Speaker 1 (00:49–00:51)

So we'll get started.

Speaker 2 (00:51–02:18)

Apologies on the delay. So I'll call the meeting to order. It's 7 of Milton School Building Committee. It's 7-16 on March 24th.

As typical, we do a roll call vote on this. So with me in the room is Gwen Hoffman. Yeah. Mark Loring.

Here. Akbar Abang. Here. Oh sorry, Tom McCarthy.

Yeah, I remember, sorry about that. John Cohen, Tim Lombard, present. And then online we've got Scott Tereshack, present. Second thing on our agenda is typical citizen speak.

So if you're here tonight for citizen speech, please raise your hand. So give it a couple minutes and just wait for that. All right, hearing none. All right, we'll move on.

Uh, agenda item number 3 is 2 parts. It's approval of our past meeting minutes. So, our past meeting was Monday, January 13th, 2025. In that meeting, we also set an executive session, so we have minutes for both of those.

Those are all distributed as party packets. So, give everybody a chance if there's questions, comments, and if none, we'll entertain a motion to approve.

Speaker 3 (02:24–02:25)

Motion to approve.

Speaker 2 (02:26–03:29)

Perfect. I'll second. Seconded by Mark. All right.

And because we're a hybrid, we're going to do a roll call vote. So Glenn Toffman. Yes. Mark Loring.

Yes. None of the voting that were correct. Agra Bhan. Yes.

John Cohen. Yes. Kim Lombard. 16.

Scott Tereshak. Yes. And Sean O'Rourke. Yes.

Um, all right, the 4th item on the agenda. Is everyone's aware is a discussion of module 1. so everyone's aware. Uh, we've all entered into will be starting in May, but we have the opportunity now to kind of get ahead on some of this stuff.

And, you know, the main reason for the meeting tonight was kind of just a. walk through some of this, get everybody back re-engaged, because we've kind of been on pause for a couple months while a couple things were going on. So with that, just give me a second. I'll pull up the MSBA module one and kind of walk through it.

Speaker 4 (03:39–03:41)

You can display it there, right?

Speaker 2 (03:41–05:20)

I can, yeah. Oh, yeah. Can you pull it up? The website?

Yeah, this module one. So for module one, we kind of walked step by step. So, the, the 1st thing that's going to be due 30 days after I think it's May 1st when we get in is the ICC, which is the initial compliance certification. Shane, can you hit on the link for that?

Down the bottom blue hyperlink 1st, 2nd paragraph right there. So essentially what this is, is just acknowledgement of us entering into MSBA. So it's signed by the chair of the select board, the school committee, and I believe the superintendent. So this is basically a formal paperwork that, you know, we'll be working with those entities over the next couple months and, you know, get ahead.

So any questions on the ICC? That's what I mean. Yeah. Yeah.

So with this is, again, it's just MSBA's kind of contract language saying you're entering into their module one. Yes, sir.

Speaker 3 (05:23–05:37)

Timing-wise, we can't submit that till May 1st, and then we wait for them to say they're accepted or whatever, and then we go to the next school building committee submission.

Speaker 2 (05:37–06:29)

Is that how it works? So if you go back? So what they showed here, the flow chart that they have there, the flow charts laid out by the days that they allow you to do some of these. So they don't have to be sequential like that.

Obviously, we did the funding way ahead of it. So the flow chart's a little deceiving, because it looks like you have to do the ICC, then jump into the next one, jump into the next one. So essentially, for us, my goal is We've got to get the ICC done within the next month as quickly as we can. And again, it's three signatures.

That's all it is. And then we submit it. And we'll hold on it in the middle until we're formally entered in May. And then essentially, it just goes in the file with them.

So it's not like they get it and then let us go to form a school building committee, which is the next one.

Speaker 3 (06:29–06:32)

OK. So when do we do the school building committee?

Speaker 2 (06:32–06:39)

We've already done the school building committee, so we'll just submit that. When do we submit it? Yeah. My goal is the day after we get accepted in.

Speaker 3 (06:40–06:43)

Okay. You mean the day after May 1st?

Speaker 2 (06:43–06:43)

Correct.

Speaker 3 (06:44–06:49)

Okay. Yeah. Because we've got to be careful. They say don't get ahead of yourself.

