–58:29)
No, 3,500. 3,500.
Speaker 8 (58:29–58:32)
Sorry, I don't know why I said 3,000. I meant 3,500.
Speaker 5 (58:33–01:00:23)
Mark, go ahead. No, I'm sorry. I was just going to say, I actually have one more slide after this that talks about some of the MSBA metrics and how we fall into line with that. And I'm wondering if we could just jump to that slide.
Thank you. And maybe this will help people understand where Milton is falling in line. So this top bar is the last five middle schools that you can see the third row, or sorry, the third column that they're starting construction between now and next year. So these are the current middle schools.
And then the enrollment is the next column over. And so Clinton and Whitman Hanson are pretty close in line to what the size of the Milton middle school is the middle school is 670 enrollment and the preschool is the 130. So then you look at the gross square footage for each of those schools and you can see the average is 194 and 205. And if you look at the total of those five schools, the average is about 186 square feet per student.
So then if we scroll down a little bit, Sean, thank you. So for the, Two, we had two revisions, one at 168 and one at 152. So if we look at the 168, our average comes out to 211 square feet per student. But if you looked at the further revised one, the 152, we're at 191 square feet.
So we're right in line, we're right in target with the earlier middle schools that you'd seen up above. Like we're right there. So that to me was another gut check of like, is this the right size school?
Speaker 1 (01:00:24–01:00:29)
I think there are a couple of questions going on, Sean. Yep. I'll let Mark keep going and then Sean's up next.
Speaker 8 (01:00:30–01:01:38)
Yeah, I really appreciate the slide. The slide's very helpful to, again, just put it in context of other places. I do have the question of, I'm not that concerned about three lunches, because if you assume a lunch is 30 minutes, right, three lunches, and that includes transition time, three lunches is an hour and a half. You know, gets you through them and very reasonable 1130 one o'clock range, I think, as people have said the issue with Cunningham Caldecott is there at like six lunches, and so they're going from 10 o'clock to two o'clock.
And also cafeterias are some of your most underutilized spaces throughout the day. So if we can increase utilization in places where kids are actually learning and not places where they are 25, 30 minutes in a day, I think that, in my mind, is the priority. I do wonder, just to the point of the cafeteria, based on the square footage, what do we expect I know that somewhat is dependent upon design, but in terms of like total number of students that could be seated within a space of that size, what do we think that is?
Speaker 5 (01:01:42–01:01:57)
I think Sean Burke has those numbers. He ran through, Sean, correct me if I'm wrong, it was 700 students for the max enrollment for the school.
Speaker 15 (01:01:57–01:02:54)
Actually, Mike Perla had a chart that went through all the different scenarios, and I think one of the things I wanted to point out as well on this is the 670 that we're all looking at here, that is not the current enrollment of the 7th and 8th grades of Pierce. 7th and 8th grade of Pierce, I think right now is 606. So just to keep it in perspective, when we talk about making sure there's room for expansion and making sure there's room for growth, that growth is already built into that 670 number. So I just want to make sure everyone's on the same page with that.
We are building in for growth. We do have room in the building for expansion beyond just by the count. You've never had a class of 670, as far as I know, in those two grades. Mike had run different scenarios on that, and I'm not sure where he went up with, but the original one at 168, he had somewhere closer to 800 kids you could fit in that school if you needed to.
Speaker 1 (01:02:56–01:04:22)
Yeah, so just for people's understanding too, the way, and Shanali, correct me if I go wrong, but for the MSVA square footage you get, there's a spreadsheet that MSVA has with built-in formulas. You plug in your student enrollment, and then it back populates basically your spaces in there and tells you, you put these spaces in, you can make a school work. Correct. Yep.
So with us, I'll go back one slide. When we put the population number in just for the middle school, we were at 111,000 square feet with 670 students. And that's, as Sean just said, a little bit higher than what we currently have at the school right now. Um, so, you know, we've got an extra 16,000 square feet in there that's built in.
So, you know, as far as. Capacity or future capacity in the building, you know, we, we've definitely accommodated for that. For me, I've always been cognizant since first day on this committee that whatever we're building for this, we want to make sure we have expansion room in there because as everybody knows, we don't have any more land to build another school later on. My goal is to get this one right.
Keep going on the slide, Shanali. We'll get into it.
Speaker 5 (01:04:22–01:04:29)
So this was the last one on the utilization. And really, this was just an update for everybody to understand where we landed.
Speaker 8 (01:04:31–01:04:43)
Sorry, just to clarify my last question. It was related to the cafeteria itself. If we cut square footage on the cafeteria itself, do we know what the capacity of the cafeteria space would be under the new square footage?
