Board: School Building Committee

Date: 2026-09-14


Transcript

Auto-generated; may contain errors.

Speaker 1 (00:19–00:21)

Let's do it. All right, good evening.

Speaker 2 (00:21–00:41)

I'll call to order the Town of Milton School Building Committee. It's now 7.02 p.m. on September 14th. As we typically do, I'll just take a kind of roll call vote, roll call attendance of the people that are here.

I'll just start with folks online, Tim Lombard.

Speaker 3 (00:43–00:43)

Present.

Speaker 2 (00:44–02:00)

John Phelan. Present. In the room, Bob Mayhew. Present.

Peter Obersheimer. Here. Scott Tereshek. Present.

Nathan Hutto. Present. Glenn Hoffman. Here.

And Sean O'Rourke here. Second thing on our agenda, as always, is citizen speak. We ask, we reserve the first 15 minutes of each meeting for any citizen that does want to speak. If you're online, please just raise your hand and we'll call on you.

And then we ask that you state your name and address for the record. And seeing nobody in the room, and only one extra person online, so we'll, Go now to agenda item number three, which is discussion approval of meeting minutes. So in your packets, you guys had received the meeting minutes that PMA has produced for August 3rd and August 24th. I'm still delinquent on the July minutes, so I'll be working on them for our next meeting.

So for those, I'll just pause to see if there's any commentary on August 3rd or August 24th.

Speaker 4 (02:01–02:12)

I got your, Peter, your note earlier today about the one sentence. I'm happy to explain it. I can pull it up on the screen.

Speaker 5 (02:15–02:59)

While Seamus pulls it up, I just propose one edit to the minutes that I thought reflected our conversation. It was in the topic of like laboratory action items, and it was on who may look, it may not matter, because we were just speculating like who would own action items at the time, but I think I brought up operating cost analysis, and I thought at the meeting, Sean, you made clear that would probably not be the province of the school building committee, so I just proposed editing that to clarify, you know, that that might be, School committee not school building committee. I proposed. Yeah, clear language in that, but.

Speaker 2 (02:59–03:39)

Sorry, Nathan, not trying to put that it was just a. Yeah, no, I agree. I mean, the operating costs associated with the salaries and stuff like that. We're not privy to that end of it.

So I would agree to it and just see if anybody has any. Objections to the edit. So with that edit, just see if there's any other commentary or questions on the minutes for August 3rd or August 24th. Entertain any motion?

Speaker 6 (03:41–03:48)

I'll make a motion to approve the meeting minutes for August 3rd and August 24th of the school building committee.

Speaker 2 (03:52–04:02)

Any further discussion? Hearing none, we'll go to a roll call vote starting with folks online. Tim Lombard?

Speaker 3 (04:04–04:05)

Yes, I approve.

Speaker 2 (04:06–04:13)

Okay. Mark C just joined. Just give me a heads up. We're approving minutes from August 3rd and August 24th.

Speaker 7 (04:13–04:15)

Yes, I vote to approve.

Speaker 2 (04:16–05:09)

Okay, thanks, Mark. And then in the room, Peter Obersheimer. Yes. Scott Tereshek.

Yes. Nathan Hutto. Yes. Glenn Hoffman.

Yes. And myself, Sean O'Rourke. Yes. Item going specifically off the agenda is a little off, so we'll just jump right.

Item four was new business, which didn't have anything. Item five. Item 5, old business. All right, hold on.

Let's go to item 4, new business. It's below item 5 on the agenda. Sorry about that. So new business, project approach discussion.

Is this something you guys wanted to talk about?

Speaker 4 (05:09–05:19)

This was related to the elaborate funding and how we would approach that. Okay. Leading to the discussion about the articles that are needed.

Speaker 2 (05:19–09:00)

Okay. So. All right, so for the project approach. So, as if you're not aware, you should make you aware now the town and what I'm going to try to do is kind of summarize right now what where I see the town is at with this.

call it new project at Labor-Ray. And I'll pause after I'm done and let Mark or Peter kind of fill in sections that I might have missed from their perspective on the school committee and the select board. But essentially, the Labor-Ray campus, the offer to purchase that was accepted by Labor-Ray for $11.75 million. So, what that does right now is, for the school building committee, we've been working essentially over the summer to develop a program to see what could fit at Lab Array, and that provided input from school committee that gave initially a certain number of options, again, to theoretically look at what could fit at Lab Array, and then what we did is took that prescribed option, which was a pre-KK, and contracted with Architects DLR Architecture to develop a cost estimate that could then be inputted into essentially analysis to make a decision on whether Lavaray wouldn't work for a good purchase.