Speaker 2 (06:49–06:50)

Yeah. Okay.

Speaker 5 (06:50–06:50)

Yeah.

Speaker 2 (06:51–08:05)

we've checked with them they've allowed us to kind of get this head start on everything so my goal is whatever we can submit once we're formally into it that we have already filed out and done yeah get all that on record with them as quickly as possible so the next one or at least the next portion of the module they talked about this formation of school building committee so as everyone's aware we've augmented our committee now uh tom mccarthy's on with us uh i forget what principal is going to be Uh, joining us, I think it's John for cutting him. Nick Milano, I think is on a Katie Blake is on it for the certification. So, there's a number all the members that got augmented, like, we talked about before non voting. So, it's still the 9 of us that have been on the committee or all the voting.

The next one that we'll be working here, and this is one I think everyone's going to be interested in, is the educational profile. So the white part of that box, MSBA does that. So, and Sean, correct me if I go wrong on this, but the educational, we provide an online enrollment projection up to 90 days.

Speaker 6 (08:07–08:09)

So.

Speaker 7 (08:09–09:05)

So, I mean, this part we're using afterwards, but during that process, the industry will work with you to set your enrollment over that, you know, whatever the 270 day process, but if you're ready to do it sooner, they'll meet with you. And that's going to set your enrollment for the different options that you're deciding to study. And it's kind of a little, it's a little bit back and forth. They'll look at like Department of Education stats for the year over year, they'll look at how many students you retain, new growth in the area, they'll look at birth rates and things like that, and they'll come up collectively.

It's a negotiation, but they'll come up with a collective number with this committee to decide on, okay, these are the enrollment options that we're going to study for. So whatever school options you decide to put forth. And likely, it's going to be an ad. Typically, they make you do a code upgrade at whatever building and add Reno.

And then you can do it in a new build.

Speaker 3 (09:05–09:26)

There was some confusion, too, about there's a module 2, which is the select the project management team and the design team, right? That kind of squeezes in somewhere between the facility study and the end of the You know what I mean? That's got to be done first. That part of it's confusing.

It's kind of left out.

Speaker 7 (09:27–09:48)

Some of the slides. So module 1 will finish with you having funding for a feasibility study and an enrollment. Uh, plan with the MSP of what you plan to study and then you'll have to get together before picking an OPM and an academic. I just go to that'll be module 2.

I believe the forming team building with us.

Speaker 3 (09:48–09:51)

And then that's in between. Then the.

Speaker 7 (09:51–09:56)

Feasibility, yes, forming the team and then you start to correct. That's right.

Speaker 2 (09:56–10:41)

But if you just click with us, yeah, it'll give the flow chart of the whole thing. Yeah. Yeah, oh, yeah, there we go. So, so this is, this is all the modules that are there.

So, for this eligibility period is the 1st, 1 that we're doing forming the project team is the next 1. and that's basically where we start bringing on the, the architect. Like, we did before, and then once we have the architect on board. We have our options that we're looking at the basics for the feasibility study and our funding.

Then we pull all that together all the trigger and jump into feasibility study. Make sure to speak up too, because the mic's down here, just to make sure.

Speaker 4 (10:41–10:53)

So what extent can we use the material that we have already created?

Speaker 2 (10:54–11:55)

So because of the process with MSBA, right, they require you to go out and basically, it's basically, we can't even assume we've had professionals working with us for the past year. So we get into the, like I said before, at the beginning, a couple of months ago, this is like a reset button for this. So we hit the reset button, we go out. Now, we're gonna go out similar to what we did, I think it was like a year and a half ago, interviewed all the OPMs and architects.

We're going to re-go through that for the OPM section, because we're the ones that get to choose the OPMs. So, you know, nothing's precluding them from resubmitting on this. And then, you know, we can go through that process. The architectural selection will be done by a designer selection panel from MSBA.

We'll have three seats, three seats on there. So out of those three seats, whoever gets chosen, you'll have some input on which architect you'd like to go in, but you're not guaranteed the same one. The work they've done.

Speaker 8 (11:57–12:14)

Well, I think 15, right? Depends on who shows up, because it's each board member, but I think it's up to, I think, 16 seats on the board. So they, yeah, three hours. No, we don't.

