Board: School Building Committee

Date: 2023-11-29


Transcript

Auto-generated; may contain errors.

Speaker 1 (03:41–03:43)

Meeting to order 704.

Speaker 2 (03:44–03:52)

And just for attendance purposes, as they always do, just a roll call. So Carrie Hurley? Here. Dr.

Miranda?

Speaker 3 (03:52–03:52)

Here.

Speaker 2 (03:53–05:16)

Mike Zulis? Here. Scott Tereshek? Here.

And Sean O'Rourke? Here. So first thing we have, second thing we have on our agenda, is CitizenSpeak. We allow 15 minutes of our meeting with three minutes per speaker.

We ask if you are here to speak, you just raise your hand, you'll be recognized, and we ask that you just state your name and your address. So we'll give it a minute and just check to see if anybody is here for CitizenSpeak. Seeing none. All right, perfect.

Next on the agenda is approval of meeting minutes. So I sent out the minutes for September 25th. Oops, September. Sorry, I thought Sean Burke was trying to get on.

And I sent out meeting minutes for September 25th, September 29th, October 16th, and November 13th, which will basically bring us up to date. On the agenda, we did have September 12th, But when I reviewed the September 25th meeting, we actually approved those minutes of that meeting, and they're posted online. So just check to see if everybody had a chance to review those.

Speaker 4 (05:16–05:19)

I did not attend the 25th or the 29th.

Speaker 2 (05:19–05:31)

Correct. I went through and made a list ahead of time of who was absent just for voting purposes. Mike, I think you were down for the last two meetings. You were a bit low, so.

Speaker 5 (05:32–05:38)

I don't know what happened to me. 16th and 14th. Busy man?

Speaker 3 (05:39–05:40)

Or lazy.

Speaker 2 (05:41–05:47)

So with that, with obvious extensions for people that are absent, I'll entertain any motion to approve?

Speaker 5 (05:48–05:53)

I'll move to approve the minutes from September 25th and September 29th.

Speaker 4 (05:54–06:00)

I'll move to approve the ones from the 16th, October 16th and November 13th.

Speaker 2 (06:02–06:17)

Two different motions, so we have to take two different votes. So let's just have you second, Mike, if that works. All right. And then we'll take a, I guess, we're in person.

Speaker 6 (06:17–06:20)

Second Scott, or are you doing one?

Speaker 2 (06:20–06:22)

We're doing.

Speaker 6 (06:22–06:26)

Do you want me to make a motion to approve all the minutes?

Speaker 2 (06:26–06:47)

Nope. We've got one motion on the floor, so it's for the September minutes. Mike couldn't make a motion for the other ones because he wasn't here. So Scott seconded.

So all those in favor, please raise your hands. I abstain. And now a motion for the October and the November.

Speaker 7 (06:48–06:53)

clarification actually if it's abstaining for one of the two.

Speaker 3 (06:53–06:54)

Yep.

Speaker 7 (06:54–06:59)

Abstaining for the 29. For the one that you were not present. Correct.

Speaker 2 (06:59–07:08)

All right. And then basically just need a motion for the October and the November minutes.

Speaker 6 (07:11–07:17)

I'll make a motion to approve the minutes from 10, 16, and 11, 13, did you say? Yeah. Yeah, I second.

Speaker 3 (07:17–07:23)

And again, all those in favor?

Speaker 2 (07:23–07:25)

Aye. Opposed? Aye. Abstain?

Speaker 5 (07:26–07:30)

Second. Mark Warren's race is named.

Speaker 8 (07:49–08:02)

Hey, everyone. Hey, Mark, how are you? Doing well. My apologies.

If I'm the only one remote, I'm going to ruin the good vibes of just having to raise your hand for a vote, and I even got to do a roll call.

Speaker 2 (08:02–08:10)

It's all good. So we were just getting through approving the minutes, and you probably heard that. I apologize. I didn't see you in the waiting room.

Speaker 4 (08:11–08:11)

No problem.

Speaker 2 (08:13–10:53)

OK. So on to essentially old business for that portion of the item for the agenda. So under old business, we always have a number of different items under there. They're just kind of historic ones.

So the first one is the SVC project timeline. For me right now, I don't have an update on that, other than to say we're kind of just on track for everything that we're doing. Our onus project manager is onboarded. And the last meeting we had, I was going to update this, but I was waiting to update it until we got the updated dates for the architectural RFS that we'll be talking about later in the agenda.