I do not believe that was an intention to say this is exactly what is prescribed going to Lab Array. As we discussed at school committee or when I attended school committee presenting on this, you know, Lab Array, this was an option that we're looking at and that there could be other options that we look at. The key thing I think that we need to talk about here, too, is with LabArray, under the MSBA program that we have right now, we have a, I call it an umbrella of options that we're only allowed to look at, which is a K-5 school for 495 kids plus preschool, or a middle school, grades 7th and 8th, with an enrollment of 660, again, with preschool. It does not include a pre-KK.

So, where I think we're at right now, or what's being asked of us is the LabArray site, we've done an initial cost analysis and initial design, albeit over the summer, over the course of approximately two to three weeks of design work. with a cost estimate, and I think what's going to be asked of us is to take that analysis and try to do additional work to it, to kind of pull it up to where the previous work we did at Gout Road is, to allow the school committee and select board a kind of better analysis or more comparable, even review of it. So, with that, we also have an article, which is Item B, Article 7, which is a funding article that's there to provide funding outside of MSBA for us to hire a separate architect and OPM to, again, study this option, take a little bit further. So, I'm going to pause at that point now.

Pete, I'll ask you or Mark to kind of weigh in on any gaps I missed or, you know, feel free to provide your overview of it.

Speaker 8 (09:08–09:11)

We'll let Mark go online. Go ahead, Mark.

Speaker 7 (09:12–10:18)

Yeah, no, I think that was a good recap, Sean, of just what the school committee is discussing. And thus far, the school committee really has just voted on selecting a preliminary program to study because we had to pick something. As you all know, within the architectural scope, they can only study kind of one design. I appreciate the work of the superintendent and his team to help us kind of over a course of a couple meetings, figure out, you know, what would be an appropriate thing to study, but it still was a very quick process.

it was really just designed to select something to figure out the feasibility of the sites. Could it work for really anything of substantial use for a school project in order to inform the select board's purchasing decision? And that's really all the school committee at this point has. voted on and approved.

We do expect to have kind of further discussion at our meeting on Wednesday and potentially further discussion before the warrant, I'm sorry, before town meeting on the warrant articles, but that's all we've decided at this point.

Speaker 5 (10:19–13:01)

I'll just add procedurally where the acquisition is at is that, as Sean noted, the offer was accepted on the property. The P&S is not finalized. for the acquisition to go through, it would need to go through, pass a town meeting vote in October of two thirds. And then after that, likely a December town wide, that exclusion vote to approve the funding for the acquisition.

So that's sort of the timetable for town wide approvals for the acquisition. Um, our chair of the select board, you know. Provided some remarks at our last meeting around sort of the theory behind the acquisition highlighting 2 points. 1.

you know belief that it's it's a unique opportunity for almost five acres to become available in this town and irrespective of use it's you know seen as a valuable opportunity and secondly you know the possibility that you know it could be you know a school location subject, you know, while noting the analysis done to date has only been preliminary. There was some talk at the select board meeting for, you know, further study up of LabRae to compare LabRae versus Guile in more detail, engaging the community. At our last meeting, a work group was, I think, identified with select board, school building committee, school committee representation to start to think about what that roadmap could look like to build out a plan to develop further analysis and compare the options. I'm not in the work group.

the specifics of it. That's kind of the key thing. So that's a little bit of context for, you know, I think what leads into this meeting, where, you know, just as this continues to evolve, I think the inputs from the different committees that touch on this is very much welcomed.

Speaker 2 (13:03–16:18)

So one other kind of update, too. So myself, Town Administrator Nick Milano, and I believe Superintendent Phelan are having a call with MSBA on Friday to kind of layer in this with them. And talk with Nick today, essentially what we've got, and this will help give a little context for kind of where we're going. And these all kind of play into each other.

The first would be, as I mentioned, under the MSBA umbrella that we have, we have two enrollment options that we can look at for a new facility. And what we'd like to do is ask them of adding a third enrollment there for pre-KK. And what would that mean in regards to the overall timeline? Do we have to do that?

If we make that decision now, how far back does that put us back to in our current timeline that we're doing? Along with that is understanding what the pre-KK reimbursement will be as part of that. So as I understand it, the pre-KK option may be a little unique So, we want to truly understand what that reimbursement would look like if we chose to do it, because I think that will play into the overall decision. Do we go with MSBA for this option?

And then the third, what we're trying to do, too, is If we're not allowed to – if we look at that timeline for – if we went with MSVA for the pre-KK option and it set us back too far, one of the things we're looking to do is leverage the team that we have now with PMA Consultants and the new architect that we're going to bring on next month. What we like to try to do is layer this analysis into them so we're not hiring a separate OPM, a separate architect there, and ideally see if we can segment out on their invoices the charges to do this. And that way it basically makes it, it alleviates us from having to go out, procure new OPMs, a new architect, and then basically give us a better timeline in what we could do. is part of the work initially with MSVA, keep everything on the same timeline.

