Board: Milton School Building Committee
Date: 2025-07-21
Transcript
Auto-generated; may contain errors.
Speaker 1 (00:22–00:47)
It is 7.03, so I'll call the July 21st, 2025 meeting of the School Building Committee to order. First thing as always, we take a roll call attendance. I'll start with people in the room. Nathan Hutto?
Here. Mark Loring? Here. Tim Lombard?
Here. Tom McCarthy? Here. And then online, we have Kerry Hurley?
Speaker 2 (00:48–00:48)
Here.
Speaker 1 (00:49–02:09)
Takura Ban? Present. Scott Tereshack, present. And Glenn Hoffman, here.
Thanks, sir. And Shanna Ward. So, second thing on the agenda is CitizenSpeak. We reserved the first 15 minutes of our meetings for any citizen that would like to speak, and Dr.
Redden just showed up, too. So if there is a citizen here that would like to speak, whether you're online or in the room, please just let us know and pause for a minute. I see none in the room and none online. So we'll move on.
Item three is approval of our previous meeting minutes. So I believe everybody in their packets that I sent over the weekend got copies of the past three meeting minutes that we've had, I think going back to May. So just open it up, see if anybody has any questions, edits, comments, and if not, I'll entertain a motion to approve.
Speaker 3 (02:14–02:19)
Scott has his hand up. What's up? Scott has his hand up. Thank you.
Yeah, Scott.
Speaker 4 (02:21–02:34)
Hey, Sean. Just on the July 1st one, I'm shown as present, but I ended up not being able to make it at the last minute. OK, I'll let it go. That's the only comment I had.
Speaker 1 (02:39–03:04)
Should we take these votes one at a time, given the people? The way we've done it before is people just vote for the ones they're eligible for. So rather than trying to go individual for each one, we've done it that way, and it's fine. OK.
So it makes it easier. Otherwise, if people want to take roll call votes. Oh, that's fine. I'll just make a motion.
Yeah, for the ones for, obviously, Nathan and Megan that weren't part of the committee, then they couldn't vote.
Speaker 5 (03:04–03:09)
So they're just saying abstain from until May 12th, on the other team.
Speaker 1 (03:10–03:16)
And on the minutes, they're actually listed whether they were attending or not, so it's pretty good.
Speaker 5 (03:16–03:28)
I'll make a motion to approve the school building committee meeting minutes for Monday, May 12th, 2025, Monday, June 9th, 2025, and Tuesday, July 1st, 2025.
Speaker 1 (03:28–03:39)
I will second that. And Tim, second. Any further discussion? outside of Scott's friendly amendments.
Speaker 6 (03:41–03:45)
I just have to abstain from the May 12th meeting. I was not present.
Speaker 1 (03:47–04:01)
Yeah, so what we'll do, Carrie, is similar to how we kind of had minutes that we had to approve or multiple minutes that we had to approve before. You can just make the statement of, you know, you're abstaining from the ones that you aren't eligible for.
Speaker 2 (04:01–04:02)
OK.
Speaker 1 (04:03–04:17)
Yeah, that's fine. Okay, so with that, we'll do a roll call vote with the people in the room first. Nathan? Abstaining from May 12th, but otherwise, yes.
Okay. Yes. Tim? Kerry?
Speaker 6 (04:18–04:22)
Abstaining from May 12th, but otherwise, yes.
Speaker 7 (04:22–04:34)
Yes. Let's see, Aqua? Abstaining from the ones I'm not eligible for, otherwise, yes. Okay, Glenn Hoffman?
Speaker 1 (04:34–04:40)
Yes. Scott Tereshak.
Speaker 4 (04:40–04:43)
Staying from July 1st, the other two, yes.
Speaker 1 (04:44–05:08)
And Chatterwick, yes. All right. Moving right along, going to agenda item number four, which is old business. Update Discussion MSBA Module 1.
And this will also play into Item 4B, Project Timeline, as to what we're doing. So I'm just going to share my screen.
Speaker 3 (05:23–05:26)
Let me know if that pops up and you're going to send it.
Speaker 1 (05:31–05:33)
You guys online can see that, just let me know.
Speaker 4 (05:34–05:34)
Yes.
Speaker 1 (05:35–06:08)
Okay. Appreciate it. So what I, what I tried to do is take module one and the components of it to kind of list out what parts we've got completed. The big one that's coming up due next week is our educational online enrollment.