Speaker 5 (01:04:45–01:04:47)
You mean like the population?
Speaker 8 (01:04:48–01:04:59)
Yeah, just the assembly space. I know that's not necessarily exact numbers because you don't have a design.
Speaker 5 (01:04:59–01:05:35)
Let me tell you what I know here. So when we originally ran the MSBA numbers with the enrollment of 670 with two lunch cycles, your cafeteria came out to 5,000 square feet roughly. When we increased the lunch cycles from two to three, your cafeteria size dropped down to 3,500. And I don't know if that's answering your question precisely, but that's the reduction came, that's how we got to the reduction.
Speaker 11 (01:05:35–01:05:42)
That's helpful. Okay.
Speaker 16 (01:05:42–01:05:50)
So Mark, that ends up about 15 square foot per student with about 233 students per seating.
Speaker 8 (01:05:55–01:06:01)
Yeah, which with three lunches would get you to about three, 700 kids, right?
Speaker 5 (01:06:01–01:06:05)
Correct. Thanks for doing the math, Larry.
Speaker 16 (01:06:05–01:06:56)
Yeah, no, and that's about a standard number for tables and chairs is 15 square foot per student. And I think just to go back a little earlier, somebody had asked about the seven teams versus eight teams. I think there was sort of a question and I think still to be resolved on our end is how does that middle team, if you will, get located in a way that it can swing in either direction. So some years if you have a high population in seventh grade, it's a seventh grade team and other years it's an eighth grade team, or maybe it gets split down the middle and it's extra classrooms for either grade.
So I think there's some flexibility in that as long as we can sort out how to lay it out in terms of the building so it's really flexible and usable.
Speaker 1 (01:07:00–01:07:02)
Do you want me to proceed, Shanelle, to the adjacencies?
Speaker 5 (01:07:03–01:07:04)
Yeah.
Speaker 14 (01:07:04–01:07:15)
Actually, I think if I could jump in, I might try to present this just because I'll probably want to point this out. So let me try and hopefully it works.
Speaker 5 (01:07:20–01:08:09)
So while Andrew's pulling that up, just to Given a quick introduction. So last time you saw the sort of diagrammatic plans of how the spaces were going to be laid out in terms of where the entry was where the gym. where we thought the classroom bars were. These diagrams get a little bit more specific and break down the rooms a little bit further.
Is this showing up for everyone? Yes, thank you. Andrew's going to walk through some of those adjacencies. There was also some feedback about the location of the gym last time that we took into account and adjusted.
I'll just hand it over to Andrew so he can keep explaining.
Speaker 14 (01:08:10–01:21:02)
Sure. Thank you. So you might recall a similar looking drawing to this that we saw last time, but with less detail. And so as Shonali was saying, what we've done is, whereas last week, and I hope that when I draw on this, is that showing up for everybody?
You can see that? Yes. We were kind of talking about it in terms of larger pieces and saying, that's a team, that's a team. And now what we've done is sort of laid out, well, what is the team composed of?
And how do we really start to build these things up? And so you'll see in this diagram and in the plans that follow that a team is, or sorry, the classrooms are represented in the blue, the light blue, and that there's a sort of, very clear pattern of where there's two teams organized next to each other. And they are sort of, in a way, mirrored about a central point. This little orange block that you'll see here is the shared prep room between adjacent science classrooms.
And the sort of dark gray that you see here is the restrooms and a stair core. I'll go through in more detail on the actual individual floors, but I also want to point out that We've sort of in the center of the floor plan in this zone on the upper levels, that's where the strategy is to locate the special education spaces and classrooms in the most sort of central part of the building so that it's the easiest to get to them. And depending on what floor you're on, if you need to get to a space that's on a different floor, it's sort of minimizing travel distances. and so forth.
And so I will, I might come back to this, this 3D view along the way, but I'm going to start with the ground floor and sort of work up the building. So on the first level, One of the big changes from the last time that we showed this level was that we did look at the recommendation from this group to relocate the gymnasium. And we are now locating it here on the sort of northwest corner. Some of the feedback we received was that, you know, when there's after hours weekend events, people will want to park their cars close to the gym, which makes perfect sense.
And so previously the gym was sort of in the back area. We've moved it here. and the hope being that, you know, that way we're making the most use of the larger parking lot that's right off of Kyle Road. So that's one large adjustment from last time.
Another is that this was, and by the way, I just want to preface that these diagrams and adjacencies are still showing and assuming a 14 setup. We wanted to kind of get feedback about the seven team idea before we looked at how that played out. So everything you're going to see is looking at four teams, and we can kind of talk through how a three and a half per grade might play out. So this is the larger cafeteria, which we rotated in order to take advantage of sort of the ability for it to sort of spill out and access green space in this area to the east of the building.