No, but weren't you saying that in your experience,

Speaker 7 (12:14–12:38)

the vast majority of the time, the architect in the town would prefer to go to is the selected architect. Most of the time, yes. But you have to position yourself correctly. And you work with your OPM moving up to that period to figure out what's important to you and then make your case.

You're going to make a good case to NFB is why you feel that they're the best firm for you. You convince them, then, yeah, they'll certainly go along with it.

Speaker 8 (12:38–12:54)

And typically, at the end, when you're discussing all the architects, the last three to speak on the kind of whole thing before you go into voting are the three members from the town. So that kind of gets the last word in before voting starts. So it's going to be cool.

Speaker 7 (12:54–13:20)

And is John Little going to be on that list? We don't know yet. I would assume they would apply for it, but this is a full public RFP. So you'll go out to just a full public advertisement career like the check was set in process.

But it's not like there's a set list. I believe there's a set list. You have to have some sort of certification with the MSBA, which Arrow Street does. But it'll be open to any architect, including Arrow Street, that's in that pool that wants to go after the project.

Speaker 2 (13:20–14:01)

And then just one more thing on your question about reusing what we already did. So the goal is to reuse whatever salvageable information and data that we have. For example, we have an existing survey of the lot, right? So we're able to just hand that over to the design team when they come on.

We've got borings, or at least we're assuming they're going to put the building in a similar location to where we were doing before. We have boring geotechnical data of that stuff. Again, stuff that we can turn over just to, you know, push them in the right direction and, you know, get them going a little bit and not spend money for a second time.

Speaker 4 (14:01–14:10)

What are we doing with the trafficking investigation? Are we forced to get servants?

Speaker 2 (14:10–14:42)

We have terminated their services. Not terminated, it's probably a bad word. We have closed out their contract. They had a contract with us to do the feasibility study up to a certain point.

We had a certain amount of money that was set aside for that, I think 475,000. and they've billed all 475, they've been paid, and they delivered that final feasibility and process meant to us in November. So yeah, if we would, there's no more parallel paths right now, we're going on one path.

Speaker 9 (14:42–14:49)

It's not to be clear if we didn't select another architect, you could hand them that package and say this is the direction we would like to go, correct?

Speaker 2 (14:50–15:07)

I, I think theoretically, I'm not saying we do that. Yeah, I, I, I think it would be hard for an architect just to take someone else's work and just say, I'm running with exactly that. You know, technically, could we. Yes, but I don't know how we can enforce that.

Speaker 7 (15:08–15:20)

Now, I think the architect that is selected that would come on board will go back through our previous meeting minutes that included attachments that would have referenced that if they wanted to see what our previous discussions were, right?

Speaker 9 (15:20–15:30)

Well, I think… Speaking from experience, no matter how strongly I feel about someone dealing with is the owner and it's their decision at the end of the day, what the applicant will do.

Speaker 8 (15:31–15:36)

Scott raised his hand. Yeah. Thank you. Scott, go for it.

Speaker 5 (15:37–15:51)

I was just going to say, we slightly varied from MSBA requirements with the last design too, so I'm not sure we can exactly just take it and reuse it. There's got to be some bringing it up to their standards.

Speaker 7 (15:52–16:20)

Excellent point, but I would say, turning over all of that information, but at least let them understand where you ended off from your educational plan from your, you have a space summary that basically mimics the space based summary. They can tell how many classrooms you wanted to have, how many different world languages, all that sort of stuff where we have lots of conversations with the school department on. they can take that and hit the ground running. You're going to have to do those meetings again.

You're going to have to do your educational planning again, but it may give you a head start on it and you further refine it.

Speaker 2 (16:20–16:53)

The other product I think would be good is from the teachers, the facilities, people, and stuff like that. Having already gone through this visioning and stuff like that already, it's almost like a dress rehearsal for now. The next one that we're doing this, I think before when they were doing it, Who's the name? Mike?

He did a great job, but it was like, there's a lot of coordination, a lot of meetings, a lot of questions. And I think it was hard for people to kind of see where visualize what was being asked to them.

Speaker 8 (16:53–16:59)

And it's probably going to be about 50% chance that it's going to be Mike.

Speaker 6 (16:59–17:07)

Yeah, probably.

Speaker 4 (17:08–17:14)

So yeah, so could we go back to module one?