With this one, I've got access now to the MSBA portal. There's a few things, I'll pull it up just so if you guys that don't have access to it kind of see what it is.
Speaker 3 (06:08–06:16)
So within MSBA, sorry, no.
Speaker 1 (06:17–09:10)
So there's two portions that we need to fill out the enrollment questionnaire and a follow up enrollment questionnaire. So within the initial one for the enrollment questionnaire, portions of this have been filled out by the town district or as it deals with enrollment population sets that are here for reported births. family goes back 10 years, so we're getting all that information. Projected permits to be issued, so we're working with the town administrator on that.
Housing for people over 55. Other housing projects that are coming online, and I think there's certain things within the town that will play into that. Additionally, housing sales, and then essentially, These first four tabs lead into some type of algorithm, I believe. And with that, this bottom part here is a projection.
So what they do, I'm trying to read MSBA's mind or their tutorial, is based on those inputs that we give them, it will give a projected enrollment, and we'll be using that as the baseline as the overall project. So once those are finalized over the next week, we'll submit it. The submitting authority has to be the chief executive officer, so a student is either a select board or an alumni as their designation. The other component that deals with this too, is the follow-up questionnaire that deals with different things for the schools, general information, out of district that's already filled out, special education information that's here, pre-K and kindergarten data, and then again, based on all that stuff submitted.
So essentially, my understanding of all this stuff that's utilized to help present the overall projections that we'll be using as the baseline for the project. So right now, As it stands, timeline, this is on track for us to complete next week. So with that, I just wanted to provide an update to the committee and just check with anybody if they had any questions or comments. And there's one other document that we talked about before.
I know we sent some edits back on that. Is that one all set, ready to go?
Speaker 5 (09:10–09:15)
Yeah. Okay. That's good. Okay.
Is that uploaded as an attachment to one of these things, or?
Speaker 1 (09:15–09:46)
No, I submitted separately. I think we had to submit that one separately. So that's the separate, you know, it took information from a statement of interest. And like I said, I just wanted to elaborate a little bit further, because it just talked about, you know, the overall, just middle school program.
Anyone didn't think we had blinders on when we were looking at Sorry about that. So, yeah, I'll just see if anybody has any questions or comments in regards to just that component of Model 1.
Speaker 3 (09:52–10:02)
Do you need any help with anything, Sean?
Speaker 1 (10:02–11:32)
HAB-Michael Leccesereeeeeeeeeeeeeeeeeeeeeeeeeeee Yeah, so, so Scott, in regards to your question, like, most of that information, I don't think a lot of us have. So, I went through basically crafted a black better order to do this for Nick Milano and John Phelan, who's the interim superintendent. Uh, just basically stating, you know, these are the things that we need outlined it. So, uh, my hope is to have a call with them this week, uh, and, you know, kind of get all that information down, um, by Friday.
And that gives us a couple of days next week to just kind of, uh, touch base if anything, any of the last minute things are outstanding. But again, I just wanted to bring it up mainly for, you know, everybody's information to let them know kind of where we're at in that process.
Speaker 3 (11:34–11:42)
Okay, thanks, Sean. Any other questions, comments?
Speaker 1 (11:44–13:48)
All right. The other one that we have, we'll be having definitely more time on this one for 180 days, is the maintenance documentation. So I know, Tom, you've got a good head start. I've done everything that I can do.
I've turned the rest over to budgetary. Central office yes, I know Katie's working on it. Yeah. Yeah.
So there's some of that that deals with like, funded allocations and resources and stuff like that. So I appreciate your help. So, so the overall good thing is, you know, I mean, by the time, like, After next week, and once the maintenance documents are done, we've essentially completed module one, but the reality is, on my end, I'm not expecting us to kind of meet, oh, actually, I'm sharing, sorry about this. Keep jumping around, it's been a long day.
The board of directors meeting for MSBA is August 27th. But I'm just not sure if I'd like to try to get on that meeting to, you know, have us push through module one to module two. But I know the one other, there's one other component actually not listed on there because it's not a to-do list for us. We have to meet with MSBA to kind of have a reconciliation of that enrollment projection to kind of come to an agreement on what those numbers are.
Um, so I don't see that happening anytime before, you know, that August meeting. So most likely, um, we'll make that progression from module one to module two, probably at the October meeting. Uh, so like as we, as we kind of dive in and look at the overall project timeline, um, I I'm thinking, you know, October is more of a safer, uh, realistic timeline for when we make that transition over to module two.