So, the work we do at Gout Road to progress that in parallel with the work we'd have to do with library would all fall under one design team. And then the last one is, if they don't allow us to do that, what is, you know, if we want to go out and procure on our own a separate OPM and a separate designer, what does that, you know, what does that do with our MSBA process right now and kind of get some feedback from them on that. So, those are essentially four additional options we're going to be talking with MSBA about on Friday. So, not going to try to be a mind reader to tell you what I think they're going to say, but I just want to let you guys know that's their, you know, the outcome of that meeting.

We'll follow up on our next meetings to

Speaker 9 (16:18–16:23)

Is there any precedents for this, Sean, that we know of? Or maybe that's a better question for our audience.

Speaker 2 (16:23–16:25)

I would defer to our owners.

Speaker 9 (16:25–16:26)

Precedents for what portion of it?

Speaker 2 (16:26–16:35)

Precedents for what we're trying to do, what do we got? You've got to be specific, Glenn. You've got to be specific, because there's a lot of stuff on here.

Speaker 10 (16:35–17:08)

So I don't know of any other projects where they've simultaneously, through an MSBA process and a non-MSBA process, looked at two different options. I do know, as Sean said, that if you added separate enrollment, they typically make you go back to their enrollment period and go through the enrollment study again, and then they will certify a new enrollment for, or maybe they won't, but they'll study the pre-K option. And so I think, as Sean said, they're waiting to see how long that would take to get you back in, and you would likely be starting over, and you would go-

Speaker 9 (17:09–17:10)

political spectrum, right?

Speaker 10 (17:10–17:58)

Well, they just haven't studied it. It wasn't part of the invitation. It wasn't part of the program. So it's not that they disagreed that we would need it.

It's just that it wasn't part of the original program. So typically then, you'd basically be starting back there and going through that process again, then re-advertising for an OPM, and then re-advertising for a designer with the added enrollment options. The other thing that Sean talked about was the standalone pre-K, kindergarten, early education center. I know they did one recently, and I reached out to the architect there just to kind of get a sense of what was eligible and what not.

But on Friday, they're going to actually ask the MSBA the same question to see if all of that building is eligible and how it shakes out. Because that may make a difference on whether or not it's even worth pursuing through an MSBA program or just pursuing on the side.

Speaker 6 (18:01–18:17)

When you say go back to the beginning, But your soft prediction was or your experience was that if we try to add a early childhood element to this, that the tendency may be to have us go back to the beginning. Does that mean?

Speaker 10 (18:19–18:53)

Restart our application and get in line with everybody else I think you know starting after they've invited you in when then they invited you in to do the enrollment study Which I think you got invited in December and they started that and went some may or something so that at that point you have to be back on their schedule to do an enrollment study and So the question is when could you do that and how long would it take and then you have to go through the OPM? selection again and then So the risk is not losing our seat in the MSBA program, it's just going back to, it's going back. Historically, that's what we've heard is that it's starting over in the enrollment period, not starting over and reapplying for invitation. Got it.

Speaker 2 (18:53–19:53)

Okay. To be clear, the enrollment period started last May. So not May 2026, but May 2025. What does that mean?

So when you're looking at a timeline for that, I don't think it would take us as long. So if you remember, we started in May 1st, 2025 with Module 1, which gave us a 270-day window. And we finished it fairly quickly, but still it took until October of last year before we graduated essentially in Module 2, and then started working through hiring an OPM and now an architect. So, you know, that turn back time, you know, when you're thinking about it from today, I don't think it will push us as far back as, you know, what if you did the number of days or whatever.

Yeah, whatever it is, I think it would be about a year. Because we already have the front end stuff already taken care of for module one, we can just resubmit that again. But if you're just trying to get an idea of what that delay would look like, my guess is about a year.

Speaker 6 (19:57–20:48)

John, do you mind if I ask you just a couple more questions? I know you want to hear from people, but just to make sure I understand. So you talked about some of these scenarios having us have the same OPM and the same designer for both schools. which I understand the logic.

I thought I had heard discussion before that getting a designer that can do both schools, like say it's a middle school and an early childhood school could be tough, but maybe you feel like there's enough overlap. Do you see that as an option in all of these multiple paths, or does that only work in some of these, like MSBA, or a mix, or a hybrid, or whatever?