Speaker 5 (17:23–17:23)

Yep.

Speaker 2 (17:24–19:06)

So, after we get done with that, this is 1, that's that's probably going to take a decent amount of time for us. So it's maintenance documents and enrollment certifications. So the maintenance documents portion of this, and that's what we have Tom here to as part of the committee. they have a survey that they have you go through and basically, you know, document what's installed, what are your maintenance records, stuff like that.

So that I think is our biggest deliverable next. You get 180 days for that. But again, I started talking with Tom. Yeah, I'm pretty confident I went through this because I did a virtual call and it was quick questions and then there was a follow-up.

Visit, we went to every school, there was a lot of information that jumped out. So I think we're good. Yeah, I think they have us documented on. Okay.

So I think they may have done that as part of their. assessment when they were choosing us for this. But I think what they'll probably have us do is formally document all that stuff. So, you know, what I'll be looking for is, like, some of us to kind of volunteer.

You've got enough on your hands, so you use a resource to help us kind of understand everything that's there. But similar, like, the statement of interest we did before, we want to build, like, a little team, you know, over the next couple over the next month, that's ideally my goal. So come May, we have a team set up working with Tom and start inventorying all this stuff that's going to be there.

Speaker 10 (19:06–19:11)

Do we have a template?

Speaker 2 (19:11–19:24)

I believe so. So my hope is that we can get that template. I think it is a template of questions, how it responds. It was a lot of drop-down boxes.

Speaker 4 (19:25–19:35)

So, I mean, I have that, but they were pretty strict about not sending it here. It was a virtual call and then a site visit.

Speaker 2 (19:35–19:57)

They couldn't send that information for us. Yeah, I wasn't involved in that. But I think, I think for us, the hardest lift over the next six months is going to be that documentation there. If it's already done, it'll make me much happier.

Yeah, it seems like it's a web-based application.

Speaker 8 (19:57–19:59)

It's already done. I'd like to apologize.

Speaker 2 (20:00–20:08)

I think there's a little cleaning up, though. So there's a little

Speaker 4 (20:08–20:15)

some more information you can add to there, or even Justin, that I know is down there in the back.

Speaker 2 (20:15–21:57)

It was literally, there didn't even be a lot of time to gather. When I understood the virtual call, I answered all those questions, and then the gentleman came and did the site visit. Almost a completely different set of questions, and it really was a lot like that. So, there's some stuff we can clean up.

Cool. That's good news, I think. And then, you know, the next part is, you know, the final box, which is funding, which we get that checked off and ready to go. So, you know, my goal kind of on this module one is, I know they give us 270 days, but, like, for me, after May 1st, I want to be done in 90 days.

be done, hit the summer, middle of summer, something like that, complete, and go into module two to start teaming in the fall, or at least that's my goal. Advertise for the OPM, advertise, get through the architect. I, like, we got on a rhythm, I think, for that we had them on boarded by December, January, something like that, and then get them going. So, you know, long term kind of planning or projections, like, put our foot on the gas the next couple of months, get as far ahead of us as we can and ideally 90 days after May.

have everything ready, and I want to talk with MSVA to find out when their board meetings are, so we can kind of, you know, aim for getting everything completed before that next board meeting, get on with January and see if we can make that graduation from module one to module two. They've got their board meeting set for 2025 already.

Speaker 8 (21:57–22:18)

Okay. I'll just put those up right now. Send them out at the beginning of the year. Yes, the board meetings are all the dark blue ones.

So I can send this to you by email, but this is also on their website. They just routinely, at the beginning of the year, they go through as the whole committee and basically set the calendar for the year.

Speaker 10 (22:19–22:20)

Every other month?

Speaker 8 (22:21–22:41)

Yeah, and then there's some committees then. And some submissions don't require meeting with the boards. This is really just the invitations from one module to the next. etc.

And then the facilities, subcommittee stuff, that stuff you'll get to in feasibility study.

Speaker 7 (22:44–23:25)

One of them that is never too early to start thinking about is EdPlan. MSB is really big on the educational plan, and the building you build needs to kind of fit with your EdPlan. So just thinking about getting any documentation from the school department you might need to gather or figure out who the right people to involve in that process is, it takes a while to do. And oftentimes during the school year, it becomes much more difficult to engage people to do it.