We also went deeper with the development of the layout of the pre-K, and you'll see that we looked at moving the location of the entry. I think previously it was shown either further south or in the midpoint, but actually putting it somewhat closer to the middle school in order to create some efficiencies of, on the one hand, reducing travel distance from the kitchen, which is here, to bring food to the substantially separate classrooms, which is these two here. And also by putting the administration block of the pre-K on the north side, there's sort of a direct path of travel and reduce travel distance between the administrative and medical components of the middle school administration and the pre-k administration. The idea is that each building has its own spaces, but we thought that there would still be, it would be beneficial for one to be able to quickly travel to the other without having to kind of wind through a labyrinth to get from one place to the next.
So those were some of the ideas that were driving how the first floor of the pre-K was starting to lay out. And I will note also that the, you know, It's not labeled here, but this green block here is the sort of gym space, the idea being that that potentially could open out into the green space that's back here and, you know, access to the pre-K play area. Um, we've talked a lot about potential future expansion on the pre-K and in this, um, this version, the idea is that it might actually be better to expand here. The idea being that we have a central stair and, um, elevator and sort of hallway set up that you could then continue that, um, circulation, um, pattern in the future and add on classrooms or whatever other rooms might be desirable.
So that's sort of what was driving that. And I'm happy to zoom in on any of these, by the way, if people want to see it. So turning back to the middle school for a moment, this has the entry still located at the sort of inflection point of the bar with a lobby space and stair that works its way up. And we have our music and art exploratories and STEM, tech and flex still on the first floor as we showed last time.
One thing you'll see as we walk further up the building are there's sort of three vertical circulation cores. There's the central one at the main entrance and then sort of one that's sort of at the midpoint of the two wings. And we think that we're definitely going to need three. We're trying to make sure that we didn't get to a situation where we needed to have four if we could help it.
So I'm going to go up one level now to level two. And here's where you'll start to see two of the teams. So this is seventh grade, team one and two. And I am going to zoom in briefly on this.
just to talk about the organization a little bit. So each team you'll see has four classrooms. And the larger one, the one that I just did number four here, that's the science classroom. This orange block here is the shared prep room.
So this classroom and this one here both benefit from that. That was one of the efficiencies that we realized. And then these small blocks that you see here and here between the pairs of classrooms are these small group rooms, which are intended to sort of enrich the education that's provided in the classroom by giving the opportunity to step out of the classroom as a small group and work on projects or have assistance from a teaching assistant, etc. And then this is looking at developing a shared space between them that is sort of the learning common space for that team.
And so this model is saying that each team kind of gets its own shared space. And the idea is that this would really be a place for some architectural identity for the team and for the school. These would be spaces that really feel like something where you enjoy being. And then you can see, um, here that we've got the, uh, in the pink rooms, we've got the special education programs, um, in the center of the, of the floor plan.
And then moving over to the left, this area here is the media space. And, um, we've also, um, thought about and Bill Fish really liked this when he saw it earlier today, locating the guidance component adjacent to the media center so that it wasn't just that, you know, the sort of go to the scary guidance office, you know, down by the principal and like you're in trouble, that it could be something that's a little bit more informal and be designed so that it felt like a place that you you might feel good about going, and it would sort of just lower the stress about maybe talking about some tough issues. So we like the adjacency possibilities of the guidance being paired with the media center. On the second level of the pre-K, which is, you know, remember, it's not connected, so you can't actually move from the middle school to the pre-K on this floor.
But since we're here, this is, you know, it's an efficient layout. It gives us the seven classrooms, The pink blocks being the small group rooms, similar to what we talked about just now on the classroom of the upper middle school. The orange block is a teacher planning space and some of the special education spaces. So the pre-K is really thought of as a We're being very efficient with the layout and using the connections that we can create to the landscape, particularly on the first floor, to make a special moment for the pre-K.
Then moving up to the third floor, and I'll zoom in here. So this is sort of the, in a way, the most regular floor plate of all, because you can clearly see that structure of the teams. So you've got the third and fourth of the seventh grade teams on the north end here. and the first and second teams of the eighth grade on the west side here.
And you can see the sort of mirroring of the team about that central point, which has the stair and restrooms. and the shared science prep space and the special education at the central point. And our hope is that we can make something special and nice with this stair element. And this could be an additional kind of gathering space with views to the landscape and natural light, et cetera.