Speaker 2 (20:49–22:46)

It would only work in the MSBA. It would only work in the MSBA. Because essentially, I think the bigger question that will come up in the coming months is if It's, do we want to stay with MSBA, or do we want to go on our own, if Laboret is that decision? And where that's at right now, I think a lot will be determined after Friday's meeting from the feedback we're getting now.

And like I said, I don't want to try to guess at what potentially MSBA wants will say on some of this stuff. But for your question of, you know, the paths that we're looking at, what we're trying to do is lay out a path that we can work under our MSBA umbrella and still work with Laborate and Galroad at the same time, which I think is the most efficient. And so with that, we could operate under the same budget that we have right now and keep that essentially all under one umbrella. If we're not allowed to do that, and they say, okay, you can layer it in, but you're going to be delayed by a year, that's our next decision.

Okay, do we want to delay this project a year, come back with all three options and restart again? And then I'm assuming we can keep our OPM that we have here, or do we have to go out and re-procure? I don't know yet. But then the last option is if we don't want to wait for that delay, then is it okay, Mr.

MSBA, if we kind of go out and procure our own guys that we may want to look at this on our own and kind of go on our own paths? So those are kind of the three avenues I think we're looking at right now. And like I said, it's complicated because there's so many different balls in here that we're looking at right now. But to simplify it, those are kind of the three lanes.

Speaker 10 (22:47–23:14)

As far as the designer capabilities, all of these options have a pre-K component to them. So all the designers that have submitted on it, they can design any type of school from pre-K up to high school. And they all have it on their resume. So I think the capability is there of all four of these.

I wouldn't worry about that. Because they're going to have to do it. Even with the middle school, there's a pre-K option there. So they're going to have to study and program a pre-K option.

And then the decision is made whether or not to include that. But it is part of the program.

Speaker 6 (23:16–24:42)

You said you have more. Go for it. Last one. Go for it.

So there's multiple paths, but let's just dichotomize it. One is… We have one option is we explore the current program, I'll just call it Guile Road, explore the Guile Road program under MSBA, and then simultaneously through the separate funding mechanism, explore the Labire site, not under MSBA. That's one option.

The second option is we merge these two things under MSBA and we explore them simultaneously. My assumption is that, and this is, I guess I just want you to check this, that the latter, like a merged set of projects under MSBA is simpler to execute. The process is probably very different from the former process where we would be evaluating things simultaneously all the way down to the end potentially, whereas a joint program we might figure out the program we want, look at enrollment, then choose a site, then design a school for that site. Whereas the former process has us doing all of that stuff for two schools and two sites.

Is that accurate?

Speaker 2 (24:43–27:20)

I got a little distracted and I'll explain why. Because when you're talking under the current MSBA one, I'll just give you kind of where my mind was going when you're saying that. With the current MSBA umbrella of enrollments, grades 7th and 8th or K-5, We can also look at that as Laboret. So it's still kind of merged between the two.

It's only the pre-KK option that we have to go back and kind of redo some of this stuff. So I just want to be clear just for everybody of like if we decide to just stick with MSBA and proceed with the enrollment options that we have now, we can still look at Laboret as part of that. When you were talking merging it, I just want to make sure people don't know right now it's under MSBA. We still have two options we can look at.

It's just that pre-KK option is not currently covered under there. So, I think the question you're asking is by merging that, say we include delay year, include pre-KK under that option, that's a more efficient option to study rather than the other one. I don't know. So I'll just speak off the top of my head.

If we were to join it under MSBA and delay a year, right? We would then be starting back up or kind of getting to where we are right now, onboarding an architect a year from now, right? Rough number. And then we would start doing the design, re-looking at this stuff and coming to some conclusion under those three options at some point in the future after a year to say we want to do guile or we want to do lab array out of those options that we're looking at.

If we went at parallel path right now, and we went MSBA, we didn't include Lab Array Pre-K in there, and we hired a separate team and worked in parallel, we'd come to that decision sooner. So while it may not be as efficient, call it from our time, because if we go parallel paths and we have two things, it's a lot of work. But it all depends on when you want to come to that decision, a year from now or a year plus. whenever it takes once we get back to where we are now with those three options and then build it out.

So, I don't know. I wouldn't be able to guess on a time on that, but that's, you know, just from you presenting that, that's kind of my reaction to it.

Speaker 11 (27:20–27:36)

Okay. That's helpful. Can I ask one question related to it? Sure.

What's the timeline right now for developing the options that MSBA has asked for and making a decision on those for the Guile Road, forgetting about Monterey? John, you got a schedule?

Speaker 10 (27:37–29:42)

Yeah. Yeah. Sure. Sure.

And I can pull it up too. Yeah. I have it here. The industry process works is they have the initial one is the PDP preliminary design program.