Speaker 3 (13:52–13:59)
Any questions? That's still within the schedule. Yes.
Speaker 1 (13:59–20:18)
So, you know, overall, I mean, we had 270 days to complete, and, you know, we have to complete Module 1 by next January. In fact, I think if we get it done in, you know, late August, early September, that's definitely a good head start. Um, just pull up the agenda then just. So, the, the, the next item we're going to talk about under new businesses, a discussion vote school building committee fall town meeting article that also plays with this overall project timeline.
So I know in our last meeting, a number of us had questions in regards to the timeline so. The last meeting, I had a PowerPoint presentation that gave kind of a schematic layout of a timeline for what we were doing. And I tried to dive a little bit deeper into some of it. So in the documents I had sent, initially with your packets, I had sent in this kind of timeline for other districts, what their modules were, their start dates.
and durations for everything. And I tried to snip in from MSPA's website where those dates came from, just so there was a clarification for where they were. And the dates associated that I put over here in yellow were, you know, the Milton assumed ones. This was kind of a good starting point, but for me, it helped a little bit better to kind of dive into, you know, overall, you know, Gantt chart and this, you know, pictures are a lot easier for it.
So, looking at these and, you know, kind of ignoring the actual years, because these vary, but just take a look at Canton. So, Canton got invited into their eligibility period March 3rd, 2022, and they don't give when they finish module one, start of module two. They only give you when they start module three, which is the feasibility study. So for them, their start of the feasibility study was October 26, which basically lands there.
So somewhere between here and here, they completed module one and module two. And just to remind everybody, module two is formation of the project team. So it's what we did for those of you that were on the committee. It was what we did two years ago.
We re-interviewed OPMs over a period of time, hired an OPM, and then I joined an architect through a selection process. So what I tried to do is I took Camden, Marlborough, Quincy School, and the Denham schools, basically put the timelines, the durations for all these together. And then what I tried to do for everyone to kind of review is if we took Kenton's timeline and attributed it to Milton. So for us, we got our invite in December.
We really couldn't start till May. And then started looking at these durations of everything. And I used this with the understanding of, you know, most likely we're not going to be able to progress to module two until October of this year. So trying to take the chunks of time that they got associated with these to look at these.
So if we utilize Kin or we mimicked Kin's timeline, you know, we would go out and Kin, move this out of the way. We would basically make the end of 2027, beginning in 2028, and line us up for a town meeting in 2028, for a special town meeting, and then a follow-on vote. So the one thing that was absent from the initial spreadsheet I sent you were these town votes that happened, town meeting votes, and the debt exclusion vote. And these were on the town administrator's slides from that December presentation with the select board.
And so what I tried to do, as I said, kind of navigate with. So after Canton, similar, I took Marlborough, I looked at them, and similarly for Marlborough, we finished end of 2027 towards 2028. And again, this makes the assumption that we've onboarded an architect and an OPM by January of next year. And for Ken, we would have onboarded an architect and an OPM by March of next year.
For Quincy, as we laid out this timeline, this was a little bit longer. They had a longer duration, it looked like, for their schematic design. That would push us all the way into 2029 for the annual town meeting. Then similarly for Dedham, 2029.
I put these there just to put graphics to the descriptions that we were talking about before because I know there was concerns of how this would all play into what's shown in red here, which is our reverter clause in the land swap that we had. which is scheduled for June 30th, 2028. So that's essentially why this shows up in red here. So, you know, with this stuff, you know, I sent it, I tried to send it over the weekend for everybody to kind of dive in a little bit, because I know you guys all love diving into this stuff over weekends.
So I'll open it up just for, you know, questions or comments or anything right now. I'll try to answer whatever I can.
Speaker 3 (20:24–20:30)
I appreciate you laying this out.
Speaker 5 (20:30–20:36)
It was a very helpful visualization to speak out where we're at. It's unfortunate. It's helpful.
Speaker 1 (20:37–23:26)
Yeah. The one other, so the other one that I've done, share it too. So I went through to figure out what an article would look like for the reverter clause. And in speaking with someone's experience of putting these type of articles together before, it's essentially the entire act that was passed as part of the legislature.
And so what happens is, There's front end language to the article that basically it's our generic thing here asking for us to authorize the select board to petition the general court to enact legislation relating to the authorization of the town to use certain land acquired for conservation purposes, for school purposes, and substantially the following form. So that's verbatim, I think, for what we had in the land swap. The difference is, The yellow portion that I highlight here is what we're trying to do is tell them that this entire article has already been passed. We're looking for amending that existing article.