I think that there's a lot of potential for how that could go. And then if I go up to the fourth floor, you're seeing the third and fourth, eighth grade teams, same structure as below. Here we've got world languages as a sort of destination location and some special education. I'm looking at this now.
I'm not sure why we didn't just flip these. I think we would have done that had I not just seen it. So you could imagine that the pink, The zone is sort of like this, and the world languages are paired together as a cluster. So again, this is the four-team model, not the three-and-a-half team per grade.
So I'm going to go back to the three-dimensional view here. If anyone would like me to dive in deeper in any particular areas or any questions.
Speaker 16 (01:21:03–01:21:07)
Andrew, can you zoom in on that a little bit?
Speaker 14 (01:21:08–01:21:08)
Sure.
Speaker 16 (01:21:11–01:21:24)
Yeah, I think that should help folks. Thanks.
Speaker 1 (01:21:24–01:22:10)
Sure, Sean. Yeah, quick 1 Andrew, so could you go to the plan view of the 1st floor? Yeah, that one. So I know we still have to have discussions with the fire department regarding the possibility of having the road extended on the backside of the building between the field.
If it became a need to do that, could we eliminate the road to the preschool on the left side of the plan and potentially shift the building over a little more too? Or, or the southern portion of the building, the auditorium, the, the cafeteria and stuff like that.
Speaker 14 (01:22:10–01:22:22)
So, let me make sure I understand the question if we had a road. That did this correct could we could we do away with that? Yeah, and kind of take the whole.
Speaker 1 (01:22:23–01:22:43)
mass of the building and kind of go this way with it is that yeah not the whole mass but basically part of this yeah the southern half of it so the the uh the auditorium the cafeteria and you know everything along that line and just shift that over a little it would just open up more of the green space between the cafeteria and the field
Speaker 14 (01:22:47–01:24:19)
Um, I think that the answer is that, uh, something like that probably is possible. The thing I would just caution about is that there's a pretty good elevation change between here and, um, you know, where the, where the building is. And so, um, you know, putting a road without, unless, unless this whole edge moves a good amount to the West. To put a road in between the athletic field in the building would would mean, you know, retaining wall.
there might be an argument where that's worth it, you know, if all things considered that that makes sense. So that's something we would want to look at because of course, if we did shift the building to the West, that starts to have an impact on our parking here. So, but I think that in terms of like access and distances that we need to maintain for fire department, et cetera, an option that looked at the road as you described it, and sort of, you know, having this loop be like that, we could meet the fire department needs as we understand them right now, because we would have access, and it would only be this sort of western edge that needed to be within the kind of hose distance, which it certainly would be. But I think the question becomes, what sort of hoops do we have to jump through in this zone
Speaker 1 (01:24:20–01:24:58)
vis-a-vis the elevation change. Yeah, because my end, what I'm, what's drawing my attention is any of the I call it green space on the plan. On the left, the triangular area of the site, having an opportunity to have parking over there. Whereas if we could shift the building over a little and introduce parking over there, that may help.
Then along that road, if there was a road that went as you drew there in red, up where your cursor is, we can introduce additional parking up there too.
Speaker 14 (01:25:00–01:25:05)
Yeah, it's a fair question. Yeah, you don't have the answer.
Speaker 1 (01:25:05–01:25:24)
It's just more just brainstorming when I was looking at it. So thank you. Sure. Sorry, Andrew, you can drive and call people.
Sorry about that.
Speaker 3 (01:25:24–01:25:33)
I just was curious, does the media center Um, is that code for library in some way, shape or form?
Speaker 14 (01:25:34–01:25:34)
Yes.
Speaker 3 (01:25:35–01:25:37)
Yes. Okay. I just want to make sure.
Speaker 14 (01:25:39–01:25:39)
Yes, it is.
Speaker 3 (01:25:40–01:25:40)
Thanks.
Speaker 14 (01:25:42–01:25:43)
Uh, let's see, Mark.
Speaker 8 (01:25:46–01:27:02)
Uh, yeah, I think, I mean, overall, I like the plan. I like the layout. Um, I mean, I assume we're going to have to add another staircase or two on kind of the ends from an egress perspective, but I assume that's just. a small thing that you put on the sides.
I agree with Sean. I think anything we can do to, you know, again, outsource spaces I've shared before is so limited on the site. Whatever we can do to try and consolidate it in certain ways or, you know, move parking lots and parking spaces to the outer areas in order to, you know, get back some more green space in places that can be utilized by kids, I think would be ideal. So I think those are great points, Sean.