That's 1 where you're going to look at all the sites available and you're going to look at all the options basically on all the sites. So that would be Cunningham, Collicott, putting an addition on there. I think it's unlikely they would make you study knocking down that complex and building that brand new for 1400. I can't, I can't see there's any appetite for that, but then.

Guy road would be a new elementary school on that site and a new middle school on that site with or without. pre-K. If library is purchased and that becomes part of the equation, then I believe they would have us do a middle school on that site and a elementary school with or without pre-K as well as part of the study. So that would be finishing up sometime at the end of April of the 2027.

And then from all of those options, the committee will select a handful of them, which they want to further study into the MSBA's PSR, Preferred Schematic Response. And through that, it's about another six month process where you're going to study, further study all those options, refine them, do estimates on them. And at the end of that, you're going to pick which option you want to proceed with into schematic design. So you present that to the MSBA at their facilities assessment subcommittee meeting.

They agree and they let you go into schematic design. You'll take another six months or so furthering that design and then bring it back to the MSBA where they'll approve your final grant. So it's about a year and a half from the time that architects contracted on board to the time you go into the MSBA with your schematic design. But it's about a year from the time the architects hire you to you have what your design is going to be that you're going to really do some heavy detail design to get to refine that.

And then if you had another option with the pre-K, K option, it would be kind of the same thing except another option on the Guile Road site and at the library site. You add a freestanding pre-K kindergarten and potentially an addition on Cunningham with a, you know, whatever the enrollment is of a pre-K, K option as well.

Speaker 11 (29:42–30:03)

So just to get back, because that was a lot of information. With what MSBA has given us right now, it sounds like April of next year is when we have the options prepared for them to take a first look at, and then there's a six-month period to make a decision.

Speaker 10 (30:04–30:24)

October or December? It's October 2027 right now. It's a little over a year from today. Okay, so that's that's what we're dealing with through time with the caveat This is generally a schedule that we put together and then we still have to hire the designers name would have to agree to a schedule But we're fairly confident that this is about the correct timeline for an MSBA project.

Okay?

Speaker 9 (30:26–30:38)

Consider that's another year price escalation, which is likely if you delayed yet, we delay it another year If it's only a year If it's only a year

Speaker 11 (30:38–30:45)

That's an assumption that we'd be yeah, let's turn this all around the year everything else seems to take a lot longer.

Speaker 9 (30:46–31:14)

So I Would personally I would think one year would be the minimum Sean if you give me if you already answered this if we did do the pre KK not under MSBA We could still use the same architect in the same That's what we're gonna ask on That's another cost. In my mind, that's another cost savings is not having to use two separate architects and two separate…

Speaker 2 (31:16–31:40)

Just thinking about that. So if we were to continue, again, PMA is our onus project manager right now under our MSBA program. We're going to talk about the architects that have submitted on this coming up. But by October 20th, by the end of October, we're going to have an architect.

So your question was, if we decided to leave MSBA, could we still retain those people?

Speaker 9 (31:52–31:55)

I think you could, but it's just a question you ask.

Speaker 2 (31:55–32:16)

Yeah, I don't see why—we'd have to go through separate procurement there. So similar, we're going to have to—again, that's—I'll call it option four for those things that we're talking to them about. Yeah, depending on how procurement would work out, how we select them. Potentially, yes.

Speaker 10 (32:17–32:31)

I don't think you could run both projects at the same time without procuring. You could do any one project of that, I think, on the singular procurement. But if you're going to do two major projects, I think that would probably require you to go out and do another OPM and designer selection for that separate project.

Speaker 2 (32:31–32:40)

It's just too much scope to add to a… No, I think what Glenn was saying is with that separate procurement that you're doing. Essentially, if you guys submitted on it separately… Oh, yeah.

Speaker 10 (32:40–32:43)

I don't mean to preclude you from hiring, but you would have to do that separate procurement.

Speaker 2 (32:49–34:56)

Just seeing if anybody online had anything yet. I don't see any hands raised. So the other part too, just for people's clarity too, Article 7, which was the funding article, was there basically in the hopes that – we talked about for our committee, you know, for us, we like to react kind of quickly and kind of be proactive. So, the intention of that article was to have funding available that if the decision was to go full-on to Laboré, that we had funding there, we wouldn't have to wait for a future town meeting.

So, just kind of bringing that up for everybody to understand kind of the origin of where that article came from. And then, you know, the hopes is, you know, with that direction, we could just get going as quickly as possible. So I think, you know, with the LabArray, you know, discussion and the overall intent of Article 7, which is our funding article, For me, it's good to hear from each of you where we stand. I think part of it is with this meeting with MSVA coming up Friday.