So once we get those dates for the architectural RFS, so we'll repopulate everything so we can kind of track it over our next couple meetings that we're having. So essentially with that, let me see if anybody has any questions or comments. Just see if he jams them. All right.

Second thing, item 4B, discussion update, contract with PMA consultants. So we've executed the contract with PMA consultants because of my scheduling snafu this week. I am handing over all scheduling duties, minutes duties, and everything to our OPM. I've already talked to Sean about it.

So he's going to start reaching out to everybody, coordinating when meetings are, getting a little more a better schedule, take the minutes, publish everything, basically alleviate that, so I don't have to be bothering you guys through text. But essentially for that agenda item for contract update, any questions, comments, anything? All right. Item 4C, the SBC funding article, so tell me, that we're going to have a public hearing on that.

It starts Monday, December 4th next Monday. So we have our article in place for that. My anticipation is it probably won't happen on that Monday night, but the following Monday night for the second night of town meeting is probably what I'm anticipating it going. So it's basically just regurgitating the presentation they did a dollar value of $400,000 that we have on there as the ask.

So that's basically our plan with that. So right in 4C, to see if there's any comments or questions. Pretty straightforward that we've done that stuff.

Speaker 5 (10:54–10:57)

We have a presentation. We're going to give a presentation. We're all set to go.

Speaker 2 (10:57–12:00)

Great. Yeah, I'm just going to utilize the same presentation I had from before. Yeah. Yeah.

Item 4D, Discussion, Possible Vote, Land Swap Alternative Analysis. So this is the alternative analysis that we needed to do for EEA. It's part of our… So we have essentially a bill of roll to them that's going to consist of this alternatives analysis for everything that's there.

I sent out an initial draft of it a couple months ago. I don't have the final draft ready, so it's not ready for a vote right now, but that coupled with the, what do they call it, the appraisals and the special legislation is basically, we're going to gather all that stuff up and it'll be part of our submittal TEA. Has the appraisal come back yet? Not that I've heard.

So I know Nick had executed a contract to get that done. But I haven't heard anything. But I'll check on that.

Speaker 5 (12:00–12:08)

I think they're making inquiries today. They're making inquiries today. And they might have a report as soon as tomorrow. Right.

Speaker 2 (12:21–14:03)

So, you know, for those of you that got it, I get your comments that I have to still incorporate through there and stuff like that, but if anybody else has anything, feel free to send it along. Going quickly. So item 4E, which is discussion update, Mass School Building Authority. Again, I keep that on there just in case something pops up in the 48-hour window before we have the meeting, just so we have it.

Nothing has come up. So we have not heard from MSBA. There is no planned site visit or anything like that. So as we know, in about two weeks, on September 14th is when they make the decision.

So we're kind of waiting patiently I'm going to go back from that on that. Item 4F, discussion, possible load, architectural services, Bergamo Road. So there was the request for services, I think we sent it out previously, just kind of for in a draft view so everybody can get a feel for it. I sent out before the meeting the kind of final version that was there.

for most of what we're looking at trying to do for this is one, look at the overall contract value that we want to allocate for this. The one that was sent out has numbers of 400 and 450,000. So I know when we looked through the budget that we have there, and I don't know if you want to talk about it, but you looked at Scott for it, you know,

Speaker 4 (14:07–15:02)

Yeah, when we plugged in $450,000 for architecture, that was leaving us about $10,000 left in the budget. So if we were to use $400,000 versus $450,000, it gives us a little bit more flexibility if there's changes for their scope or OPM or anything else. In that, we do have some projections for extra costs for lands land surveying and appraisals in case those go over. So I think those are covered, but it would just be for, you know, any additional architectural services we might need or OPM services or anything else that pops up.

Speaker 2 (15:03–17:04)

I think it goes back and forth. So in talking with Sean Burke at PMA, the funding that we have, he thinks, will get us by for some stuff. I think it falls on us as a committee to decide, do we want to essentially spend everything that we have to go forward with it? And then have that, you know, part of this plays out in my mind of if we spend everything, call it the $450,000, we only have $10,000 left, we'll hit sometime next fall and have $10,000 left at that point.

That if we anticipate having to do anything between the fall and essentially the next town meeting in December, or fall and say the next annual town meeting fall of May in 2025, is that enough? So I think that's basically for us to kind of discuss a little bit here. To what number do we plug into that for? And there's nothing saying if we make it 400,000 for the Arctic, there's nothing we can amend it later on if we see that, you know, if we see that fit too.