And I like the adjustment that Kerry suggested that y'all implemented with moving the, separating the gym and the auditorium a little bit more and having the entrance of the gym kind of close to the parking area. I think that's great. And within this current outfit, you could even have maybe an event at the auditorium where they park in the back and an event at the gym where they park in the front and kind of have a little bit more separation. All those things are really nice.
Where is the nurse station in this situation? Is it over by Health and Physical, or is it in that gray little box next to the auditorium?
Speaker 14 (01:27:03–01:27:21)
It's within the admin block here. It's not differentiated. That would be the middle school medical. And the assumption is that there's a component here for the pre-K as well.
Speaker 11 (01:27:22–01:27:23)
Thank you. Sure.
Speaker 14 (01:27:24–01:27:24)
John.
Speaker 7 (01:27:27–01:27:58)
Yeah, my other question, I hear a lot about sped growth, and that's a huge issue. And I'm looking at these layouts, is it meeting our goals? I guess, John, I'm guilty of not sitting down with you. We should find out what the goals are for these.
things. But I hear that the special ed is a big issue now, growth of that population.
Speaker 1 (01:27:59–01:29:08)
Yeah, so I'll jump in as best I can, John. So that was specifically why I asked earlier when we were looking at reductions and confirming with Shonali that the special ed reductions didn't happen as part of those revisions that we did to the floor plan. So the visioning session, a lot of the spaces that were asked for for special ed are still there. So as we went through reductions and stuff like that, we didn't touch a lot of that.
And, you know, we're acknowledging the increased enrollment in special ed that we have right now. And that's part of the crunch that we're having overall in schools of not having space to service, you know, the children as we need. and then essentially having to send them out of district. So the hope with this project is, again, free up space at all the existing elementary schools by pulling some grade levels out of there.
That frees up some space for their special ed programs. And in this building, we're introducing the proper amount of space for special ed for it.
Speaker 7 (01:29:10–01:29:31)
And if I can add to the other thing is that I heard to it, Cunningham, there's a requirement that the special education space be equal to other space. And as I look at this layout, it doesn't look the same. Are we accommodating that?
Speaker 1 (01:29:33–01:29:37)
So let either Mark or Larry kind of jump in on that one.
Speaker 8 (01:29:37–01:29:39)
Yeah, I can jump in.
Speaker 1 (01:29:39–01:29:40)
Well, go Larry.
Speaker 16 (01:29:40–01:31:00)
I was going to say, so typically, so if you have a special ed classroom, it's the same size as your regular ed classroom. The other spaces, the special breakout rooms and other half classrooms and things are sort of sized to the population you're serving at the time. The one thing I think which you may be thinking of is there's very much a requirement that there Both integrated into the general floor layout and they're not isolated in one particular area so that, you know, you get the sense of. Down the hall at the end is where all those kids go.
Um, and I would anticipate as we develop this further that we will reach out to. To desi to get them to review the special led similar to how it happens with the MSBA. But, you know, we'll do it a sort of similar approach where Once we get a sort of more firm layout you send it to them and they look at it and agree to your general layout because again. They don't want them all in one little corner of the building.
We think right at the center is a good spot for them and puts them sort of in and amongst the rest of the classrooms in a good way, but also in a relatively accessible way.
Speaker 14 (01:31:06–01:31:07)
And Carrie's got her hand up.
Speaker 3 (01:31:07–01:31:48)
Yeah, sorry. So John made me think of, and this is more going towards brainstorming and questions about if others people are thinking outside the box, and particularly how Mark was trying to reduce the size of the cafeteria, where I think it's actually a good thing that it's bigger. I'm wondering with all of the increase of kids with ADHD and not many people sit in seats, as breakaway space. And I'm just wondering if there's any programs that people are implementing, particularly in the kind of common areas.
Are people thinking about that?
Speaker 16 (01:31:50–01:33:03)
Yeah, I would say that's sort of a further level of refinement. A couple of things are happening. One is along the corridors and those sort of centralized locations is finding little moments that you can put a quiet space that somebody, if they're feeling a little overwhelmed can duck into. And we're trying that at a couple of schools.
In the cafeterias, I think it's pretty common. We haven't quite gotten to this level of discussion yet, but to have either a separate room or separate little alcove like spaces. So kids who are, Overwhelmed by the activity of the cafeteria, the, the level of, um, uh, energy or noise. Depending on how you see it, um, have spaces where they can be separate from those, um.
Activities and then, you know, there's certain. Uh, some of the guidance teachers can run like a lunch bunch group. Um. and pull some kids out and have them doing lunch separately because they want them to have a little separate and different experience.
So I think all of those are in subsequent phases of the work we're doing, but I think all good to pay attention to.