I think we're going to have more follow-up discussion because I think We might have more clarity on kind of which direction we're going kind of after that meeting. We get, you know, feedback from MSBA on essentially those four options that we talked about, too. But I'll just see if anybody else has anything else they want to talk about in regards or questions for Laboreo, the funding article. If not, we can move on.

Speaker 11 (34:56–36:28)

Yes. I was asking the questions on timing because I wanted to figure out, you know, if we're going to, I guess the questions for me are elaborate are, you know, on the surface right now, it doesn't look like it meets the needs that we were set out to solve seven years ago. Um, and. So to me, it's like a short-term fix.

And then a couple of years later, we're back here having the same discussions we did seven years ago. Not that it's a bad idea, but I just don't think it solves all the problems that we set out to do. So I'm all for studying it further, but I don't want it to impact, in my opinion, the Guile Road project. So to me, in my head, it's, OK, if we're going to agree to vote for Article 7 to fund studying Laboré, I would like to put some time limits on that.

it's got to be done before any of the options are completed for Guile Road so that all those decisions can be made before we submit to MSBA. That would be one thought on it. And that way we're never slowing down that process, but we're leaving our options open. And I guess, would that funding only be for a school or would it be for other

Speaker 5 (36:31–36:44)

possible uses of that property? Right now, the article is written to only be for study of a school. Okay.

Speaker 11 (36:44–37:34)

I don't have it in front of me. So if we're just looking at a school, then I guess I would I guess what was done already was pretty good. And so I'm sure other options can be developed to make it bigger or change the arrangements or whatever. Grades go in there, but I don't see a drastic change from what was already done, would be my gut feeling on it.

So I guess I'd be cautious of how much we spend going through a whole bunch of lab array options, when in the back of my mind, it still doesn't solve the problem we started out trying to solve seven years ago.

Speaker 2 (37:36–42:00)

And just some comments on that too. Article 7, we put in for $1.2 million, and the intention of that was, I think, the decision, or the anticipation of the decision was going to be binary. We're 100 percent going Lab Array or 100 percent going with Guile. And if we were going Lab Array, we needed funding to take it to a full design, basically, following the MSBA process.

So, that's why the allocation was so much larger. I think the ask now is a lot less. Similar to what we did before, just to your point of how much we want to spend on this. If it's a year's worth of work and we're trying to do a parallel path until say October next year, spend there.

So that's another thing that we should talk about at some point. Maybe not tonight because we're just starting with it. But what is that right number? The previous design we did at Gout Road, we spent $450,000.

And you saw the work we got out of it. It was – yeah. And I think that's what we're trying to do is take the overall program that we did at Laboret. And again, as Mark said, and I was talking about, it was initial test fit to see what could fit there.

But when I saw the amount of work that went into Gow Road, the visioning sessions that were done, there was an educational planner that came in and met with the district. There was a lot of front-end work that fit into that design, and nothing against what we did so far. The architects met with the superintendent, the director of preschool, and had an in-depth discussion with them. But I just think more work needs to be done to just ensure the program that we're building out there meets everything they want to do, and maybe it might get smaller.

But until that's done, I think that's the ask that's coming, or at least what I'm hearing from select board and school committee. is to get that back up to the same point. It's a long-winded way of saying, I don't think we need 1.2 million. My guess is it's going to be somewhat similar to what we spent before.

The other part that you brought up too is You know, the nature of elected boards is you guys rotate. You know what I mean? So every couple of years, everybody's up for reelection. And so the time that people have been on some of these boards, for things that have happened prior to they were elected.

I think it's tough. The one nice thing about this committee is the five of us that have been appointed in Glenn have been here since the beginning. So for us, when we're talking about some of this stuff, for us it seems repetitive sometimes because we've gone through it maybe five or six times with different people. So what I try to do too is pull up the origin, like where this decision was made, because I heard it select board from the chair of, you know, how do we come to a middle school?

We looked at pre-KK and like, how is this decision made? So, what I'd like to do, Peter, is forward you the school committee meeting from, it's March 17, 2022. And that gives the school committee at the time, their points and their recommendation for this. And it talks to the superintendent, it talks to basically everybody that took a vote at that time.

Because that vote that's there is essentially the last direction we've got on this project. So for me, I haven't heard anything since March 17, 2022 that we're going in any different direction. And that's for us been our marching orders. And, you know, Nathan, Mark, you know, from a similar end, if it's okay, I'll forward it to you guys at school committee.

Because it just, I think it answers a lot of the questions of how did we get here? You know, where did all this come from? And it'll be helpful. So, you know, if there's no objections, I'll forward those to you guys.