So the earlier you just kind of start thinking about it, the better off you're going to be. And in our file share, there are some examples there. If anyone's curious as to what an MSBA ed plan looks like, we've put through some examples from like four or five different projects up there. So feel free to go through there and take a look.

Speaker 2 (23:29–23:38)

Any other questions about module one or MSBA kind of marching orders for the next six months?

Speaker 10 (23:38–23:43)

Just because the plan, that's the educational profile.

Speaker 7 (23:43–24:15)

No, no, it'll be for the planning of the new building. So, yeah, when you're looking at your spaces, we want to make, you have to make sure that whatever you put in your plan aligns the spaces. And it's just 1 of those things that once once you get into it, it's people don't realize how much work it is to kind of drop that document up. So.

just getting your, how the school teaches and how they plan to teach. And if you don't have that already written down and documented, it would be a good time to start doing that. And then you can, it'll be modified for whatever project you're going to move into.

Speaker 4 (24:16–24:20)

You know, I'm pretty sure you're saying that you think it would be a fast architect.

Speaker 7 (24:20–24:29)

Could we create that kind of document? I think bits and pieces of it, but not, I don't think to a level that the MSBA would, it would be acceptable for that. Right.

Speaker 2 (24:39–26:38)

Look good to move on next agenda item. All right, moving on. Um, agenda item number 5 discussion statement of interest colleague, the lover Tucker and Pierce middle school. So, as you guys know, we submitted a statement of interest only for the Cunningham because, you know, essentially told us.

you can only submit on one school, submit for, you know, the worst case one. So we did it for Cunningham. So after we've been accepted, there was, you know, the option for us, they became aware that, you know, a middle school is an option we wanted to look at. And my understanding was they wanted us to, any of the other affected schools, submit statement of interest for those, essentially so they're on record that, you know, we're going to be doing work in these other schools.

So I think it's, My read on it, it's not as deep as we would need to go for the previous statement of interest of how, Mark, you can testify to this of how long and deep everything was on there. But I think what we need to do, and I was nervous because I thought this was due this April. It's actually due next April, so we've got some time on it. But we're probably going to have to submit statements of interest for any If we do the middle schools, an option, it touches all the other schools.

So we'll have to develop a statement of interest for each of those other schools again. So MSBA just has it on a record statement of interest for those other schools. Not that those schools would be accepted or anything like that, but I think it's just an internal paperwork thing. So Peter got that email from them.

Can you copy it on that one? So that's just another one on our radar over the next kind of year to start pulling some of that paperwork and stuff together for it. So open it up, see if there's any questions or anything like that. There was, I don't think we're not submitting it to get accepted.

So we're submitting that stuff essentially for record of those other schools that we might be touching them. Yeah.

Speaker 4 (26:39–26:48)

And I know we're not touching this school, but this is sort of creating a campus here and it's adjacent to this school or what's happening.

Speaker 2 (26:48–27:39)

So I don't know. Yeah, to do a heavy rebuilding. This is the discussion I want to have with MSBA to find out exactly, you know, Get them to understand what our program would be if we do the middle school and. Based on that program, what are their requirements?

I think they initially they just rattled off. They wanted piercing and I don't think they realize we're going to touch the others. So, just to protect us from the agenda, I listed everything else, but knowing we've got a year to do this and we're going to start engaging with MSBA after May, we're going to have a direct project manager with them. So, these are the type of questions that were coming up for that that we can present to them.

So, as you know, over the next You know, 6 months or something like that. You'll start hearing us talking about the same interest again, just sort of raising.

Speaker 9 (27:42–27:47)

So, any questions, anything else.

Speaker 2 (27:48–28:41)

All right, agenda item number six, discuss, close out, OPM contract for a non-MSBA school project. So our friends at TMA, this is our last meeting with them. So you guys have done a great job. Appreciate everything.

Thank you. I'm not looking forward to taking minutes again. We'll suffer through it. Suppose I can volunteer as a time resident to take minutes.

But yeah, I think for the next. So, essentially, with this, we've got our final invoices for again, those were submitted as part of the packets and stuff like that. So. It's going to get these guys paid.

You guys are way under budget, from what I understand.