Speaker 3 (01:33:03–01:33:10)
Yeah, I just wanted to make sure we didn't nip away at some square footage there. That's all, by making that comment.
Speaker 16 (01:33:12–01:33:20)
Thank you. Yeah, no, I think I think there's the opportunity in the cafeteria, uh, to create those separate breakout spaces with our 3500 ft.
Speaker 12 (01:33:22–01:33:22)
Thank you.
Speaker 8 (01:33:25–01:34:15)
I can just say from experience again when the Aero Street designed our high school like we have the three breakout spaces essentially that connect with our cafeteria for just that the purpose of what I was describing. And again, we also find it to be enormously helpful because of the again, the down time that cafeterias typically have that we use them for advisory spaces or pull-out spaces or meeting with seniors with our counseling team or, you know, it just provides greater flexibility than, you know, pulling 12 kids into a 3,500 square foot kind of open space, which doesn't feel very small or personal. And, you know, you can run a few of those if you get kind of a couple of those pull-out spaces. So I think all those ideas that Aerosphere brings.
into at least the space that designed for us. And I assume that are probably even better now are great things that address that area. And I think that's a great point.
Speaker 16 (01:34:22–01:34:26)
Yeah, I was going to say, if it's helpful, I can show you a picture of that one.
Speaker 1 (01:34:30–01:34:30)
Yeah, go for it, Larry.
Speaker 16 (01:34:31–01:35:18)
OK. Let's see if I can share my screen. Hopefully you guys can see that now. So this is one of the rooms that's right off the cafeteria, which sort of is over in this area and has these large glass doors that can open up.
And as mark indicates, it can be used either by kids who just want a little relief from the. The rest of the cafeteria, or if you had a particular group, you know, classroom size that you say, hey, let's all get together at lunch or let's just use this as a. A seminar room, uh, even though it's not scheduled.
Speaker 1 (01:35:19–01:35:24)
All right. Andrew, Shanali, anything else on adjacencies or anything like that?
Speaker 14 (01:35:25–01:35:28)
That was it from our end.
Speaker 1 (01:35:29–01:36:40)
OK. All right. Any other questions from members or comments or anything like that? Seeing none, I'll keep moving.
So item 5C, which is the discussion update of the cost estimate. So, you know, as everyone's aware, all the work we're doing is to lead into a cost estimate that we can present. You know, for doing these type of estimates before is specifically just for electrical, but similar to what you see here, you take the overall program, you start breaking into almost blocks or modular pieces that we're just seeing on the floor plan. And basically each one will probably have different values to them.
I know from electrical point of view, I would do, if I was laying out a building, Looking at what would be in each room differently, pricing one of them, and that gives me a price I can apply towards all the other blocks. My anticipation is for the cost estimate that we're going to be getting, the gentleman that's doing it, what's his name again? Shaneli or Sean? I apologize.
Speaker 5 (01:36:40–01:36:41)
Peter Bradley.
Speaker 1 (01:36:41–01:37:23)
Peter Bradley. So, you know, his end is, you know, he's basically going to be taking the floor plans that we see here, minus one team, you know what I mean? And I appreciate all the work you guys have done, but also take into account narratives for, you know, the MEP systems that we're going to have there, structural systems we've gone through and done, geotechnical borings, so we understand the subsurface conditions. And basically, you know, aggregate all that data and put a dollar value to it.
So, you know, remember to open it up to see if there's any questions. If anybody has, you know, we'll do our best to kind of answer them.
Speaker 2 (01:37:35–01:37:36)
Yep, John.
Speaker 7 (01:37:37–01:37:40)
Is this, you mean regarding the estimate stage?
Speaker 1 (01:37:41–01:38:05)
Yeah, correct. So that's kind of, you know, the reason we've been having, you know, the meetings kind of every week up till now is, you know, honing in on a program that we're doing now. So, you know, I think at this point, you know, we're getting to the, you know, what we consider a right square footage, the right systems, and, you know, feeding that over to the estimator to get him going.
Speaker 7 (01:38:06–01:38:21)
And I've been on the MSBA site, and I see two types of numbers. I see an estimated total project budget and an estimated construction budget. Which are we working on?
Speaker 1 (01:38:24–01:38:26)
Sean Burke, if you want to jump in on that one.
Speaker 15 (01:38:26–01:38:49)
Sure, the answer is both. Our estimator, Peter Bradley, will come up with an estimated construction budget. He's looking at the cost of building the building. And then on top of that, the total project cost will include OPM fee, designer fees, testing during construction, moving, utilities, FF&E, which is equipment to fit out the building, and any contingencies that we include in the project.