Part of the discussion too is if The architects, you know, for example, need more money. Is it something that we go back in May and ask for more money at that point, too? You know, if it's a much larger number than the $50,000 that we reserve or something like that. So, you know, I guess we'll get a better feel for that as we start interviewing architects and bringing them on.

But having that kind of set number is what we've talked with Sean Burke at PMA. rather than leaving it open-ended and just saying, what are you gonna do for us? Have a set target, a budget for them and say, we need you to work within that budget. And I'm fine with whatever number you come up with as a group.

Oh yeah, Mark, sorry.

Speaker 8 (17:05–17:12)

Just a question, did Sean Burke have a opinion on 400 versus 450?

Speaker 2 (17:12–18:01)

I think either number he thinks would be lighter. So for some of the architects that he's talked about or talked to, they would like to, I think, go a lot further than what we're anticipating as far as their design. I know a lot of them that he's talked to are very eager to get going on the project. But, you know, I remind him on multiple occasions, we only have a certain amount of set budget that we have to work within.

So I want to be conscious of that and not spend too much. So with that, I think with that, we can make it work. But obviously, if we had higher funding, we could kind of do a lot more with it.

Speaker 8 (18:05–20:37)

Yeah, no, it's helpful. I mean, I guess my general thought is, what would we be What would we be saving the $50,000 for? There's kind of two lines of thinking. One is, is the extra $50,000 really going to move the needle as it relates to an architect's desire to bid on the project or be able to give us, within a scope of work, everything we want?

I don't know. But then I also weigh, What are we saving the $50,000 for? If we approach something where we need more money, it's, as we say, probably going to be architecturally related. And so why not just put that in there to get the strongest possible proposal?

And if we end up needing more money, as has been kind of discussed, you know, it's very likely we'll need to then go back to the town and ask for more money in that situation because the 450 from everything, you know, you're saying that, you know, Sean Burke is saying is light in our estimates that that would be enough to hopefully cover us is maybe correct, but you know, we might've missed the mark there. So I think I'm, generally leaning towards saying we should put the full, you know, or the 450 towards it. And, you know, I also don't know if we have, I guess the other question I have is, is our only option also to kind of just wait until May? Because I know one of the calculations we were doing as it related to asking for the extra $400,000 was the burn rate and saying, you know, we wanted enough funding in order to make sure we could keep this moving and that we weren't just going to be kind of sitting idle for several months.

And so, you know, is that all still kind of, is the OPM kind of confirmed that our thinking there is correct and that we really should still be fine until we get to the Maytown meeting? or is there something else we should be thinking about in terms of asking the town to amend the article or to potentially like look into calling a different town meeting and at some other points to make sure we're not in that situation? Those are the things I'm kind of just speaking as I'm thinking about things, but those are the things that come to mind.

Speaker 2 (20:37–22:24)

further commentary on there. So within the RFS, the services that we ask the architect to have readily available are outlined in there, which basically cover anything and everything. So your point of including that $50,000 in there, and if something were to come up, they should have the ability through whatever subcontractor they've teamed with to fulfill that. So that's…

that's just weighing in on, you know, the idea of putting, you know, the full 400, you know, all 450,000 in there. The other part, you know, for me, I'm looking at this just from like my own profession where, you know, you get a project and, you know, for example, what we got here is a blank slate. So it's essentially an empty lot that, you know, architect would be able to, come in, start planning a school, lay out everything and do, you know, full design of everything all the way there so we can see why they'd want to be aggressive or eager to get going. And with that, they would spend as much as they needed to over that course.

But, you know, if we're trying to just get them to understand that we need them to get to a point for us to accurately price this to go after overall funding for the project, and then that overall, you know, eagerness can get put to use after we get full funding to really run through and get into all the details of everything. I think that's what our ask is. So we're not asking them to run through and lay out the details of every room, draw, you know, schedules for every door, every window and stuff like that. It's just more to Get this project to a better point so we can price it a little more accurately if that makes sense.

Speaker 8 (22:27–22:51)

Yeah, it does. Yeah, I mean, it's a. We are trying to work on a shoestring budget and do as much as we can for as little as we can to make sure we don't get over our skis and over-design something that ultimately the town rejects. So I think that's a fiscally responsible strategy that you're coaching us on, Sean.