And a couple hands raised. Yep. And Tim. All right, Tim, thank you for being patient.

Speaker 3 (42:01–43:57)

Oh, yeah, no problem. I mean, fortunately, Scott covered a lot of my thoughts, and then the discussion in the room there answered a bunch of my questions. I similarly had questions about what some of the non-school-related uses might be for the Labouret site. I mean, overall, I want to say congratulations to the town, and I am appreciative and supportive of the notion that this is a unique opportunity for the town to acquire this parcel, and I agree about Being excited to be a part of the envisioning discussion for what the school uses might be for that site.

I am I share some of these concerns that using the parcel to accomplish an early childhood education center could fall short of the task that we've been prescribed with. I kind of just sat here, Sean, and my silly back of napkin tells me that we're going to accomplish less than 50% of our task, and we put the town at risk of becoming responsible for upwards of 70% of the cost of a project. that would meaningfully fulfill our original charge and, you know, get us to a pretty complete solution. And I'm, you know, I'm concerned about the timeline too.

I share these concerns. I'm not super optimistic that we would, and I know that this is an upcoming discussion. I'm just not very optimistic that we would get a decision that says we're gonna forego MSBA and pursue an early childhood education center without that funding. So yeah, I guess I'm not saying anything new here.

It may have been if I had got my hand up earlier, but no, I kind of, I'm in step with what's being said in the room, I think.

Speaker 2 (43:58–47:25)

Okay, thanks. Hearing nothing else, anybody right? So, I think what we do, you know, like, like I said, I, you know, the, the acquisition or the acceptance of the offer was new since our last meeting. And, you know, I mean, I just wanted to.

One, get feedback from members of the committee, and I think it's helpful for the other boards and committees to hear your perspectives. But for us, I think after our meeting with MSBA on Friday, there'll be it will, for lack of a better word, fine-tune the discussion next time we have it. Because right now, there's a lot of variables that are out there. And anyone knows me, I like to take variables, change them to constants.

It makes it a lot easier to analyze. So I'll kind of leave that. Item right now for our next meeting so I'm going to close item four and Looking back at the agenda moving up. We're going to old business, which is our MSBA designer submission reviews And I'll just list all of them because I think they're all gonna kind of wrap into each other Design a selection panel meeting update and item C.

We're not talking about which is library update Which is we just covered that pretty much in depth. I So, right now, for the designer selection panel, myself, Glenn Hoffman, and Mark Loring have all been chosen. So, Superintendent Phelan selected me to be his appointee. Glenn Hoffman was selected by the select board, and Mark Loring is representing the school committee, so the three of us.

We'll be working with the MSBA on the designer selection panel. Right now we've received four submissions that are there. Yep. And I believe, and Sean correct me if I go wrong on this, like we'll want.

to hear from the entire committee, just basically a high-level review of their thoughts and stuff like that. What I'll do is I'll forward those submittals to you. The submittals are roughly 80, 90 pages each, roughly. A lot of the upfront stuff as far as reference checks and stuff like that are all being done by our own project manager.

There's a technical approach section to it. I forget exactly which one. But what that does is look at the enrollment options that we have and the sites that we have and says, here's what we have. And there's actually some concept designs that are on there that are pretty unique.

So, you know, it gives, you know, it's nice. The good thing working with architects sometimes are other people, they come up with these different ideas for things that we might have in our head as a concept of like, this is how we're going to do it because we've already seen it at Gout Road earlier. And a couple of them are totally different. So I'll get those over to everybody to start taking a look at, but specifically Mark, Glenn, myself will be diving in much deeper.

And Sean, feel free to chime in on anything I may miss, because this is our first time going through this.

Speaker 10 (47:25–47:59)

It's section 10 is as Sean said that's the section that the architects have I think six pages that they're allowed to Yes, kind of present the project in their vision for the project The rest of it is a lot of forms that they fill out references jobs that you've done in the past which is important There's letters at the beginning of it kind of an intro to the project. So it'll give you a sense of how they see it But if you go into that section 10, that's really where you're gonna see what each design firm feels like this project should be and can be. And so if you're going to spend any time, if you don't have a lot of time and you want to spend it on one section, I would say section 10 is probably going to give you the best feel.

Speaker 4 (47:59–48:09)

And the link that I sent earlier today with the meeting minutes should already have the four submissions in there. So you should already have access to that at least on the committee level.

Speaker 10 (48:10–48:29)

And those are towards the end of the document. So like Jonathan said, they're mostly like 80 pages. They start around like page 65 to 70. So if you scroll down, you'll see the section 10 start and then you'll see some pictures and some some things that are not they don't look like a government sheet that they filled out to submit as part of the process that's where you want to be reading it.