So part of it is we need to repeat the entire article to have the public on notice of what we're talking about. Because if we only talked about the Roberta clause, it wouldn't give overall context. as far as what we're doing. But essentially what it does here, if we go down to the very bottom, the reverter clause shows up in section two, and this would be essentially our amendment.
And so for us, for a town meeting article, we'll repeat everything just with our updated text. And then the other description in the article, it allows the, the general court or the legislature to vary the substance of it. So essentially you're saying we're editing this to that and make it much more simpler. So, you know, with this, that's kind of where we're at right now as far as, you know, what our overall timeline looks like.
And if the committee wishes, you know, based on our last meeting, you know, feedback that I was getting, what it would take to extend that reverter clause. So with that, I'll just kind of open it back up to everybody and kind of see where people are at.
Speaker 5 (23:27–23:39)
So it looks like the proposal is to extend a date of the reverter clause out to 2033. Any, what was the logic behind choosing that date?
Speaker 1 (23:40–25:07)
It was, so it was a five year recorder clause. So we just added another five years to it. So there wasn't, there wasn't an exact arithmetic done, but it was just a double the existing. The main thing that we should keep in mind too, is, you know, when we were looking to, when we were doing the land swap, the, the intention of us going with MSBA or even the real reality of it didn't exist.
We never thought we would be in MSBA. And with us, we figured a non-MSBA path within five years we could do. And so the year after, we worked with the Ombud architects, OPMs, got everything up to speed, got concepts, schematics, design, a cost estimate, and lined up with the line swap. And we were ready for the debt exclusion vote last November.
It just, you know, at the time, it's like, we're going to put it on there. So, like, for us, that five-year timeline, we were fine with when it was a non-MSBA project. Now that it's an MSBA Um, you know, the concerns I heard from at least a couple individuals last time basically, would we skip MSVA and just go direct that way if we were going to lose land swaps? So that's why I was kind of doing some of that work to kind of address some of the concerns I heard last time.
Speaker 3 (25:17–25:21)
Some other people steal the air out of the room.
Speaker 8 (25:25–25:40)
Yeah, the timeline extension makes sense. Going from a non-MSBA to MSBA, it lines up. But if exactly, use Canton as an example or anywhere else, it would make sense. I think it's like a non-controversial.
I can't imagine anybody objects to this.
Speaker 1 (25:40–26:25)
Yeah, I mean, two of the timelines we showed show it happening right on 2028, like in line with it there. Those assume, like I said, by February next year, we have an OPM, we have an architect on board. I think from October to that date, it's going to be tight on board architect, on board OPM over the holidays and stuff like that. Yeah.
So, I was trying to just be conservative with those timelines. The reality is I think those will push out a little more and kind of squeeze those up against. But I didn't want to present it that way and just make it look like every one of them couldn't meet 2020. And there's just not a lot of wiggle room.
Speaker 5 (26:25–26:39)
Yeah. It also assumes that it passes. It is funded on the first go-around, too, in that situation, which was not the case last time we did this for the schools. Yeah, something like that.
Speaker 1 (26:39–26:49)
Yeah. So you're talking about the big previous. Yeah. When they built all the schools.
Yeah. I think it was three times it went through a debt exclusion.
Speaker 5 (26:49–26:52)
Yeah. I think the extension makes sense.
Speaker 3 (26:58–27:03)
Looking online and see if anybody has their hands up.
Speaker 2 (27:06–27:16)
I mean, to me, it sounds like the, a five-year extension makes sense if the original clause was five years, correct?
Speaker 1 (27:18–28:47)
Correct. Yeah. The original clause, like I said, was five years. At the time when we were doing that, Megan, the intention was we were just going to go on our own timeline because we were applying to MSBA.
I think we applied three or four times prior to when the land swap occurred. And, you know, the prospects of getting accepted to MSBA were, in our minds, very low. So we didn't think that would happen. That's, it's just one of the big things that changed over the past year.
And it's, you know, for me, I'm not, you know, it's, you know, you go back and forth on it. You know, at one point, it'd be nice to get the project done quicker and stuff like that. In regards to, you know, people's hesitation on the overall cost program and stuff like that. I think having a third party agency like MSBA oversee it, endorse it, it will make it a little bit easier, you know, when it comes time to actually fund the entire project.