Speaker 7 (01:38:52–01:38:57)
Thank you. That was my next question. What, what is the difference? Thanks.
Sure.
Speaker 6 (01:39:03–01:39:03)
Right.
Speaker 1 (01:39:04–01:39:15)
Any other questions? So Chanel, as far as like an update on schedule for that too, um, do you have an update for the estimator?
Speaker 5 (01:39:15–01:40:14)
So, We are packaging everything and sending it out to the estimator on the 12th. We have allotted two weeks time for him to return the estimate. However, he and I have been in discussions and he's gonna do his best to get it to us a little bit earlier. Ideally the Wednesday, Basically a week and a half he's going to aim for that or obviously be in constant contact to make sure that he has everything that he needs to do this efficiently.
He's aware of the. the need to be speedy, but we have in the official schedule a lot in two weeks. So the idea is that it will get returned on the Friday, which I believe is July 26th, that we'll email it out to you end of day Friday.
Speaker 17 (01:40:14–01:40:25)
Okay. Okay, but the Wednesday you're aiming for hoping for would be the 24th.
Speaker 5 (01:40:25–01:40:51)
Yeah, that's what I'm hoping for. Okay. I'm not trying to put too much in my head about the 24th. It'll be a nice time.
I got you. Okay. But the narratives are going to start coming in early next week, and we'll start assembling them. And we'll assemble our drawings and put everything together to get it out to Peter.
Speaker 1 (01:40:53–01:41:15)
OK. And just for clarity, too, Peter Bradley was also, I think, for the other architecture team that presented to us when we were making our selection, he was also the same estimator. So his bread and butter is school building estimations. So that's what he does.
Mark?
Speaker 8 (01:41:16–01:41:49)
Yeah, as it relates to Peter, I don't think I've done a project that didn't involve Peter Bradley, regardless of the architect or GC or whoever. It's always Peter Bradley. I don't know. I don't know how he gets all that business and gets it all done, but he does all the schools.
Just, Sean, on schedule, obviously, again, the looping in the select board because we are getting to that August, it's the August 7th is kind of the deadline to put this as a vote. Is that correct? In order for, I'm sorry, Select Board to vote to put it on the fall ballot?
Speaker 1 (01:41:50–01:42:00)
I believe so. And John, correct me if I'm wrong, but I think it would be August 7th, which would be the first Wednesday of August.
Speaker 7 (01:42:00–01:42:12)
That date actually is the date that the written debt exclusion language has to go to the secretary. in order to get put on the ballot.
Speaker 8 (01:42:12–01:43:21)
Yeah, so the 7th is the ultimate deadline. Again, obviously, select board meets on Tuesdays, so that would be the 6th. So, you know, I guess my suggestion, and again, I don't know if it's you or if it's John here as our select board rep, would just be say, if we're expecting the cost estimates to come in on the 24th through the 26th, trying to see if we can schedule some special select board meetings on that 30th and that 6th, because I assume this is going to require kind of a couple, you know, a couple at-bats with the board to walk through the project as we've kind of done today. And they obviously don't even have the background we have.
And then also kind of to share the numbers, you know, if I were them, I'd want the numbers and the opportunity to kind of ask questions, you know, a week before I voted. know, that's the 30th and the 6th, and I know they don't usually meet that often, but I'd hopefully be able to understand that, given the timeline and how quickly we've been trying to work on this for the town, that they would meet and at least take a vote by the 6th.
Speaker 11 (01:43:23–01:43:25)
Yeah, go ahead, John.
Speaker 7 (01:43:25–01:43:45)
One of the first things we might have to do is move off, because we're gearing this up. We were, I believe, and I can check with Nick, but we're gearing this all up for a meeting on the 23rd. The next scheduled select board meeting was the 23rd that was geared up for this. So we may need to postpone that.
Speaker 8 (01:43:46–01:43:48)
Yeah, I mean, I guess I'm sorry, you go.
Speaker 1 (01:43:48–01:45:30)
No, that's fine. So so what one of the things when I talked with the chair of the select board at 1.2 is, you know, we were trying to plan out, you know, presentations for part of this is, you know, for the amount of work that we've done over the past, like, seven, eight months, you know, in the money associated with it, you know, our budget. Uh, I think was close over half a million dollars that we're spending, um, to summarize that in a brief presentation, I think would be too much, you know, um, so when I talked with him, when we had a meeting was essentially. my goal would be to present kind of a update for all this work that we're showing here and how we've arrived at this place and have some type of budgetary window.