Speaker 8 (28:41–29:38)

Yes, so I have a budget update. So this budget that I shared in the packet is updated for the two invoices that are included here, the January and February, which are the only two that we haven't processed through this SPC. But overall, more or less shows that we filled to date with all these invoices, about 66 grand out of the currently contracted 160. So that gives us in our contracted amount, but 93 grand that we just wouldn't be billing because we were anticipating, you know, going to all the public forums, going to, you know, presentations and all that stuff.

So we'd be expected to be ramping up as we were going towards a vote, but that was not happening. This is what is going to end up being returned unspent from that original bucket that you guys had. And now you guys are shifting to the MSBA feasibility set.

Speaker 4 (29:38–29:52)

Any questions? Thank you.

Speaker 7 (29:53–29:55)

Bittersweet, but we'll be back in front of you.

Speaker 2 (29:57–30:04)

Same proposal, same everything. We'll see what happens. All right. So, essentially with that, we just need a motion to approve.

Speaker 10 (30:06–30:13)

I'll make a motion to approve the invoices. Any discussion?

Speaker 2 (30:14–30:19)

Hearing none. So, roll call vote. Glenn Hoffman? Yes.

Mark Lawrence?

Speaker 10 (30:19–30:19)

Yes.

Speaker 2 (30:20–30:22)

Paco Alonzo? Yes. Jonathan Hain?

Speaker 10 (30:22–30:22)

Yes.

Speaker 2 (30:23–31:35)

Tim Lombard? Yes. Scott Tereshek? Yes.

And myself, yes. The final, second to final agenda item is future meeting dates. So I figure we're kind of Going at a slow pace right now is good, but I'd probably like to do this, you know, one meeting next month at some point just to check in. And then I think once we get into MSBA and stuff like that, we might go back to more of a a rhythm or a cadence that we're going for.

I don't think we have to go every two weeks, right? Originally when SPC was formed, we were going like every three weeks. But, you know, we can talk about that at the next meeting. But I think for us, you know, if we aim for this is The problem with April is school vacation week.

On the 28th, I'm actually, I turned 50 on the 28th, so I won't be here for that. If we wanted to… Yeah, what is it?

Speaker 10 (31:35–31:36)

It could be.

Speaker 4 (31:36–31:39)

It could be.

Speaker 2 (31:39–31:41)

In May?

Speaker 4 (31:41–31:47)

Yeah. All right. So we're in command, right? Yeah, I think so.

Speaker 2 (31:50–31:58)

So I think for this, you know, if everyone's fine with it, I'm fine with it. We wait until after. So when is town meeting?

Speaker 10 (31:59–32:03)

Town meeting is the 5th and 8th.

Speaker 4 (32:04–32:28)

Yeah, that was because of the festival. So I don't foresee that in the event. So just a heads up, the 17th, the two weeks I'm up, the last two weeks in May I'm not up. Okay, that's 12.

Speaker 2 (32:28–32:38)

Well, where are we going? Blackwell Island. There we go. I'm going to be fishing on the 12th.

We can't please everybody.

Speaker 9 (32:38–32:47)

I'm just trying to. I'm trying every time. Smoke is actually out of season.

Speaker 2 (32:47–32:59)

I can't really get the smoke on that. All right. So May 12th. May 12th.

I'm good. I know you're not good.

Speaker 4 (33:00–33:05)

You can call a lot of shots. Well, we were on that.

Speaker 7 (33:06–33:13)

So good. I'm not going to be worried when I'm there. I am going to be, but I have to say goodbye.

Speaker 8 (33:14–33:21)

Scott, are you good for the 12th?

Speaker 2 (33:21–33:51)

Sorry about that. Yeah, that's fine with me. Cool. So future meeting date, 12.

Last thing on the agenda item is adjournment. So I'll entertain a motion to adjourn. All right. And then roll call vote just to keep it normal.

Glenn Hoffman. Yes. Mark Loring. Yes.

Mack Orban.

Speaker 3 (33:51–33:51)

Yes.

Speaker 2 (33:51–33:52)

John Cohane.

Speaker 3 (33:52–33:53)

Yes.

Speaker 2 (33:53–33:57)

Tim Lombard. Yes. Scott Tereshak. Yes.

John O'Rourke.

Speaker 1 (33:57–34:00)

Yes. All right. Thank you very much. Have a good night.