Speaker 6 (48:31–48:36)

What kind of input are you looking for from us, just like general reaction?

Speaker 4 (48:36–48:42)

The general reaction, overall impressions, how you think that their mission fits Milton.

Speaker 10 (48:42–48:58)

Do they read the RFS? Do they understand what the project is? And do they have a good sense of what Milton's looking to do? And then a lot of times, they'll have historic, what they've done in the past.

And do you think some of their past experiences align well with Milton's vision for this new school?

Speaker 6 (49:00–49:28)

And then how should we, so in these proposals, in section 10, I think you said, there's like their vision for what the school could be. How should we interpret that? Should we interpret that as like, this is the perspective the designer will bring, and we should anticipate that this will be what they're driving toward? Or is it just a representation of like, their creativity, for lack of a better word.

Speaker 10 (49:29–49:41)

It could be both, but I think reading through that, you're kind of trying to figure out if that designer and the words that they have on the page and what they're presenting is something that aligns with your values and aligns with the values of the child.

Speaker 6 (49:42–49:47)

So what they're putting on the page, we should take seriously as a representation of their vision?

Speaker 1 (49:48–49:48)

Yes.

Speaker 10 (49:48–50:05)

And certainly go through the rest of, they'll have past project experience, they'll have some other information, but this section particularly is, it's open-ended. So that's why, like, this is what their, this is their presentation to you to say why, you know, this is what our vision is and we hope that you agree with it and hire us to do this project.

Speaker 2 (50:14–51:06)

Any other questions in regards to design a selection panel and just keep an eye on line to folks. We do need our feedback. That's right into our next agenda. So, kind of moving on, we talk about next meeting.

Knowing things are with the discussion we have with library is kind of moving fast towards town meeting. And I think certain boards of committees are kind of looking for input from us and others. What I'd like to try to do is have meeting in 2 weeks on the 28th. I'm away the following week.

So that's. That also gives us time before the designer selection panel to kind of review those submittals over the next two weeks. Is that correct?

Speaker 4 (51:06–51:25)

Because design and selection panels… It would be on the… We have to get all the materials over to them by the 17th, and then that locks us in for the 6th. October 6th would be the designer selection panel.

Yeah. So this meeting would allow us to get feedback from the committee. Yep. And then the DSP members would kind of take all that in.

Speaker 10 (51:26–52:20)

It just as a reminder, there's a designer selection, a panel that's seated by the MSBA. You have 3 seats of that as part of this committee, and they will review with you all 4 of the designers. They'll give their their review. And then at the end of that, they'll be able to take in you rank 3 to 1.

You give a three to the most preferred, two to the second, one to the third, and then they tally those up to try to get a sense of who they're going to shortlist. Oftentimes, they shortlist three. Sometimes, they shortlist two if there's a clear distinction. Rare cases, they shortlist all four.

And then two weeks later, they will bring in whoever gets shortlisted in for formal interviews where they will present to the designer selection panel a more detailed vision for the project. And then at the end of that meeting, The designer selection panel along with your three representatives will vote for the designer and then you start contract negotiation.

Speaker 2 (52:20–53:48)

very similar to what we did. We were in charge of hiring the OPM. We went through a large list of OPMs that were there, subcommittee shortlisted it, and then we brought each OPM in for individual interviews and then picked one from there. Our position on it is diluted with only three of the seats that are there, but that's essentially the process.

One other note on future meetings, and Tim, just reminding you, next Thursday we'll be meeting with the citizen that did the enrollment analysis. So, anybody else, the subcommittee that was formed, Tim Lombard, myself, Kerry Hurley, and Aqua. We've done our review on it, and we just want to sit down with the citizen, hopefully come to a reconciliation on positions on it and stuff like that. So anybody else that would like to sit in on that meeting is welcome to.

But the intention right now is just to have the subcommittee meet with them on the 24th. All right. With that, we've kind of come to the end of our agenda. So I will detain any motion to adjourn unless anybody has anything online that I may have missed with a hand up or anything like that.

Seeing none.

Speaker 6 (53:50–53:51)

I'll make a motion to adjourn.

Speaker 2 (53:52–54:07)

Second. Second. All right, we'll do a roll call vote because we're hybrid online. Mark Lorry?

Yes. Tim Lombard? Yes. In the room, Peter Obersheimer?

Speaker 10 (54:07–54:08)

Yes.

Speaker 2 (54:08–54:14)

Scott Tereshek? Yes. Nathan Hutto? Yes.

Glenn Hoffman? Yes. And Sean O'Rourke.

Speaker 1 (54:15–54:17)

Thank you very much. See you in two weeks.