And I mean not the fine-tuned number from Peter Bradley, but some idea where we're going to land based on MSBA data and some of the soft costs we can ascertain quickly. And then follow that up with the follow-on meeting from the select board after they've had time to kind of digest the details that we have there and an overall window of a budget and then come back at that date and present what Peter Bradley's final budget was. So that's one of the hopes that we'll be able to do. And if it's Uh, if it's held to the 23rd, um, you know, uh, you know, shanali, you know, maybe we talk a little more to, um, see if we can get Peter to move or, or see what we can do to kind of move that faster, but, um.
To be continued for our next meeting.
Speaker 5 (01:45:30–01:45:32)
Yeah, let, let me, let me think about it.
Speaker 7 (01:45:36–01:45:43)
And in that, you know, we have to balance the. The speed with the confidence of the result.
Speaker 8 (01:45:45–01:46:14)
Yeah, I can say Peter at times move pretty quick. And again, he's quite good, but doing it in six days, seven working days, that is pretty fast. So I think I'd be surprised if he could commit to getting it done by the 23rd. From my experience, it's really fast.
Two weeks is already a good timeline, but one that I think is doable.
Speaker 1 (01:46:17–01:46:41)
Yeah. Okay. And then, you know, just for the process by which we're going about for the, you know, for the assessment, you know, Sean Burke, if you just chime in a little bit in regards to, you know, typical MSBA project or stuff like that, when cost assessments are done, kind of how they're done or kind of how our path either aligns with that or does not align with that.
Speaker 15 (01:46:42–01:47:03)
Yeah, this estimate would be kind of aligned with their preliminary schematic report. That's when you basically have a site and have a model in mind. And at that point, you would estimate and then really create your whole project budget and submit it to the MSBA based on the projects that you choose. And then they would review and approve you to continue on with your project into detailed design.
Speaker 1 (01:47:05–01:47:11)
And that budget that gets developed at that time, is that also the one that talent would vote on?
Speaker 15 (01:47:11–01:47:20)
That's typically the one that MSD would include for the entirety of the project. So this would be the time when you have your site, you'd set your total project budget at this point.
Speaker 1 (01:47:20–01:47:54)
Okay. All right. Any other questions or comments? All right, seeing none move on to item 6, which is our future meeting dates.
So, just kind of look to our architects to see, you know, is there a need for us to meet next Monday? If not, do you want to push it for 2 weeks? I'm just. Trying to see if there's anything else on our end that you need input from the committee.
Speaker 5 (01:47:57–01:48:42)
I don't foresee anything. I think at this point, the team's going to revise the plans to reflect the 152 gross square footage. And those are going to be the plans for Peter Bradley. It's not to say that we can't make revisions when we get to the next phase, but it'll be enough for him to give us the estimate.
And then I think we need to just work with the consultants to make sure that the scope that they're writing into their narratives is correct. And I think that's an us thing, not a you thing. So I would say we would not need a meeting. Um, next Monday.
Speaker 1 (01:48:42–01:48:56)
Do you want us to hold the hold one as a placeholder and then, you know, we can cancel it later this week. Thursday is our last day to post. So I'm just, I'm just asking on behalf of everybody else, if we need to just kind of hold that as a placeholder.
Speaker 16 (01:48:56–01:49:27)
I was going to say, this is a bit of a short week, so we're going to have much to show you. That's new Monday evening. So maybe meet in two weeks on the 15th. And as she says, so the estimate work will have gone out.
Uh, maybe if we have something come up, we could. We could ping some folks on that, but, um, we could certainly show you the updated plans and continue to push and pull a bit on the plans without. Uh, I don't think too much impact on the pricing exercise.
Speaker 1 (01:49:29–01:49:51)
All right, so just for, for other members, you know, if you could just kind of pencil in, you know, a Monday, the 15th and, um. We'll plan on that. Right, and our final thing on the agenda is adjournment. So I'll entertain any motion to adjourn.
See if we get in before nine o'clock.
Speaker 4 (01:49:54–01:49:55)
So moved.
Speaker 1 (01:49:55–01:50:49)
All right, so moved. Is there a second or a second? Second. There we go, second.
All right, and so, all right, roll call vote. Carrie Hurley? Yes. John Cohane?
Yes. Scott Tereshek. Yes. Selena Miranda.
Yes. Aqua Baum. Yes. Mark Loring.
Yes. Tim Lombard. Always the last one. We'll count him as an extension than Seamus, if you would.
I want to make that nine o'clock deadline. And me, I'm a yes. So perfect. Thank you guys very much.
And we'll see you in two weeks. Thank you. Have a great day. Thanks, everyone.
Have a great day.
Speaker 11 (01:50:49–01:50:50)
Thanks, everyone.