Cary, Aqba, any comments? I know you guys were kind of vocal at the last meeting, so I just want to make sure that any of the comments you guys provided last time are addressed.
Speaker 6 (28:47–28:55)
My comments are the same as the last time. But I think the extension is worthwhile.
Speaker 1 (28:56–29:03)
No, just because you guys had mentioned the foregoing MSBA in the city overall projects.
Speaker 6 (29:03–29:23)
Yeah, I mean, I'm still concerned that we're not going to be able to build the school that we want to build, and it's going to take longer to do. So yes, my comments still remain the same, but I do agree in this instance for the betterment of the group. Obviously, from a timeline perspective, need to go for the extension.
Speaker 1 (29:24–29:25)
I appreciate it. Thank you.
Speaker 7 (29:27–30:07)
I stand with… Sorry, I didn't catch that. I will start. I stand with Kerry on her position.
I am concerned that we will not be able to build it once. If we don't handle the land carefully and we lose the land, I know like many who've been on the committee for a long time, there's no other land available and it's going to make this a little more difficult. But I support what the committee is doing and whatever I need to do to show that support, I'll be happy to.
Speaker 1 (30:08–30:50)
No, I appreciate that. Again, just want to make sure, you know, because, you know, the takeaway in the last meeting, there were certain things asked. I just want to make sure those were covered. So essentially, this is on for an agenda item for a discussion slash vote.
So if people are so inclined, they can make a motion to put this up and then, you know, I can relay this to the select board. I know because we're just doing this tonight, probably won't make their agenda tomorrow, but I can show up at citizen speak and just, you know, make them aware so that on their next meeting it's there.
Speaker 3 (30:59–31:00)
the motions.
Speaker 5 (31:00–31:38)
And I'm just going to figure out the link. Do you want me to pull up the… Yeah, what's the name of the editor? We all need you.
I appreciate you. He makes all the motions. I'm looking forward to it. Just article XX?
Or… Article, okay. I'll make a motion to submit the article to extend the timeline for the land swap as presented here to the select board for inclusion on an upcoming town meeting, all town meeting.
Speaker 2 (31:39–31:40)
I second.
Speaker 1 (31:42–32:03)
And Megan seconds. Any further discussion? Seeing none, we'll go to a roll call vote. All right, Nathan Hutto.
Yes. Mark Lauren. Yes. Tim Lombard.
Yes. Carrie Hurley.
Speaker 6 (32:04–32:04)
Yes.
Speaker 1 (32:06–32:11)
Aqua Vaughn. Yes. Scott Tereshek.
Speaker 4 (32:11–32:11)
Yes.
Speaker 1 (32:13–32:17)
Glenn Hoffman. Yes. And Megan Harrington.
Speaker 2 (32:18–32:18)
Yes.
Speaker 1 (32:20–33:16)
And myself, yes, unanimous. All right. Thanks for doing that, Sean. No, no problem.
The only other thing we've got on the agenda, our next meeting would be August 11th, keeping with every three-week schedule. The following one after this, when I started laying it out, was the weekend of Labor Day. Um, so I, I think, you know, just keep, be aware for an audible either the week before or the week after, but we're definitely not doing September 1st. Um, so, you know, just putting that on everybody's calendar.
Um, I don't think there's anything between now and then that will kind of pop up. It will need to do as far as like module work or MSBA. So it should be good so far.
Speaker 3 (33:16–33:28)
Good. I'm going to miss that. All right. I'll get away as well.
That's fine.
Speaker 1 (33:29–33:48)
All right. All right. So with that, Item 7, I'll entertain a motion to adjourn. Make a motion to adjourn.
Motion. Second. Any discussion? Roll call vote.
Nathan Hutto. Yes. Mark Warren. Yes.
Tim Lombard, yes. Kerry Hurley.
Speaker 6 (33:49–33:49)
Yes.
Speaker 1 (33:50–33:54)
Aqua Vaughn. Can we stay a little longer?
Speaker 3 (33:54–33:54)
Yes.
Speaker 1 (33:56–34:03)
Scott Tereshek. Yes. Glenn Hoffman. Yes.
Megan Hagerty.
Speaker 2 (34:04–34:05)
Yes.
Speaker 1 (34:05–34:09)
And Shadow Work. Yes. All right. Thank you very much.
Speaker 9 (34:09–34:12)
See you next. Thank you, Tim. Good night.