Speaker 5 (22:52–23:15)

We included that full amount in the projected budget for the warranty. Well, what happens is we have $275,000, and then the $400,000, yeah, that was… No, I mean, in other words, we're going to be allocating the full amount, less $10,000, right? We're going to have $10,000 left over.

Speaker 2 (23:15–23:16)

Yeah, correct.

Speaker 5 (23:17–23:27)

And that, as I think, is similar to what we… the total warranty. in terms of our firmly and our projected budget. We're losing it all, right?

Speaker 2 (23:27–24:04)

Yeah, what happened was, even when we did that analysis that was there, we held certain money back for, for example, if we had to survey all the additional parcels up on Randolph Ave, there was additional stuff that EDA- We have those, we have those, right? Yeah, that's our overall budget. Those are set back, similar for the appraisal services. we did those and we had money set aside for those.

So with the money remaining, call it $460,000 roughly. That's what we're looking for. How much of that do we want to allocate? Right.

Speaker 5 (24:04–24:11)

And that was all projected to be used in the correct direction of the market. Yeah. And that's what the OPM is suggesting.

Speaker 3 (24:11–24:12)

Yeah.

Speaker 5 (24:12–24:32)

So, and that's what, that's what, that was what our projection was before. Now the OPM has kind of confirmed that. Oh, it says it's a little light. Yeah.

So I guess that would be my favorite, you know, of keeping consistent on this and following what sounds like a European suggestion.

Speaker 2 (24:33–25:33)

Yeah, in my end of, you know, the need for any additional services that may come up, that's why we're hiring the architect and their whole team to just address all those. And if something comes in that's outside of that, I couldn't really imagine what, because, you know, we've got them looking at traffic studies. They will have civil engineers for stormwater analysis. Not sure.

I'm good with the 450 as well. Yeah, it's just the other way too is like for the survey work that we have money allocated there, that survey work isn't guaranteed that we have to do it. We're just kind of keeping it there too. And if we don't have to do that, that would then fall back into, you know, a reserve fund for us if we wanted to do that.

So if everybody's okay with 150,000, you know, I can let PMA just revise that document and stuff like that. So

Speaker 7 (25:35–25:37)

I think that's good.

Speaker 2 (25:38–25:43)

Sounds good. Sounds right to me. Sounds like an informal vote. We're just waiting for our motions.

Speaker 5 (25:45–25:47)

So do we want to approve the RFS?

Speaker 2 (25:49–25:50)

Or just recommend it for select?

Speaker 5 (25:50–26:01)

Well, I'll make a motion to recommend approval of the RFS. Recommend the select board to approve a request for services for a limited amount of $450,000.

Speaker 2 (26:02–26:13)

I'll second it. Any further discussion? All right, so because Mark threw it all off, we'll do a roll call vote. Kerry Hurley?

Speaker 1 (26:14–26:14)

Yes.

Speaker 2 (26:15–26:30)

Selena Moreno? Yes. Mike Zubel? Yes.

Scott Tereshak? Yes. Mark Lauren? Yes.

And Sean O'Rourke? Yes. Great, we'll get that out and done.

Speaker 5 (26:31–26:37)

I think that will be on our select board meeting on Monday night, right before town meeting.

Speaker 2 (26:39–27:21)

So the next one that we have on there for item five is future meeting dates. I didn't put anything on there right now. Obviously the town meeting in the next couple of weeks and then the with the architect, there might be a need for something between now and Christmas. So I'll let people know as we start diving into that.

So essentially, Sean Burke will be in touch. So stay tuned. Any questions or anything like that? Or Monday's still a good night for everybody.

I apologize for the scheduling error.

Speaker 4 (27:24–27:27)

Yeah. Also be flexible knowing that. Yeah.

Speaker 2 (27:28–28:05)

Town meeting is the next two Mondays. The next two Mondays, too, yeah. Yeah. Okay.

All right. So we'll be in touch about that. Yeah. So our last thing, item six, is adjournment.

So we'll entertain a motion to adjourn. So moved. All right. Second.

All right. All right. Roll call vote again. Carrie Harwood?

Yes. Dr. Miranda? Yes.

Mike Zillowitz? Yes. Scott Tereshek? Yes.

Mark Lowry? Yes. And Sean O'Rourke? Yes.

Excellent. Thank you. Thank you very much.

Speaker 3 (28:05–28:07)

Have a good day.

Speaker 1 (28:08–28:10)

Well done. Thank you.